Walsh v. Cornwell

172 N.E. 855, 272 Mass. 555, 1930 Mass. LEXIS 1266
CourtMassachusetts Supreme Judicial Court
DecidedOctober 2, 1930
StatusPublished
Cited by25 cases

This text of 172 N.E. 855 (Walsh v. Cornwell) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. Cornwell, 172 N.E. 855, 272 Mass. 555, 1930 Mass. LEXIS 1266 (Mass. 1930).

Opinion

Field, J.

This is an action of contract brought in the Superior Court by an owner of land against a builder to recover damages for breach of a written agreement to erect a dwelling house thereon. The case was referred to an auditor whose findings of fact were to be final. The trial judge denied the defendant’s motion to recommit the report to the auditor and ordered judgment for the plaintiff for $4,900, with interest from the date of the writ, and the defendant excepted.

The auditor found that the defendant entered into a contract with the plaintiff to build a dwelling house for the plaintiff to be completed in October, 1926, for $13,400, payable in instalments, that the plaintiff fully performed his part of the contract except the payment of the last instalment of $900, which amount he contends he is not required to pay because of nonperformance by the defendant, that because of the defendant’s “failure to build according to the plans and specifications serious defects resulted in the finished house,” that “if the house had been constructed according to the contract, plans and specifications, it would have been of the fair market value of $13,400 at the time fixed for completion in October 1926,” that “the fair market value of the house at the time fixed for completion . . . was $8,700,” that, if material, “it would have cost in October, 1926, at least $4,000 to tear down parts of the structure and rebuild it to accord with the terms of the contract, specifications and plans,” but “it would not be practicable and economical to make all alterations necessary to make the house conform” thereto, that the plaintiff actually expended $299.41, the reasonable cost of remedying certain minor defects, that he “made his last payment on October 23, 1926, then telling . . . [the defendant] that the house was in an unsatisfactory condition,” and the defendant then gave the plaintiff “a receipt . . . which indicated that . . . [the plaintiff] paid with reservations,” and that the plaintiff “moved into the house about October 28, 1926,” “about the time the house was completed.”

The contract provided that payments should be made [560]*560by the owner, the plaintiff here, “only upon certificates of the Architects” and should be “due when certificates for the same are issued,” but that “no certificate given or payment made . . . , except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and ... no payment shall be construed to be an acceptance of defective work or improper materials.” There was also a section in the contract like that considered in Loftus v. Jorjorian, 194 Mass. 165, 168 (see also White v. Abbott, 188 Mass. 99, 100, 101, Norcross Brothers Co. v. Vose, 199 Mass. 81, 84, 85), authorizing the plaintiff upon default of the defendant; certified by the architect, to furnish labor or materials required by the contract or terminate the employment of the defendant and complete the work included in the contract, and providing that the “expense incurred by the Owner . . . , either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the Architects, whose certificate thereof shall be conclusive upon the parties,” and a section providing for arbitration if the “Owner and Contractor fail to agree in relation to matters of payment” or other matters not here material.

The auditor found that the “architect did not supervise construction or issue certificates,” that he “had not supervised the work in its progress nor had he followed it in its progress, although he saw the house a few times while it was being built,” and that there was no evidence that the plaintiff “asked the architect to supervise” or that the defendant “took any action about supervision by the architect.” It was not found that any matter was submitted to arbitration.

1. There was no error in the denial of the motion to recommit.

No ground for recommitting the report is shown by the record outside the report itself. It was within the judicial discretion to refuse to recommit the report on the ground of its form. In this aspect the refusal to recommit did not amount to a ruling of law. See Koch, petitioner, [561]*561225 Mass. 148, 150. W. R. Grace & Co. v. National Wholesale Grocery Co. Inc. 251 Mass. 251, 253. The defendant’s contention that the report is incomplete because it does not set forth the contract as to which a question of interpretation is raised, is without foundation. A copy of a contract is attached to the declaration. This is sufficiently identified in the report as a copy of the contract made by the parties and is embodied in the report by reference. Nor can we say that the report does not set forth the provisions of the plans and specifications sufficiently to present the questions of law in issue. Recommittal because of the refusal of the auditor to reopen the case “for the purpose of hearing new and additional testimony” was discretionary with the trial judge (see Wells v. Wells, 209 Mass. 282, 291, W. R. Grace & Co. v. National Wholesale Grocery Co. Inc. supra) and no abuse of discretion is shown.

Rulings by the auditor as to the admission and exclusion of evidence are reviewable by us on the exception to the denial of the motion to recommit. Lunn & Sweet Co. v. Wolfman, 268 Mass. 345, 348 and cases cited. In these respects, however, no error appears.

The defendant’s offer to show a statement by the architect of the amount which, in his opinion, should be allowed by the defendant to the plaintiff for defects and the amount which should be paid by the plaintiff to the defendant for extras, was excluded rightly. The statement did not purport to be an architect’s certificate within the meaning of the contract. See Hennebique Construction Co. v. Boston Cold Storage & Terminal Co. 230 Mass. 456, 462. This evidence was merely hearsay as to the architect’s opinion.

An engineer, called by the plaintiff, was permitted to testify as an expert. Some of his testimony, according to the report, was disregarded by the auditor. The question, therefore, whether, if this testimony was admitted wrongly, the report should be permitted to stand was not a matter of law reviewable here, but a matter solely within the discretion of the trial judge. Chelmsford Foundry Co. v. Shepard, 206 Mass. 102, 108. The other testimony of this witness that “he thought the house was then worth $9,000” [562]*562and “it would, in his opinion, cost $4,000 to make the house conform to plans and specifications, made up in part of $500 to correct the roof and $1,500 to cure the paint and plaster trouble,” was admitted properly. We cannot say, on the findings as to his qualifications, that he was not qualified to give this testimony. His opinion as to the value of the house was material on the issue of its value as left by the builder, an element in the measure of damages. Pelatowski v. Black, 213 Mass. 428, 430, 431. See infra. The defendant did not object to the testimony of this witness as to the cost of making the house conform to the plans and specifications, except on the ground that he was not qualified to testify, or to the admission of any of his testimony as immaterial because of the provisions of the contract as to an architect’s certificate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bean v. Cy Realty Corp
1 Mass. L. Rptr. 574 (Massachusetts Superior Court, 1994)
Iacovelli v. Russell
1984 Mass. App. Div. 231 (Mass. Dist. Ct., App. Div., 1984)
All Stainless, Inc. v. Colby
308 N.E.2d 481 (Massachusetts Supreme Judicial Court, 1974)
Concannon v. Galanti
202 N.E.2d 236 (Massachusetts Supreme Judicial Court, 1964)
Wolk v. Teich
23 Mass. App. Dec. 5 (Mass. Dist. Ct., App. Div., 1961)
Jones v. Elliott
108 N.W.2d 742 (Nebraska Supreme Court, 1961)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Staples Coal Co. v. Ucello
131 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1956)
Ficara v. Belleau
117 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1954)
Ravage v. Johnson
56 N.E.2d 25 (Massachusetts Supreme Judicial Court, 1944)
Karlinski v. P. R. & H. Lumber & Construction Co.
281 N.W. 898 (North Dakota Supreme Court, 1938)
Chesler v. Nobilio
1 Mass. App. Div. 439 (Mass. Dist. Ct., App. Div., 1936)
O'Reilly v. O'Reilly
199 N.E. 741 (Massachusetts Supreme Judicial Court, 1936)
Barrows v. Checker Taxi Co.
195 N.E. 112 (Massachusetts Supreme Judicial Court, 1935)
Carbonneau v. Cavanaugh
194 N.E. 724 (Massachusetts Supreme Judicial Court, 1935)
New England Newspaper Pub. Co. v. Bonner
68 F.2d 880 (First Circuit, 1934)
Royal Paper Box Co. v. Munro & Church Co.
188 N.E. 223 (Massachusetts Supreme Judicial Court, 1933)
Zarthar v. Saliba
185 N.E. 367 (Massachusetts Supreme Judicial Court, 1933)
Federal National Bank v. Commonwealth
185 N.E. 9 (Massachusetts Supreme Judicial Court, 1933)
Barton v. Morin
183 N.E. 170 (Massachusetts Supreme Judicial Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
172 N.E. 855, 272 Mass. 555, 1930 Mass. LEXIS 1266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-cornwell-mass-1930.