Raito, Inc. v. Cardi Corporation

CourtSuperior Court of Rhode Island
DecidedApril 5, 2010
DocketC.A. No. PB 07-3235
StatusPublished

This text of Raito, Inc. v. Cardi Corporation (Raito, Inc. v. Cardi Corporation) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raito, Inc. v. Cardi Corporation, (R.I. Ct. App. 2010).

Opinion

DECISION
Before the Court for decision are Super. R. Civ. P. Rule 56 cross-motions for summary judgment brought by Defendant and Third-Party Plaintiff Cardi Corporation (Cardi) and Third-Party Defendant Western Surety Company (Western). Cardi has filed a Third-Party Complaint against Western for all sums, if any, due to Cardi from its subcontractor Raito, Inc. (Raito). Western, the surety for Raito, has moved for summary judgment, arguing that Western should be discharged from any liability under the parties' Performance Bond because *Page 2 Cardi failed to comply with its express conditions precedent. Cardi's cross motion for summary judgment challenges the existence of such conditions precedent.

I
Facts Travel
On or about August 1, 2003, Cardi, as general contractor, entered into a contract (the Contract) with the State of Rhode Island, acting through the Rhode Island Department of Transportation for the construction of a new arch-span bridge over the Providence River on Interstate I-95 (the Project). Cardi, in connection with the Project, entered into a subcontract (the Subcontract) with Raito to install a series of concrete foundation shafts for the new bridge. (Pl. Ex. A.) With regard to the Subcontract, Raito, as principal, and Western as surety executed Payment Bond No. 929298884 (Payment Bond)1 and Performance Bond No. 929298884 (Performance Bond). (Pl. Ex. B.)

Cardi alleges that during the course of the work, Raito failed to perform the work in a timely and acceptable manner which resulted in delays to the Project and costs and damages to Cardi. Despite the alleged delays, Cardi never gave notice that it was considering declaring a default or attempted to arrange a conference with Western and Raito, but rather "back-charged" any delay costs against amounts which would have been due to Raito for its work under the Subcontract. Raito then filed the instant action to recover monies allegedly due from Cardi in connection with work performed as a subcontractor on the Project. Cardi counterclaimed against Raito to recover damages caused by Raito's alleged failure to timely and effectively perform such work. Additionally, both Raito and Cardi have brought actions against each other's sureties. Here, Western, Raito's surety, requests summary judgment on the basis of Cardi's *Page 3 failure to issue a notice of default and to terminate Raito's Subcontract, which it alleges are preconditions to liability, at some specified time prior to filing the instant action against Western.

II
Standard of Review
Summary judgment is proper when, after reviewing the admissible evidence in the light most favorable to the non-moving party, "no genuine issue of material fact is evident from the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, and the motion justice finds that the moving party is entitled to prevail as a matter of law."Smiler v. Napolitano, 911 A.2d 1035, 1038 (R.I. 2006) (quoting Rule 56(c)). When considering a motion for summary judgment, "the court may not pass on the weight or credibility of the evidence but must consider the affidavits and other pleadings in a light most favorable to the party opposing the motion." Lennon v.MacGregor, 423 A.2d 820, 822 (R.I. 1980). During a summary judgment proceeding, "the justice's only function is to determine whether there are any issues involving material facts."Id. (quoting Steinberg v. State, 427 A.2d 338, 340 (R.I. 1981)). "Therefore, summary judgment should enter `against a party who fails to make a showing sufficient to establish the existence of an element essential to that party's case * * *.'" Lavoie v.North East Knitting, Inc., 918 A.2d 225, 228 (R.I. 2007) (quotingCelotex Corp. v. Catrett, 477 U.S. 317, 322 (1986) (construing the substantially similar federal rule)).

III
Discussion
This action centers on whether the Performance Bond, a standard American Institute of Architects A312 Performance Bond, 2 required Cardi to issue a notice of default and to terminate Raito's Subcontract before commencing an action against Western. Western argues that notice *Page 4 of a default and termination are conditions precedent under the Performance Bond which should have been satisfied prior to commencing this action against Western. Cardi argues that the Performance Bond, which by reference incorporates the Subcontract, does not create conditions precedent requiring notice of default and termination prior to filing an action against the surety. Additionally, Cardi contends that even if the Performance Bond does contain such preconditions, Cardi satisfied them with its 2009 termination of the Subcontract.3

Under Rhode Island law, a performance bond must be strictly construed and the nature and extent of a surety's liability is governed by the express terms of the bond. Marshall Contractors,Inc. v. Peerless Ins. Co., 827 F.Supp. 91, 94 (D.R.I. 1993) (citing Narragansett Pier R.R. v. Palmer, 70 R.I. 298, 302,38 A.2d 761, 763 (1944)). However, in the instant matter, since the Subcontract is incorporated by reference into the Performance Bond, they should be construed together. See Stanley-Bostitch,Inc. v. Regenerative Environmental Equipment Co., Inc.,786 A.2d 1063, 1065 (R.I. 2001). When reviewing a contract, terms that are clear and unambiguous must be applied as written A.F.Lusi Construction, Inc. v. Peerless Insurance Co., 847 A.2d 254,258 (R.I. 2004) (citing W.P. Associates v. Forcier, Inc.,637 A.2d 353, 356 (R.I. 1994)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Systemized of New England, Inc. v. Scm, Incorporated
732 F.2d 1030 (First Circuit, 1984)
State v. District Court of First Judicial Dist.
220 P.2d 1035 (Montana Supreme Court, 1950)
Marshall Contractors, Inc. v. Peerless Insurance
827 F. Supp. 91 (D. Rhode Island, 1993)
Stanley-Bostitch, Inc. v. Regenerative Environmental Equipment Co.
786 A.2d 1063 (Supreme Court of Rhode Island, 2001)
A.F. Lusi Construction, Inc. v. Peerless Insurance
847 A.2d 254 (Supreme Court of Rhode Island, 2004)
Lavoie v. North East Knitting, Inc.
918 A.2d 225 (Supreme Court of Rhode Island, 2007)
Bank of Brewton, Inc. v. INTERN. FIDELITY INS. COMPANY
827 So. 2d 747 (Supreme Court of Alabama, 2002)
Vickers Antone v. Vickers
610 A.2d 120 (Supreme Court of Rhode Island, 1992)
Ins. Co. of No. Amer. v. Metro. Dade Co.
705 So. 2d 33 (District Court of Appeal of Florida, 1997)
Steinberg v. State
427 A.2d 338 (Supreme Court of Rhode Island, 1981)
W.P. Associates v. Forcier, Inc.
637 A.2d 353 (Supreme Court of Rhode Island, 1994)
Lennon v. MacGregor
423 A.2d 820 (Supreme Court of Rhode Island, 1980)
Gustafson v. Max Fish Plumbing & Heating Co.
622 A.2d 450 (Supreme Court of Rhode Island, 1993)
Dragon Construction, Inc. v. Parkway Bank & Trust
678 N.E.2d 55 (Appellate Court of Illinois, 1997)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Nelson v. Ptaszek
505 A.2d 1141 (Supreme Court of Rhode Island, 1986)
Smiler v. Napolitano
911 A.2d 1035 (Supreme Court of Rhode Island, 2006)
Enterprise Capital, Inc. v. San-Gra Corp.
284 F. Supp. 2d 166 (D. Massachusetts, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Raito, Inc. v. Cardi Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raito-inc-v-cardi-corporation-risuperct-2010.