Gillis v. Cobe

59 N.E. 455, 177 Mass. 584, 1901 Mass. LEXIS 703
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 27, 1901
StatusPublished
Cited by49 cases

This text of 59 N.E. 455 (Gillis v. Cobe) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gillis v. Cobe, 59 N.E. 455, 177 Mass. 584, 1901 Mass. LEXIS 703 (Mass. 1901).

Opinion

Loring, J.

1. The first question submitted to the court by the referee is whether the defendants’ act of putting in the tanks constituted an act of acceptance which dispensed with the necessity of the plaintiffs’ furnishing the architect’s certificate.

The plaintiffs contend that this question does not arise in this case, because it is nowhere provided in the contract that their right to recover the contract price depends upon their securing a certificate from the architect. Though the provisions of this contract are not as explicit as building contracts usually are in this respect, yet, on a fair construction of its terms, we think that the plaintiffs’ right to recover does depend upon their producing a certificate from the architect. In the specifications, which are made part of the contract, there is this provision: “ Payments to be made only upon a written order from the architects, as the work progresses. No order will be considered an acceptance of the work on which it is given. Only an order for the final payment shall be considered as an acceptance of the work.” This clause, taken in connection with the two following clauses of the contract, must be taken to make the payment of the contract price dependent upon the architect’s giving his certificate : “ Any disagreement between the owners and the contractor upon any matter arising from these specifications or drawings of the work required, shall be decided by the engineers and architect, whose decision shall be final and binding on both parties.” “ All payments shall be made upon the written certificate of the engineers and architects.” We are therefore of opinion that this question does arise.

Further, we are of opinion that the act of the defendants in using the building when the plaintiffs stopped working on it [590]*590was not an acceptance of it. By the express terms of the contract, “ Only an order for the final payment shall be considered as an acceptance of the work.” The building became the defendants’ property, as it was affixed to their land; when the plaintiff stopped working on it and the architect refused to give a certificate that it was constructed in accordance with the requirements of the contract, the defendants were not bound to remove the building, nor were they bound, so long as the building stood on their land, to abstain from using what was their own. The use of the building, therefore, was not an acceptance of it under the contract; nor was it an acceptance of it apart from the contract for the purpose of a recovery under the rule of Hayward, v. Leonard, 7 Pick. 181; there is no question of acceptance in case of a recovery on that ground; that rule depends upon other considerations.

2. The second question is whether a recovery can be had in this case on the common counts, without furnishing the architect’s certificate. In the contract which the parties in this case have made, they did not go so far as to negative any recovery by the contractors, in case the architect refused to give his certificate ; in the absence of such a negative stipulation in the contract, the failure to secure the architect’s certificate cannot be a bar to the plaintiffs’ right to recover on the principle of Hayward v. Leonard, if they are otherwise entitled to recover on that ground. Fitzgerald v. Allen, 128 Mass. 232. Atkins v. Barnstable, 97 Mass. 428. Reed v. Scituate, 7 Allen, 141, 144. Reed v. Scituate, 5 Allen, 120. Walker v. Orange, 16 Gray, 193. Snow v. Ware, 13 Met. 42. It is not necessary to determine whether the rule enforced in Hayward v. Leonard rests on general principles of justice, or is derived by construction from the fact that there was no intention to render the services gratuitously.

3. The third question submitted by the referee is, whether the plaintiffs can recover on the doctrine of Hayward v. Leonard on the facts found by him in the award.

It is contended on behalf of the plaintiffs that the referee has not reported this question to the court. The referee concludes his award with the following statement: “ If the court is of opinion that this action can be maintained on the foregoing statement, then I find and report that the defendants owe the [591]*591plaintiffs the sum of $1,066.” The plaintiffs contend that this is nothing more than a reference to the two questions of law which, by the preceding paragraph, were referred to this court. But that would not be a fair construction of these words had they stood alone; and they cannot be construed as if they stood alone, for, if nothing more than that had been intended by the referee, there could have been no reason for the extended statement of facts contained in the award. Though the statement of facts in an award is not of itself enough to hold that all questions of law arising on those facts are submitted to the court,— Rogers v. Mayer, 151 Mass. 279, — yet, on a fair construction of this award as a whole, we are of opinion that the referee submitted to the court the question of the plaintiffs’ right to recover on the common counts on the facts found by him. See Fairchild v. Adams, 11 Cush. 549, 555.

The plaintiffs’ second contention in this connection is that the following findings of the referee entitle them to a recovery on the common counts: (1) “ The evidence shows that the plaintiffs have performed the work, and furnished the materials required by the plans and specifications, except that they have failed to,put in any of the iron rods except one, which by the plans and specifications were to be furnished and put in by the plaintiffs, running from side to side of the building and across the corners, through the concrete, and the one they did put in was placed under and not through the concrete.” (2) “I find on the third and fourth counts, both on quantum meruit, that the plaintiffs have performed the work and furnished materials in the construction of the building called for by the contract in good faith, and that they are of value to the defendants, . . . and that such work and materials are of the value of $1,266.”

These findings cannot be taken, on any fair construction of the award, to be a finding that the plaintiffs complied with the contract in the construction of the building in all particulars except in putting in the rods. There is a specific finding in the award to the effect that the plaintiffs did not prove that they complied with the contract requirements in laying the cinder filling, on which the concrete floor which gave way and sank, when put into use was to, and does, rest. This finding is as follows : “ 1 am, on the evidence, unable to determine to what [592]*592this sinking of the floor is chargeable, whether to insufficient tamping or ramming and wetting of the cinder filling, which the plaintiffs were required to do by the contract, or to the spongy, swampy condition of the soil, — foundation for the cinder filling, — for which the plaintiffs are not chargeable.” This specific finding cannot be taken to have been annulled by the general findings; these general findings must be taken to amount to nothing more than a finding that the building was erected by the plaintiffs, and erected in good faith.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dolan v. McQuaide
79 A.3d 394 (Court of Special Appeals of Maryland, 2013)
Salamon v. Terra
477 N.E.2d 1029 (Massachusetts Supreme Judicial Court, 1985)
Peavey v. Pellandini
551 P.2d 610 (Idaho Supreme Court, 1976)
P. J. Riley & Co. v. Aberthaw Construction Co.
327 N.E.2d 909 (Massachusetts Appeals Court, 1975)
Paul Hardeman, Inc. v. Arkansas Power & Light Company
380 F. Supp. 298 (E.D. Arkansas, 1974)
Kass v. Todd
284 N.E.2d 590 (Massachusetts Supreme Judicial Court, 1972)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Banking & Trading Corp. v. Reconstruction Finance Corp.
147 F. Supp. 193 (S.D. New York, 1956)
M. Ahern Co. v. John Bowen Co. Inc.
133 N.E.2d 484 (Massachusetts Supreme Judicial Court, 1956)
Masse v. Smitherman Cotton Mills, Inc.
9 Mass. App. Dec. 31 (Mass. Dist. Ct., App. Div., 1955)
Zani v. Garrison Hall Inc.
14 N.E.2d 118 (Massachusetts Supreme Judicial Court, 1938)
Beverly Hospital v. Early
197 N.E. 641 (Massachusetts Supreme Judicial Court, 1935)
Poorvu v. Weisberg
286 Mass. 526 (Massachusetts Supreme Judicial Court, 1934)
Barton v. Morin
183 N.E. 170 (Massachusetts Supreme Judicial Court, 1932)
Searls v. Loring
176 N.E. 212 (Massachusetts Supreme Judicial Court, 1931)
Walsh v. Cornwell
172 N.E. 855 (Massachusetts Supreme Judicial Court, 1930)
Reynolds v. Cole
172 N.E. 91 (Massachusetts Supreme Judicial Court, 1930)
Santoro v. Mack
145 A. 272 (Supreme Court of Connecticut, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
59 N.E. 455, 177 Mass. 584, 1901 Mass. LEXIS 703, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gillis-v-cobe-mass-1901.