Norcross Bros. v. Vose

85 N.E. 468, 199 Mass. 81, 1908 Mass. LEXIS 789
CourtMassachusetts Supreme Judicial Court
DecidedMay 21, 1908
StatusPublished
Cited by25 cases

This text of 85 N.E. 468 (Norcross Bros. v. Vose) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norcross Bros. v. Vose, 85 N.E. 468, 199 Mass. 81, 1908 Mass. LEXIS 789 (Mass. 1908).

Opinion

Braley, J.

This is an action brought to recover a balance claimed to be due for the erection of a building, to be used in the defendant’s business as a manufacturer of pianos. The auditor to whom the case was referred having reported, that with the exception of the item for drafting plans, the plaintiff was entitled to the amount shown by the declaration, less certain deductions for defective work and materials and for failure to [92]*92finish the building within the time named in the contract, it relied unreservedly upon the report, and, not having introduced evidence to control or vary the findings, they must be deemed to have been regarded as the basis upon which the plaintiff’s right to recover finally rested. The allowance for. changes in the foundations, caused by a departure from the original plans, having been conceded, the declination of the defendant to accept the amounts allowed for delay and imperfect construction of the concrete floors narrowed the controversy before the jury to these issues, respectively raised in the first item of the declaration in set-off and by the claim for recoupment. R. L. c. 174, § 1. Blacker v. Boott, 114 Mass. 24, 27. Ford v. Burchard, 130 Mass. 424. Blood v. Wilson, 141 Mass. 25.

If the evidence introduced in support of the counterclaim was competent, the jury were warranted in returning a verdict in favor of the defendant, as they could find the entire damages suffered from a failure to comply with the contract more than exceeded the entire amount demanded. The plaintiff, while taking no exception to the admission of this evidence, and offering no rebuttal, then requested the justice to rule, by the terms of the contract, the plaintiff having been dissatisfied with the decision of the architect as to the number of days chargeable to it for delay in the construction of the building and having requested arbitration of the dispute, which the defendant refused, the defendant could not recover damages from the plaintiff, as an award was a condition precedent to the right to bring suit. It also asked for a further ruling, that as the architect, under the authority conferred upon him to approve payments, had given a final certificate for the full amount demanded, the claim in recoupment could not be maintained, or, if this ruling was refused, then the defendant was bound by the allowance for defective work made by the architect, and the plaintiff was entitled to recover this balance without further deductions. We are of opinion that the denial of these requests was right. It may be assumed from the reference in the closing sentences of articles seven and eight, that the parties intended to incorporate the provisions as to arbitration found in article three, and make them applicable in the same manner to this part of the contract. If the entire contract is examined, it is seen that it [93]*93was not the purpose of the parties, except as to the requirements of article five, to make the action taken by the architect upon the various details of construction as the work progressed final, and in this respect the contract differs from those construed in National Contracting Co. v. Commonwealth, 183 Mass. 89, 92, Norcross v. Wyman, 187 Mass. 25, and White v. Abbott, 188 Mass. 99, where the determination of the architect or supervising engineer upon such matters was held to be conclusive. See Hebert v. Dewey, 191 Mass. 403, 408. Instead, when called upon to act, his decision, if unsatisfactory to either party, was to be referred to arbitration for final settlement. But article six, upon which the set-off rests, contains no reference to either mode of adjustment. It stipulated that, if the completion of the building should be delayed beyond the time named, liquidated damages at the rate of $50 a day should be paid by the plaintiff, “ until the whole of said work is fully completed.” Hall v. Crowley, 5 Allen, 304. If not conceded, it was undisputed that the limit had been exceeded by sixty-five days, before the building was finished. While the auditor’s decision exonerated the defendant from any breach of article eight, the plaintiff has constantly asserted that much of this delay was caused by the defendant’s neglect, and default in performance, for which under the provisions of article seven he should be held liable. By construing articles six, seven and eight as dependent, and providing for a settlement without litigation of all questions of amount and value, it seeks to read into article six the arbitration clause. But if under article seven the defense of the loss of time attributable to the defendant’s failure in providing materials and labor to be furnished by him was fully available under the auditor’s finding, that the limitation within which the demand must be presented had been waived, the plaintiff had expressly agreed to pay a fixed amount for each day’s delay, from which it had not been released. This provision was not made dependent upon the agreement for an extension of time, but is distinct. It is not a promise to pay whatever sum either the architect or arbitrators might determine, but to pay at the rate named for a definite period, even if that period might be shortened, if the plaintiff found it necessary, in avoidance, to resort to the provisions for its protection contained in article seven. The [94]*94principal agreement to erect and finish the building for the consideration the defendant agreed to pay, and the agreement to pay liquidated damages under article six if the defendant claimed them, were independent provisions to neither of which was attached a stipulation that until the amount due had been settled by arbitration no suit for either the price or the damages should be maintained. An award not having been made a condition precedent to the right to sue, each was at liberty to resort to the courts for a settlement of their differences. Nute v. Hamilton Ins. Co. 6 Gray, 174, 181. Rowe v. Williams, 97 Mass. 163. Hood v. Hartshorn, 100 Mass. 117. White v. Middlesex Railroad, 135 Mass. 216, 219. Reed v. Washington Ins. Co. 138 Mass. 572, 576. Clement v. British American Assurance Co. 141 Mass. 298. Hutchinson v. Liverpool & London Globe Ins. Co. 153 Mass. 143. Lamson v. Prudential Ins. Co. 171 Mass. 433. Norcross v. Wyman, ubi supra. Hebert v. Dewey, ubi supra. Lewis v. Brotherhood Accident Co. 194 Mass. 1, 4. Hamilton v. Home Ins. Co. 137 U. S. 370. Scott v. Avery, 5 H. L. Cas. 811. Collins v. Locke, 4 App. Cas. 674. Viney v. Bignold 20 Q. B. D. 172. Dawson v. Fitzgerald, 1 Ex. D. 257.

The plaintiff, although declaring on the contract, could recover only on the account annexed, and the defendant not having been deprived of the protection and benefit of the contract, the amount recoverable is limited to the agreed price, after deducting payments and all damages suffered from the plaintiff’s breach of its various stipulations. Hayward v. Leonard, 7 Pick. 180. Blood v. Wilson, 141 Mass. 25. Burke v. Coyne, 188 Mass. 401, 404.

By article nine, all instalments as they accrued were payable only on the architect’s certificate, and by article ten, while the certificate for the final payment is to be regarded as “conclusive evidence of.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graphics Leasing Corp. v. Y Weekly
1991 Mass. App. Div. 110 (Mass. Dist. Ct., App. Div., 1991)
Ernest & Norman Hart Bros. v. Town Contractors, Inc.
463 N.E.2d 355 (Massachusetts Appeals Court, 1984)
Kelleher v. Cersosimo
320 N.E.2d 840 (Massachusetts Appeals Court, 1974)
Louise Caroline Nursing Home, Inc. v. Dix Construction Corp.
285 N.E.2d 904 (Massachusetts Supreme Judicial Court, 1972)
Sanford v. Boston Edison Co.
56 N.E.2d 1 (Massachusetts Supreme Judicial Court, 1944)
Cueroni v. Coburnville Garage, Inc.
52 N.E.2d 16 (Massachusetts Supreme Judicial Court, 1943)
Montgomery v. Karavas
114 P.2d 776 (New Mexico Supreme Court, 1941)
Lakube v. Cohen
23 N.E.2d 144 (Massachusetts Supreme Judicial Court, 1939)
Walsh v. Cornwell
172 N.E. 855 (Massachusetts Supreme Judicial Court, 1930)
Province Securities Corp. v. Maryland Casualty Co.
269 Mass. 75 (Massachusetts Supreme Judicial Court, 1929)
Kingston Realty Co. v. Dobbins
163 N.E. 753 (Massachusetts Supreme Judicial Court, 1928)
Rosenblum v. Springfield Produce Brokerage Co.
243 Mass. 111 (Massachusetts Supreme Judicial Court, 1922)
State v. Slorah
106 A. 768 (Supreme Judicial Court of Maine, 1919)
Hennebique Construction Co. v. Boston Cold Storage & Terminal Co.
119 N.E. 948 (Massachusetts Supreme Judicial Court, 1918)
Hooper v. Cuneo
227 Mass. 37 (Massachusetts Supreme Judicial Court, 1917)
Powers Regulator Co. v. Taylor
114 N.E. 356 (Massachusetts Supreme Judicial Court, 1916)
Brocklehurst & Potter Co. v. Marsch
225 Mass. 3 (Massachusetts Supreme Judicial Court, 1916)
Lincoln Stone & Supply Co. v. Ludwig
144 N.W. 782 (Nebraska Supreme Court, 1913)
Hathaway v. Stone
215 Mass. 212 (Massachusetts Supreme Judicial Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.E. 468, 199 Mass. 81, 1908 Mass. LEXIS 789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norcross-bros-v-vose-mass-1908.