Space Master International, Inc. v. City of Worcester

940 F.2d 16, 1991 U.S. App. LEXIS 17175, 1991 WL 140850
CourtCourt of Appeals for the First Circuit
DecidedJuly 31, 1991
Docket90-2113
StatusPublished
Cited by45 cases

This text of 940 F.2d 16 (Space Master International, Inc. v. City of Worcester) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Space Master International, Inc. v. City of Worcester, 940 F.2d 16, 1991 U.S. App. LEXIS 17175, 1991 WL 140850 (1st Cir. 1991).

Opinion

BOWNES, Senior Circuit Judge.

This is an appeal from a summary judgment in favor of plaintiff-appellee Space Master International, Inc. (“Space Master”). The City of Worcester, defendant-appellant, hired Space Master to construct modular classrooms to alleviate overcrowding in the City’s public schools. Under the publicly-bid contract, the City agreed to pay Space Master $1,514,559 to install within 120 days twenty-three modular classroom buildings at nine school sites. If performance exceeded 120 days, the City reserved the right to assess Space Master liquidated damages of $250 per day plus $100 per day per site.

*17 Space Master completed its work over 200 days late; the city retained $254,400 in liquidated damages. Space Master then sued the City in the United States District Court of Massachusetts, 1 seeking the withheld funds on the grounds that the liquidated damages provision was unenforceable. It alleged that the liquidated damages clause was not reasonably related to any anticipated or actual loss and that the liquidated damages withheld by the City were disproportionate to the damages incurred. Space Master claimed in the alternative that even were the liquidated damages clause found to be enforceable, plaintiff should not be held liable for the entire amount of liquidated damages because the delay was caused by acts of the City, subcontractors and factors beyond Space Master’s control.

The City moved for partial summary judgment on the enforceability of the liquidated damages provision. It conceded that “the matter of how much in liquidated damages should be assessed against Space Master [should be] reserved until after a trial on the reasons for the delay.” Space Master filed a cross-motion for summary judgment on the enforceability of the liquidated damages clause. After a hearing, the court granted Space Master’s motion and denied the City’s. The City appeals this ruling.

Standard of Review

A district court must enter summary judgment pursuant to Fed.R.Civ.P. 56(c) if

the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

“[S]ummary judgment will not lie if the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Massachusetts contract law “will identify which facts are material.” See id.

Our review is plenary, and we “view the record in the light most favorable to the party against whom a motion for summary judgment is directed, and give that party the benefit of all the reasonable inferences to be drawn therefrom.” J.I. Corp. v. Federal Ins. Co., 920 F.2d 118 (1st Cir.1990). We apply this standard as well where summary judgment motions were made by opposing parties. Continental Casualty Co. v. Canadian Universal Ins. Co., 924 F.2d 370, 373 (1st Cir.1991). “[T]he [trial] court must evaluate each motion separately, being careful to draw inferences against each movant in turn.” Griggs-Ryan v. Smith, 904 F.2d 112, 115 (1st Cir.1990).

Liquidated Damages

Under the Restatement of Contracts:

Damages for breach by either party may be liquidated in the agreement but only at an amount that is reasonable in the light of the anticipated or actual loss caused by the breach and the difficulties of proof of loss. A term fixing unreasonably large liquidated damages is unenforceable on grounds of public policy.

Restatement (Second) of Contracts § 356(1) (1979). Two factors combine to determine whether an amount fixed as liquidated damages is not so unreasonably large as to be unenforceable. First, to be reasonable the amount must approximate actual loss or loss anticipated at the time the contract was executed. Colonial at Lynnfield, Inc. v. Sloan, 870 F.2d 761, 764 (1st Cir.1989) (citing Security Safety Corp. v. Kuznicki, 350 Mass. 157, 213 N.E.2d 866, 867 (1966); A-Z Servicenter, Inc. v. Segall, 334 Mass. 672, 138 N.E.2d 266, 268 (1956); Lynch v. Andrew, 20 Mass.App.Ct. 623, 481 N.E.2d 1383, 1386 (1985); Restatement (Second) of Contracts § 356 (1981)). Second, “[t]he greater the difficulty either of proving that *18 loss has occurred or of establishing its amount with the requisite certainty ... the easier it is to show that the amount fixed is reasonable.” Restatement (Second) of Contracts § 356 comment b.

Considerable deference is given to the parties’ reasonable agreement as to the amount of liquidated damages where losses are difficult to quantify. Lynch v. Andrew, 481 N.E.2d at 1386; Kroeger v. Stop & Shop Cos., 13 Mass.App.Ct. 310, 432 N.E.2d 566, 573 (1982). That deference, however, is not unlimited. In Colonial at Lynnfield, Inc. v. Sloan, we found that the liquidated damages provision at issue was a reasonable estimate of difficult to ascertain damages. We nonetheless found that the liquidated damages provision was an unenforceable penalty because no loss had been sustained as a result of the breach. 870 F.2d at 765. Liquidated damages must compensate for loss rather than punish for breach: “[A]n exaction of punishment for a breach which could produce no possible damage has long been deemed oppressive and unjust.” Priebe & Sons, Inc. v. United States, 332 U.S. 407, 413, 68 S.Ct. 123, 127, 92 L.Ed. 32 (1947). See also Dubinsky v. Wells Bros. Co., 218 Mass. 232, 105 N.E. 1004 (1914) (liquidated damages clause was unenforceable penalty because it was intended to secure performance; no substantial loss was sustained).

There can be no question that the injury sustained by the City is difficult to quantify in monetary terms. Because Space Master breached its promise to provide classrooms for the City within 120 days, children had to attend classes in hallways, gymnasiums, auditoriums, and libraries; educational programs were compromised; and morale among teachers, students and administrators suffered. These conditions continued for over 200 days past the contract deadline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Snyder v. PO Paloska
D. Nevada, 2025
Boone Coleman Constr., Inc. v. Village of Piketon
2014 Ohio 2377 (Ohio Court of Appeals, 2014)
Bose Corporation v. Ejaz
732 F.3d 17 (First Circuit, 2013)
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
Honey Dew Associates, Inc. v. M & K FOOD CORP.
81 F. Supp. 2d 352 (D. Rhode Island, 2000)
Kelly v. Marx
694 N.E.2d 869 (Massachusetts Appeals Court, 1998)
Perfect Solutions, Inc. v. Jereod, Inc.
974 F. Supp. 77 (D. Massachusetts, 1997)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
39 Va. Cir. 292 (Richmond County Circuit Court, 1996)
Waste Mgt. v. Zimpro Envt'l
D. New Hampshire, 1995
Flanagan v. Grant
897 F. Supp. 637 (D. Massachusetts, 1995)
White v. United States
881 F. Supp. 688 (D. Massachusetts, 1995)
Fleet Bank of Massachusetts, N.A. v. One-O-Six Realty, Inc.
3 Mass. L. Rptr. 392 (Massachusetts Superior Court, 1995)
Geas v. DuBois
868 F. Supp. 19 (D. Massachusetts, 1994)
Merillat Industries, Inc. v. Johnston
865 F. Supp. 60 (D. Massachusetts, 1994)
Lincoln National Life Insurance v. Prodromidis
862 F. Supp. 10 (D. Massachusetts, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
940 F.2d 16, 1991 U.S. App. LEXIS 17175, 1991 WL 140850, Counsel Stack Legal Research, https://law.counselstack.com/opinion/space-master-international-inc-v-city-of-worcester-ca1-1991.