Jones v. Elliott

108 N.W.2d 742, 172 Neb. 96, 1961 Neb. LEXIS 54
CourtNebraska Supreme Court
DecidedApril 21, 1961
Docket34853
StatusPublished
Cited by42 cases

This text of 108 N.W.2d 742 (Jones v. Elliott) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Elliott, 108 N.W.2d 742, 172 Neb. 96, 1961 Neb. LEXIS 54 (Neb. 1961).

Opinion

Messmore, J.

This is an action in equity brought in the district court for Hitchcock County by Walter V. Jones, doing business as Jones Construction Company, plaintiff, against Howard Elliott, Harold Elliott, and Delbert Urling, doing business as Elliott Brothers and Urling Grain Company, a copartnership, to foreclose a chattel mortgage and a mechanic’s lien. The trial court found generally in favor of the plaintiff and against the defendants. The trial court further found that the plaintiff and defendants entered into a written agreement May 26, 1958, wherein the plaintiff agreed to remodel a Quonset building belonging to the defendants so that it could be used as a grain elevator, to erect two buildings for storage of grain, and to furnish the necessary equipment. The defendants agreed to pay $95,000 upon completion of the struc *98 tures and buildings. The contract also provided that .the defendants could elect a time-payment plan whereby the price would be $96,800, to be paid in certain installments in cash, of which $7,500 would be due upon completion of the buildings and structures, and the balance of $63,800 would be evidenced by four equal promissory notes each in the sum of $15,950, secured by a chattel mortgage on property belonging to the defendants. The trial court further found that after the execution of the agreement, the plaintiff commenced the reconstruction of the Quonset building and the construction of the storage building; that the defendants elected to take the time-payment plan; that on July 1, 1958, the defendants executed and delivered to the plaintiff the four promissory notes secured by a chattel mortgage; that said mortgage was a valid and enforceable lien upon the defendants’ property described in the plaintiff’s petition; and that the mechanic’s lien filed by the plaintiff was not filed within the time provided for by law and was null and void.

The trial court further found that the defendants paid the plaintiff all cash installments provided for in the contract except the last installment of $7,500 which was due upon completion and acceptance of the building and structures; and that the plaintiff furnished extras in the sum of $948.12. The trial court further found that the plaintiff failed to comply with the plans and specifications of the contract in certain respects and, for failure to so do, allowed the defendants damages in the following amounts: Headhouse, $3,434.76; cement driveway, $995; aeration system, $311.45; rewiring for aeration system, $72.50; overhead auger, $320.05; and compression flanges, $377.21. The trial court further found that the defendants lost profits in the amount of $1,753.04. The trial court further found that said amounts should be allowed as a setoff from the $7,500 and $948.12 found to be due plaintiff; that by reason thereof, the plaintiff was entitled to the difference between *99 $8,448.12 and $7,264.01, or $1,184.11, with interest at 6 percent per annum from February 1, 1959, to date, in the sum of $89.78, or an aggregate of $1,273.89. The trial court further found that the notes signed by the defendants and delivered to the plaintiff were valid obligations of the defendants, and were past due; that the amount due the plaintiff on said notes was $72,049.68 with interest at 7 percent per annum from date until paid; and that the plaintiff was entitled to a decree of foreclosure of the chattel mortgage and sale of property described in the decree for payment of $72,049.68 with interest at 7 percent.

On May 5, 1960, the trial court rendered judgment in the amount of $72,049.68 with interest at 7 percent from date of rendition of judgment on the notes, as above stated, and also rendered judgment in the amount of $1,273.89 with interest at 6 percent from the date of the rendition of the judgment, as above stated. We conclude that when the trial court allowed interest at 6 percent on the $1,184.11 from February 1, 1959, to the date of rendition of the judgment, it was in error. The trial court apparently invoked section 45-104, R. R. S. 1943, which has no application in this case where there were damages allowed to be offset against a cash payment due upon the alleged completion of a building contract. The trial court should have rendered judgment in the amount of $1,184.11 with interest at 6 percent per annum from the date of the rendition of the judgment.

The defendants filed a motion for new trial which was overruled. From the overruling of the defendants’ motion for new trial, the defendants appealed.

The defendants have set forth 24 assignments of error, most of which relate to the failure of the trial court in allowing sufficient damages to the defendants for breach of contract in certain respects by the plaintiff. The defendants also predicate error on the ground that the plaintiff failed to follow the plans and specifications of the contract relating to the footings and foundations *100 of the buildings, by virtue of which the defendants claim they sustained damages and for which the trial court allowed no damages; that the notes in question were not valid obligations, were usurious, and were void; and that the chattel mortgage given as security for the same was void, and consequently the plaintiff was not entitled tO' a foreclosure of the chattel mortgage. The defendants also claim that the trial court erred in finding that the defendants elected to pay the amount of the contract pursuant to the time-payment plan.

On December 16, 1959, when the trial commenced, the defendants were granted the right to amend their answer to the effect that the plaintiff’ failed to comply with the contract to properly construct the footings and foundations of the buildings.

The case is for trial de novo in this court.

The contract provides that the contractor should erect two Columbian rigid-frame grain-storage buildings, each 50 feet wide by 260 feet long with 14-foot high sidewalls, and roof ventilators placed on 20-foot centers. The contract provided for other construction and the furnishing of facilities, some of which are set forth in the trial court’s findings and others that are not so set forth but have been considered as to whether or not they fail to comply with the plans and specifications, and what damages, if any, defendants would be entitled to recover.

The defendants were the owners of a leasehold interest in a tract of land owned by the Chicago, Burlington & Quincy Railroad Company, upon which two buildings were to be constructed for the storage of grain, and a Quonset building, which was standing on the premises, was to be remodeled so it could be used as a grain elevator.

Upon an examination of the record relating to the damages that the trial court has allowed for the items heretofore specified, the record sustains the amount of damages as awarded by the trial court to the defendants. The trial court denied the defendants damages on cer *101 tain other items. We conclude that the trial court did not err in so doing because of the lack of proof on the part of the defendants respecting such damages. Also, the trial court did not err in refusing to allow the plaintiff certain amounts for extras claimed to have been furnished by the plaintiff, for the same reason.

We next consider how the footings and foundations were put in by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

de Vries v. L & L Custom Builders
968 N.W.2d 64 (Nebraska Supreme Court, 2021)
Oettinger v. Hiatt
Nebraska Court of Appeals, 2013
Eliker v. Chief Industries, Inc.
498 N.W.2d 565 (Nebraska Supreme Court, 1993)
PIONEER ENTERPRISES, INC. v. Edens
345 N.W.2d 16 (Nebraska Supreme Court, 1984)
Lange Building & Farm Supply, Inc. v. Open Circle "R", Inc.
342 N.W.2d 360 (Nebraska Supreme Court, 1983)
Nekuda v. Vincent
330 N.W.2d 477 (Nebraska Supreme Court, 1983)
Tibbs v. Fisher
303 N.W.2d 293 (Nebraska Supreme Court, 1981)
Remington v. Bryan
288 N.W.2d 253 (Nebraska Supreme Court, 1980)
A R L Corp. v. Hroch
268 N.W.2d 101 (Nebraska Supreme Court, 1978)
Wilson Concrete Co. v. A. S. Battiato Construction Co.
241 N.W.2d 819 (Nebraska Supreme Court, 1976)
Stungis v. Union Packing Co. of Omaha, Inc.
241 N.W.2d 660 (Nebraska Supreme Court, 1976)
Groeteke v. Stubbs
241 N.W.2d 538 (Nebraska Supreme Court, 1976)
Henggeler v. Jindra
214 N.W.2d 925 (Nebraska Supreme Court, 1974)
Sorensen v. Robert N. Ewing, General Contractor
448 P.2d 110 (Court of Appeals of Arizona, 1968)
REORGANIZED CH. OF JESUS CHRIST v. Universal Sur. Co.
128 N.W.2d 361 (Nebraska Supreme Court, 1964)
Jacobs v. Korst
122 N.W.2d 760 (Nebraska Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
108 N.W.2d 742, 172 Neb. 96, 1961 Neb. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-elliott-neb-1961.