Walsh v. Cornwell

172 N.E. 855, 272 Mass. 555, 1930 Mass. LEXIS 1266
Massachusetts Supreme Judicial Court·Decided October 2, 1930·Published·Cited by 25 cases

Opinion

Field, J.

This is an action of contract brought in the Superior Court by an owner of land against a builder to recover damages for breach of a written agreement to erect a dwelling house thereon. The case was referred to an auditor whose findings of fact were to be final. The trial judge denied the defendant’s motion to recommit the report to the auditor and ordered judgment for the plaintiff for $4,900, with interest from the date of the writ, and the defendant excepted.

The auditor found that the defendant entered into a contract with the plaintiff to build a dwelling house for the plaintiff to be completed in October, 1926, for $13,400, payable in instalments, that the plaintiff fully performed his part of the contract except the payment of the last instalment of $900, which amount he contends he is not required to pay because of nonperformance by the defendant, that because of the defendant’s “failure to build according to the plans and specifications serious defects resulted in the finished house,” that “if the house had been constructed according to the contract, plans and specifications, it would have been of the fair market value of $13,400 at the time fixed for completion in October 1926,” that “the fair market value of the house at the time fixed for completion . . . was $8,700,” that, if material, “it would have cost in October, 1926, at least $4,000 to tear down parts of the structure and rebuild it to accord with the terms of the contract, specifications and plans,” but “it would not be practicable and economical to make all alterations necessary to make the house conform” thereto, that the plaintiff actually expended $299.41, the reasonable cost of remedying certain minor defects, that he “made his last payment on October 23, 1926, then telling . . . [the defendant] that the house was in an unsatisfactory condition,” and the defendant then gave the plaintiff “a receipt . . . which indicated that . . . [the plaintiff] paid with reservations,” and that the plaintiff “moved into the house about October 28, 1926,” “about the time the house was completed.”

The contract provided that payments should be made [560] by the owner, the plaintiff here, “only upon certificates of the Architects” and should be “due when certificates for the same are issued,” but that “no certificate given or payment made . . . , except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and ... no payment shall be construed to be an acceptance of defective work or improper materials.” There was also a section in the contract like that considered in Loftus v. Jorjorian, 194 Mass. 165, 168 (see also White v. Abbott, 188 Mass. 99, 100, 101, Norcross Brothers Co. v. Vose, 199 Mass. 81, 84, 85), authorizing the plaintiff upon default of the defendant; certified by the architect, to furnish labor or materials required by the contract or terminate the employment of the defendant and complete the work included in the contract, and providing that the “expense incurred by the Owner . . . , either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the Architects, whose certificate thereof shall be conclusive upon the parties,” and a section providing for arbitration if the “Owner and Contractor fail to agree in relation to matters of payment” or other matters not here material.

The auditor found that the “architect did not supervise construction or issue certificates,” that he “had not supervised the work in its progress nor had he followed it in its progress, although he saw the house a few times while it was being built,” and that there was no evidence that the plaintiff “asked the architect to supervise” or that the defendant “took any action about supervision by the architect.” It was not found that any matter was submitted to arbitration.

1. There was no error in the denial of the motion to recommit.

No ground for recommitting the report is shown by the record outside the report itself. It was within the judicial discretion to refuse to recommit the report on the ground of its form. In this aspect the refusal to recommit did not amount to a ruling of law. See Koch, petitioner, [561] 225 Mass. 148, 150. W. R. Grace & Co. v. National Wholesale Grocery Co. Inc. 251 Mass. 251, 253. The defendant’s contention that the report is incomplete because it does not set forth the contract as to which a question of interpretation is raised, is without foundation. A copy of a contract is attached to the declaration. This is sufficiently identified in the report as a copy of the contract made by the parties and is embodied in the report by reference. Nor can we say that the report does not set forth the provisions of the plans and specifications sufficiently to present the questions of law in issue. Recommittal because of the refusal of the auditor to reopen the case “for the purpose of hearing new and additional testimony” was discretionary with the trial judge (see Wells v. Wells, 209 Mass. 282, 291, W. R. Grace & Co. v. National Wholesale Grocery Co. Inc. supra) and no abuse of discretion is shown.

Rulings by the auditor as to the admission and exclusion of evidence are reviewable by us on the exception to the denial of the motion to recommit. Lunn & Sweet Co. v. Wolfman, 268 Mass. 345, 348 and cases cited. In these respects, however, no error appears.

The defendant’s offer to show a statement by the architect of the amount which, in his opinion, should be allowed by the defendant to the plaintiff for defects and the amount which should be paid by the plaintiff to the defendant for extras, was excluded rightly. The statement did not purport to be an architect’s certificate within the meaning of the contract. See Hennebique Construction Co. v. Boston Cold Storage & Terminal Co. 230 Mass. 456, 462. This evidence was merely hearsay as to the architect’s opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Walsh v. Cornwell, 172 N.E. 855, 272 Mass. 555, 1930 Mass. LEXIS 1266 (Mass. 1930).

172 N.E. 855 (Walsh v. Cornwell) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bean v. Cy Realty Corp
1 Mass. L. Rptr. 574 (Massachusetts Superior Court, 1994)
Iacovelli v. Russell
1984 Mass. App. Div. 231 (Mass. Dist. Ct., App. Div., 1984)
All Stainless, Inc. v. Colby
308 N.E.2d 481 (Massachusetts Supreme Judicial Court, 1974)
Concannon v. Galanti
202 N.E.2d 236 (Massachusetts Supreme Judicial Court, 1964)
Wolk v. Teich
23 Mass. App. Dec. 5 (Mass. Dist. Ct., App. Div., 1961)
Jones v. Elliott
108 N.W.2d 742 (Nebraska Supreme Court, 1961)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Staples Coal Co. v. Ucello
131 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1956)
Ficara v. Belleau
117 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1954)
Ravage v. Johnson
56 N.E.2d 25 (Massachusetts Supreme Judicial Court, 1944)
Karlinski v. P. R. & H. Lumber & Construction Co.
281 N.W. 898 (North Dakota Supreme Court, 1938)
Chesler v. Nobilio
1 Mass. App. Div. 439 (Mass. Dist. Ct., App. Div., 1936)
O'Reilly v. O'Reilly
199 N.E. 741 (Massachusetts Supreme Judicial Court, 1936)
Barrows v. Checker Taxi Co.
195 N.E. 112 (Massachusetts Supreme Judicial Court, 1935)
Carbonneau v. Cavanaugh
194 N.E. 724 (Massachusetts Supreme Judicial Court, 1935)
New England Newspaper Pub. Co. v. Bonner
68 F.2d 880 (First Circuit, 1934)
Royal Paper Box Co. v. Munro & Church Co.
188 N.E. 223 (Massachusetts Supreme Judicial Court, 1933)
Zarthar v. Saliba
185 N.E. 367 (Massachusetts Supreme Judicial Court, 1933)
Federal National Bank v. Commonwealth
185 N.E. 9 (Massachusetts Supreme Judicial Court, 1933)
Barton v. Morin
183 N.E. 170 (Massachusetts Supreme Judicial Court, 1932)