Marshall Contractors, Inc. v. Peerless Insurance

827 F. Supp. 91, 1993 U.S. Dist. LEXIS 11746
CourtDistrict Court, D. Rhode Island
DecidedAugust 23, 1993
DocketCiv. A. 92-0042-T
StatusPublished
Cited by24 cases

This text of 827 F. Supp. 91 (Marshall Contractors, Inc. v. Peerless Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshall Contractors, Inc. v. Peerless Insurance, 827 F. Supp. 91, 1993 U.S. Dist. LEXIS 11746 (D.R.I. 1993).

Opinion

MEMORANDUM AND ORDER

TORRES, District Judge.

This is a suit on a performance bond issued by Peerless Insurance Company (“Peerless”) to Marshall Contractors, Inc. (“Marshall”) guaranteeing the performance of one of Marshall’s subcontractors, VT Properties, Inc. (“VT”). It is presently before the Court for consideration of Marshall’s motion for partial summary judgment in the form of a declaration that “Peerless is obligated as a matter of law to pay consequential damages under the performance bond.” That motion is denied for reasons set out below.

FACTS

Marshall is a Rhode Island corporation that was hired as the general contractor to construct housing at the Hurlburt Field Air Force Base in Fort Walton Beach, Florida. Marshall subcontracted certain carpentry, roofing and finish work to VT, a Georgia corporation. Pursuant to the terms of the subcontract, VT obtained a performance bond insuring that its work would be properly completed. The bond, in the amount of $3,478,828.00, was provided by Peerless, a New Hampshire corporation, through its Georgia office.

On November 21, 1991, Marshall declared VT in default and demanded that Peerless complete the work covered by the subcontract. When Peerless failed to make arrangements satisfactory to Marshall, Marshall completed the work itself and brought this suit.

*93 Count I of the complaint alleges that Peerless breached its obligation “to remedy any defaults in VT’s performance, to complete VT’s work in a timely and workmanlike manner, and to otherwise compensate Marshall for damages which it incur[red] as a result of VT’s default.” It seeks “damages including costs expended to complete the contract work, increased overhead and other delay expenses ... additional claims from both the owner and various project subcontractors, and ... other consequential losses.” Count II alleges that Peerless wilfully and in bad faith failed to comply with its obligations under the performance bond and seeks “all resulting damages without limitation by the penal sum of the Bond.”

As already noted, Marshall has moved for partial summary judgment to the effect that, under the performance bond, Peerless is liable for any “consequential” damages sustained by Marshall as a result of VT’s alleged default. Peerless contends that such a claim is not properly the subject of a motion for summary judgment. Moreover, as set. forth in its answer, Peerless asserts that it is not liable for consequential damages occasioned by VT’s default.

DISCUSSION

I. Appropriateness of Partial Summary Judgement

Federal Rule of Civil Procedure 56 allows a party seeking to recover , on a claim, counterclaim or crossclaim, or a party against whom a claim, counterclaim or cross-claim is asserted to move for summary judgement “upon all or any part of thereof.” Fed.R.Civ.P. 56(a) and (b). The rule also expressly provides for an interlocutory summary judgement “on the issue of liability alone although there is a genuine issue as to the amount of damages.” Fed.R.Civ.P. 56(c).

The purpose of partial summary judgment is to expedite litigation and promote judicial economy by resolving, in advance of trial, matters that do not turn on disputed questions of fact. That purpose is not served by using Rule 56 as a vehicle for obtaining rulings on issues that may never have to be addressed. On the contrary, using Rule 56 in that manner could prolong the proceedings and cause judicial resources to.be expended needlessly. 'Furthermore, “partial summary judgments” with respect to questions the existence of which depend upon the resolution of controverted matters would be tantamount to advisory opinions. See e.g., Flast v. Cohen, 392 U.S. 83, 88 S.Ct. 1942, 20 L.Ed.2d 947 (1968) (“The oldest and most consistent thread in the. federal law of justiciability is that federal courts will not give advisory opinions.”)

In this case, Marshall is not entitled to any “judgment” for “consequential” damages because Peerless’ liability under the bond has not yet been determined. Peerless expressly denies that it has breached its obligations under the bond.

In addition, Marshall has failed to establish the precise nature or amount of its “consequential” damages. It merely describes those damages generically as increased overhead, other delay expenses, and other consequential losses. In short, the relief it seeks is so vague that it cannot be the subject of a partial summary “judgment.” Unless and until Marshall prevails on the liability issue and establishes the exact nature and amount of its “consequential” damages, no “judgment” or “partial judgment” can be entered in Marshall’s favor.

The contingent nature of the partial summary “judgment” Marshall seeks with respect to damages makes it readily distinguishable from the type of partial summary judgment on liability contemplated by Rule 56(e). Determining liability (or the absence of liability) is a necessary step in adjudicating a lawsuit. By contrast, damages issues need not be dealt with unless liability is established. Therefore, addressing damages questions before that juncture may be a waste of judicial time.

II. Derivative Liability Under the Performance Bond

Even if Marshall’s motion raises an issue that could be resolved via partial summary judgement, the motion fails on its merits.

The nature and extent of a surety’s liability on a performance bond is governed *94 by the terms of the bond. Narragansett Pier R.R. Co. v. Palmer, 70 R.I. 298, 302, 38 A.2d 761 (1944); see also American Home Assurance Co. v. Larkin General Hospital Ltd., 593 So.2d 195, 197-198 (Fla.1992). Unless the parties have agreed otherwise, the determination as to what law should be consulted in construing the terms of the performance bond and in determining the effect of those terms must be made in accordance with the choice of law rules of the state in which the district court sits. Klaxon Co. v. Stentor Elec. Mfg. Co., 313 U.S. 487, 496, 61 S.Ct. 1020, 1021-22, 85 L.Ed. 1477 (1941) (In diversity cases, the federal courts look to the choice of law rules of the forum state.).

In contract cases, Rhode Island follows the choice of law rules set forth in the Restatement (Second) of Conflict of Laws. Montaup Elec. Co. v. Ohio Brass Corp., 561 F.Supp. 740, 744-745 (D.R.I.1983); Busby v. Perini Corp., 110 R.I. 49, 51, 290 A.2d 210 (1972).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
827 F. Supp. 91, 1993 U.S. Dist. LEXIS 11746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshall-contractors-inc-v-peerless-insurance-rid-1993.