Brocklehurst & Potter Co. v. Marsch

225 Mass. 3
Massachusetts Supreme Judicial Court·Decided September 13, 1916·Published·Cited by 33 cases

Opinion

Rugg, C. J.

These are three actions at law which have been reported by a judge of the Superior Court* for determination as to the correctness of his orders overruling the defendant’s demurrers to the several declarations. The action by the Brocklehurst and Potter Company will be considered first. The declaration is in three counts, the first in tort, and the second and third in contract.

The first count sets out in substance, that the defendant was a general contractor for the construction of a portion of the lines of the Southern New England Railroad and that the plaintiff had a subcontract with him for the doing of some of this construction; that the railroad corporation, in violation of its contract with the defendant, stopped all work upon his contract and thereupon the plaintiff and the defendant entered into a written contract under date of February 22, 1913, for the adjustment of their respective rights and obligations toward each other growing out of the enforced suspension of all work by the defendant and his subcontractor due to the action of the railroad corporation. The essential features of this contract were a release by the plaintiff-of all liability to it on the part of the defendant on account of work done by it on the railroad, with an obligation by the defendant to present to the railroad corporation all claims for damages to the plaintiff and all damages of his own and to collect and adjust the same, the defendant being given full authority in the premises both to settle and to sue for the plaintiff. Then followed this agreement: “and in the event that settlement is made by said [railroad] corporation with said Marsch, the said Marsch shall pay to said company [the plaintiff] pro rata share of the amount recovered, taking into consideration in said pro rata distribution all things relating to the work performed,, including plant, general outfit, etc.; and in case said company [the plaintiff] and [6] said Marsch are unable to agree upon said pro rata distribution, then, and in that event, the distribution shall be made by three arbitrators whose decision, it is hereby agreed, shall be final. Said board of arbitration shall be composed of said Marsch and two disinterested members who have a practical knowledge of such work as has been performed; said arbitrators to be appointed, one by a committee of two representing all the subcontractors on said construction work, and the third to be appointed by said Marsch and the arbitrator appointed by the parties interested.” Further allegations are that the defendant settled all claims with the railroad corporation and by fraud represented to the plaintiff that the net amount received by him was less than it was in truth, and that his expenses incurred in connection with the settlement were greater than they were in fact, whereby the plaintiff was induced to and did execute a release to the defendant in return for the payment of a sum much less than its pro rata share provided for in the agreement and that by reason of these false and fraudulent representations the plaintiff has been damaged.

The second count sets out substantially the same allegations of facts and concludes that “the defendant has made a breach of the terms of his contract, all to the great damage of the plaintiff.” The third count is for money had and received by the defendant to the plaintiff’s use. All the counts are alleged to be for one and the same cause of action.

The joinder of these several counts in one action was permissible under R. L. c. 173, § 6, cl. 6. Crafts v. Belden, 99 Mass. 535. Morse v. Hutchins, 102 Mass. 439. Whitside v. Brawley, 152 Mass. 133. Brown v. Sallinger, 214 Mass. 245.

The allegations of fraud and misrepresentations of fact in obtaining the release of all claims and demands against the defendant, dated September 11, 1913, as set out at length in count two, doubtless were not necessary to a statement of the substantive facts out of which the plaintiff’s claim arose. It may be assumed that these allegations were made in anticipation of and in answer to an expected defence of a release under seal. Although not a ground for demurrer, the pleading in the declaration in an action at law of a reply to an apprehended defence is not to be commended. Stephen on Pleading, (Williston’s ed.) 422 and cases cited.

It becomes necessary to determine the nature of the contract [7] of February 22, 1913. Its purpose was to provide a method for the adjustment of the claim for damages which the plaintiff had against the defendant by reason of being prevented from carrying forward to completion its subcontract for construction work upon the railroad. A part of its consideration was the execution and delivery by the plaintiff of a release under seal of all its claims for damages against the defendant for that cause of action. In substitution for all such claims, there is a promise by the defendant to present seasonably all his claims and all claims of the plaintiff against the railroad corporation and in case of a settlement of these claims he further promises to pay to the plaintiff a “pro rata share of the amount recovered, taking into consideration in said pro rata distribution all things relating to the work performed, including plant, general outfit, etc.” That promise is direct, plain and unequivocal. It is not made to depend upon any other act, event or conduct. It is disconnected from any other consideration. It is separated both in form of grammatical structure and in the substance of the subject matter from the arbitration clause. The amount of money which thus it was stipulated should be paid to the plaintiff by the defendant is as easy of ascertainment by the usual methods of court trial as are damages in many cases. The sum of money actually received by the defendant must be provable without difficulty. His expenses and disbursements stand on the same footing. On the averments of the declaration “steam shovel units or their equivalents” were adopted by the parties as the correct basis for distribution. But, even if this be not so, there appears to be no insurmountable obstacle in assessing damages. No greater difficulties exist than often are encountered by courts and juries. Maynard v. Royal Worcester Corset Co. 200 Mass. 1, 8. C. W. Hunt Co. v. Boston Elevated Railway, 199 Mass. 220, 236. Stevens v. Rockport Granite Co. 216 Mass. 486, 493.

The stipulation as to arbitration is not made a condition precedent to a right to recover upon the contract. It is distinct and severable from the agreement to pay a pro rata share of the amount recovered by the defendant. The phrase of the contract in this respect is markedly different, for example, from that of the standard form of insurance. St. 1907, c. 576, § 60. Second Society of Universalists v. Royal Ins. Co. Ltd. 221 Mass. 518, 525, 526. It is in legal effect like those found in Reed v. Washington Fire & [8] Marine Ins. Co. 138 Mass. 572, Norcross Brothers Co. v. Vose, 199 Mass. 81, 94, and Derby Desk Co. v. Conners Brothers Construction Co. 204 Mass. 461, 467. See Hanley v. Aetna Ins. Co. 215 Mass. 425, 429.

Free access — add to your briefcase to read the full text and ask questions with AI

Brocklehurst & Potter Co. v. Marsch, 225 Mass. 3 (Mass. 1916).

225 Mass. 3 (Brocklehurst & Potter Co. v. Marsch) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vespers Realty Advisors, Inc. v. Binswanger Management Corp.
21 Mass. L. Rptr. 77 (Massachusetts Superior Court, 2006)
Fortune v. National Cash Register Co.
364 N.E.2d 1251 (Massachusetts Supreme Judicial Court, 1977)
Allen W. Reeves v. Charles Tarvizian, Trustees
351 F.2d 889 (First Circuit, 1965)
Rankin v. Kellam
388 S.W.2d 306 (Court of Appeals of Texas, 1965)
CALEDONIA SAND AND GRAVEL CO. v. Joseph A. Bass Co.
151 A.2d 312 (Supreme Court of Vermont, 1959)
Smith Beverages, Inc. v. Metropolitan Casualty Insurance
149 N.E.2d 146 (Massachusetts Supreme Judicial Court, 1958)
Sanford v. Boston Edison Co.
56 N.E.2d 1 (Massachusetts Supreme Judicial Court, 1944)
Hedge & Mattheis Co. v. Savini
6 Mass. App. Div. 115 (Mass. Dist. Ct., App. Div., 1941)
Lakube v. Cohen
23 N.E.2d 144 (Massachusetts Supreme Judicial Court, 1939)
Keljikian v. Star Brewing Co.
20 N.E.2d 465 (Massachusetts Supreme Judicial Court, 1939)
Judkins v. Hyannis Public Library Ass'n
19 N.E.2d 727 (Massachusetts Supreme Judicial Court, 1939)
New England Engineering Co. v. Grasso
3 Mass. App. Div. 45 (Mass. Dist. Ct., App. Div., 1938)
Gallo v. Foley
11 N.E.2d 803 (Massachusetts Supreme Judicial Court, 1937)
Rainault v. Evarts
7 N.E.2d 145 (Massachusetts Supreme Judicial Court, 1937)
Grueby v. Chase Harris Forbes Corp.
197 N.E. 624 (Massachusetts Supreme Judicial Court, 1935)
People v. S. W. Straus & Co.
158 Misc. 186 (New York Supreme Court, 1935)
Bethlehem Fabricators, Inc. v. H. D. Watts Co.
190 N.E. 828 (Massachusetts Supreme Judicial Court, 1934)
Gray v. Gurney Seed & Nursery Co.
252 N.W. 3 (South Dakota Supreme Court, 1933)
Newell v. Rosenberg
176 N.E. 616 (Massachusetts Supreme Judicial Court, 1931)
Walsh v. Cornwell
172 N.E. 855 (Massachusetts Supreme Judicial Court, 1930)