ADP Marshall, Inc. v. NORESCO, LLC

710 F. Supp. 2d 197, 2010 U.S. Dist. LEXIS 43246, 2010 WL 1753585
CourtDistrict Court, D. Rhode Island
DecidedApril 30, 2010
DocketC.A. 07-129ML
StatusPublished
Cited by9 cases

This text of 710 F. Supp. 2d 197 (ADP Marshall, Inc. v. NORESCO, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ADP Marshall, Inc. v. NORESCO, LLC, 710 F. Supp. 2d 197, 2010 U.S. Dist. LEXIS 43246, 2010 WL 1753585 (D.R.I. 2010).

Opinion

DECISION AND ORDER

MARY M. LISI, Chief Judge.

Plaintiff ADP Marshall, Inc. (“ADPM”), a subsidiary of Fluor NE, Inc., brings this action for breach of contract against defendant Noresco, LLC (“Noresco”) in connection with the construction of a cogeneration facility (the “Facility”) for the Rhode Island Department of Mental Health, Retardation and Hospitals (“MHRH”). ADPM has also raised claims pursuant to a payment bond issued by Noresco’s surety, Lumbermens Mutual Casualty Co. (“Lumbermens”). Both Noresco and Lumbermens have asserted counterclaims against ADPM 1 as well as third-party claims against ADPM’s co-sureties, St. Paul Fire and Marine Insurance Company (“St. Paul”) and Fidelity and Deposit Company of Maryland (“Fidelity”), together with St. Paul, the (“Co-Sureties”). The action was tried by the Court sitting without a jury and the parties have submitted extensive post-trial memoranda. The Court’s Findings of Fact and Conclusions of Law pursuant to Fed.R.Civ.P. 52(a) are set forth below.

BACKGROUND

I. Procedural History

On April 6, 2007, ADPM filed a complaint in this Court against Noresco for breach of contract, book account, unjust enrichment, quantum meruit, and attorney’s fees. ADPM also asserted a bond claim against Lumbermens. ADPM sought payment from Noresco for “unpaid labor, materials and costs” in connection with a construction agreement it had entered with Noresco in April 2002. Based on an approved contract price of $13,643,156 and ADPM’s receipt of payments totaling $12,415,451, ADPM initially sought payment from Noresco in the amount of $1,227,705. 2 Complaint ¶¶ 14-16. In addition, ADPM sought $1,629,222 for what it claimed as uncompensated increases in scope of work. 3 Id. ¶ 17.

Noresco asserted a counterclaim for breach of contract; a claim against ADPM’s payment bond; and a claim for specific performance for the delivery of “as-built” drawings of the completed Facility, certificates of inspection, operational and maintenance manuals, and a valid Certificate of Occupancy. Further, Noresco brought a third-party claim against the Co-Sureties for refusing to indemnify Noresco when ADPM failed to pay its subcontractors.

On April 7, 2009, this Court dismissed several claims which had been withdrawn or rendered moot; in the same order, the Court denied the parties’ cross motions for partial summary judgment. ADP Marshall, Inc. v. Noresco, C.A. No. 07-129ML, Docket No. 107 (D.R.I. April 7, 2009). During the course of discovery, the parties engaged in settlement discussions but were unable to resolve their differences. *201 Before commencement of the trial, both parties presented numerous motions in limine, which the Court took under advisement.

II. The Trial

The Court conducted an eight-day bench trial from September 21 through September 30, 2009. Prior to trial, the parties submitted a Joint Statement of Undisputed Facts (hereinafter cited as “SUF”) that listed 81 statements regarding the case on which all parties agreed. C.A. No. 07-129 ML, Docket No. 127. At the trial, ADPM presented two witnesses as part of its case-in-chief: (1) Edward McNaught (“McNaught”), who was employed by ADPM as project manager on the Project 4 ; and (2) Douglas Coppi (“Coppi”), who testified as an expert on construction scheduling. Noresco presented four witnesses: (1) Wade Carleton (“Carleton”), Y.P. of Construction for Noresco; (2) Theresa McKinnon (“McKinnon”), general counsel for Noresco; (3) Bradford Bright (“Bright”), who testified as an expert on the scope of construction projects and analysis of change orders; and (4) Kenneth Monson (“Monson”), who testified as an expert on construction schedule analysis and delay. The parties elicited testimony from their respective witnesses with reference to more than 230 multi-page exhibits, including construction contracts and attachments; communications between the parties; change order requests with applicable backup information; daily reports; design sketches; and detailed construction plans. In addition to Exhibits 1 through 952, 5 which were admitted by joint consent of the parties, the Court admitted into evidence approximately two dozen disputed exhibits. On the fourth day of trial, ADPM and Noresco submitted a three-tabbed stipulation (the “Deviation Stipulation”), which listed certain change order requests submitted by ADPM that were (1) approved by Noresco but not paid to ADPM; (2) not approved by Noresco and in dispute; or (3) initially claimed by ADPM but withdrawn or reduced in the course of discovery. 6 In addition to listing the various change order requests, the jointly submitted document also describes their payment status. For a majority of requests categorized as “Approved by Noresco but Not Paid to [ADPM],” a note indicates that Noresco paid the Subcontractors directly. Deviation Stipulation, Tab 1. Similarly, of the disputed deviations, a number are noted to have been “Mettled by Noresco directly to subcontractors,” or resulting in “[u]ndisputed credits to Noresco.” Id., Tab 2, p. 2.

At the conclusion of the trial, the parties were requested to submit post trial memoranda for the Court’s consideration. The findings of fact that follow herein are based on the Court’s thorough evaluation of the evidence and its determination of the relevancy and substance of the various witnesses’ testimony.

*202 FACTS

I. The Prime Contract

On September 25, 2000, Noresco entered into the “Howard Center Cogeneration Project Design and Construction Agreement” (the “Prime Contract”) with MHRH to “furnish turnkey construction services to design, permit, build, install, startup, test, and train operators for a cogeneration facility” (the “Facility”) at the Pastore Center in Cranston, Rhode Island (the “Project”). SUF ¶ 1, Ex. 1 p. Noresco 0000379 7 . A cogeneration facility produces steam for heat and electricity for use or sale to a local power grid. See URI Cogeneration Partners, L.P. v. Bd. of Governors for Higher Educ., 915 F.Supp. 1267, 1273 (D.R.I.1996). The Project included the construction of a new cogeneration plant with two electricity generating turbines, two heat recovery boilers, and a stand-alone boiler. The Facility was to be built adjacent to an existing boiler facility which contained older equipment and was, in part, in disrepair. Trial Tr. vol. I, 17:18-18:3, Sept. 21, 2009.

The price for Noresco’s work under the Prime Contract was set at $27,550,919 (the “Guaranteed Maximum Price”), subject to approval of the performed work and authorized changes in the work. Ex. 1 ¶ 6.1. Attached to the Prime Contract as Exhibit I are the technical specifications which define Noresco’s scope of work and include preliminary drawings of the Facility. Ex. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe v. Brown University
210 F. Supp. 3d 310 (D. Rhode Island, 2016)
Axenics, Inc. v. Turner Construction Co.
62 A.3d 754 (Supreme Court of New Hampshire, 2013)
Cappalli v. BJ's Wholesale Club, Inc.
904 F. Supp. 2d 184 (D. Rhode Island, 2012)
Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority
89 A.D.3d 819 (Appellate Division of the Supreme Court of New York, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
710 F. Supp. 2d 197, 2010 U.S. Dist. LEXIS 43246, 2010 WL 1753585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adp-marshall-inc-v-noresco-llc-rid-2010.