Stungis v. Union Packing Co. of Omaha, Inc.

241 N.W.2d 660, 196 Neb. 126, 1976 Neb. LEXIS 753
CourtNebraska Supreme Court
DecidedMay 12, 1976
Docket40297
StatusPublished
Cited by10 cases

This text of 241 N.W.2d 660 (Stungis v. Union Packing Co. of Omaha, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stungis v. Union Packing Co. of Omaha, Inc., 241 N.W.2d 660, 196 Neb. 126, 1976 Neb. LEXIS 753 (Neb. 1976).

Opinions

Brodkey, J.

This case comes to this court on an appeal by the de[127]*127fendant, Union Packing Company, Inc., from a jury verdict and judgment entered thereon in favor of the plaintiff, Bob Stungis, doing business as Bob’s Kustom Body Shop, in the amount of $18,000, representing damages allegedly sustained by plaintiff as a result of defendant’s breach of contract. We affirm.

Plaintiff, Stungis, owned an industrial tract in Omaha, part of which was the site of his auto repair shop and part of which was vacant. Plaintiff’s land, on its north and west sides, was adjacent to land owned by defendant, Union Packing Company, on which defendant’s packing house was located. In 1969, Union Packing Company made plans to construct a new building on its property, which would extend close to the boundary line between its property and plaintiff’s property to the .south thereof. For that purpose, it sought plaintiff’s permission to excavate part of plaintiff’s land near the boundary line between the two properties, and, on or about December 3, 1969, plaintiff and defendant entered into a written agreement under the terms of which defendant was given permission to use the north 15 feet of plaintiff’s lot for the purpose of excavation and storing dirt. As part of that agreement, defendant specifically agreed to restore plaintiff’s land to its original condition upon completion of the construction work on defendant’s own land. During the negotiations between the parties, Stungis made it clear that he wanted the land restored to its original condition as he planned to build an addition to his auto shop, and defendant and its agents were aware of that fact. Between 1969 and 1972, defendant was engaged in the construction of the addition to its plant, and during that period removed soil from plaintiff’s property and stored it in a vacant lot near the construction site. During the course of the excavation, defendant excavated to depths as great as 30 feet below the original surface of plaintiff’s land. Upon completion of its construction work, defendant refilled the hole it had excavated on plaintiff’s property.

[128]*128Later, when Stungis was preparing to build his new body shop, he was informed that soil tests revealed the defendant had backfilled his property with uncompacted debris and that the soil was not uniform enough in the area involved to support a concrete slab floor building, and that it would be necessary to reexcavate and refill the hole to restore the land to its original condition. He then filed suit against the defendant, alleging a breach of contract to restore the property to its original condition and alleging that as a result of defendant’s failure to refill the excavation with clean and compacted fill, the value of the property was reduced from $65,000 to $45,000; and he prayed for damages in the amount of $20,000. He subsequently filed an amended petition and a second amended petition, modifying the allegations of before-and-after value of the property, but leaving the prayer for $20,000 damages unaltered. In its amended 'answer, defendant admitted the execution of the written contract on or about December 3, 1969, but alleged that it had performed all the conditions of the written agreement which it was required to perform, and denied the other allegations contained in plaintiff’s second amended petition.

Trial was had to a jury on June 12 and 13, 1975. During the trial, plaintiff did not introduce evidence with respect to the diminution of the value of the property; but rather, over the objection of the defendant, he was permitted by the court to introduce evidence concerning the cost of repair of the property. An expert witness for plaintiff testified that the cost of restoring the property to its original condition would be $18,000.

Defendant’s principal defense to the action on the matter of damages was that plaintiff had suffered no damages; and to support this proposition it adduced evidence from James Casperson, an architect for Union Packing Company, who testified that, in his opinion, the soil at the filled site was two and one-half times stronger than that on the original ground before the excavation. [129]*129The only other evidence on damages adduced by defendant during trial was the testimony of one witness that there were some bricks in the soil at the northwest part of the property and that it would take $1,900 to clean the soil in that area.

At the close of the evidence, plaintiff moved the court for leave to amend his petition to conform to the proof, in the manner set out in his requested instruction No. 1. Part of that requested instruction states as follows: “The plaintiff alleges that the reasonable cost of restoring the land to it prior condition of usefulness is $18,000.00.” Counsel for defendant objected generally to the amendment requested, without specifically stating his reasons for his objection at that time. The court granted plaintiff’s request for the amendment. The purpose of the requested amendment was to permit the court to instruct the jury on damages based on the evidence in the record, which was limited to testimony of the cost of repair, and not the before-and-after value of the property as alleged in plaintiff’s second amended petition. In its instructions, the court first told the jury that if it decided the plaintiff should recover, it would be its duty to award any damages as would fairly and reasonably, but not excessively, compensate for the injury or loss which had been sustained as a direct and proximate result of the breach of contract; and in the next instruction added: “If plaintiff’s land was damaged and can at reasonable cost be restored to substantially its condition immediately before the damage occurred, plaintiff is entitled to recover the cost of making such changes necessary to restore the property to substantially its condition immediately before the soil was excavated.” The jury brought back a verdict of $18,000, and the court entered judgment on the verdict. Motion for a new trial having been overruled, defendant perfected its appeal to this court.

In its brief on appeal, defendant sets out 18 assignments of error, only a few of which are discussed in its [130]*130brief. Rule 8a2(3) of the Revised Rules of the Supreme Court, 1974, provides that consideration of the cause by this court will be limited “to errors assigned and discussed.” (Emphasis supplied.) See, also, State v. Hoffmeyer, 187 Neb. 701, 193 N. W. 2d 760 (1972). In accordance with the foregoing rule, we shall consider only those assignments argued or discussed by defendant.

The principal assignment of error discussed by defendant in its brief was that the court erred in sustaining plaintiff’s motion to amend his petition to conform with the proof on the last day of the trial. Union Packing Company claims that it was unfairly surprised by the amendment and was prejudiced by it. Intertwined with this assignment is the defendant’s claim that the testimony relative to the cost of restoration of the property given by plaintiff’s expert witness was improperly admitted over objection, and could not serve as a basis for the amendment. Defendant also assigns as error and argues that the court erred in sustaining plaintiff’s objection to questions propounded to Stungis by defendant about the original purchase price of the subject property, and as to offers to sell or purchase his property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wellman v. Birkel
367 N.W.2d 716 (Nebraska Supreme Court, 1985)
Collection Associates, Inc. v. Eckel
324 N.W.2d 808 (Nebraska Supreme Court, 1982)
Meyer v. Sandhills Beef, Inc.
318 N.W.2d 863 (Nebraska Supreme Court, 1982)
Remington v. Bryan
288 N.W.2d 253 (Nebraska Supreme Court, 1980)
Foremost Insurance v. Allied Financial Services, Inc.
286 N.W.2d 740 (Nebraska Supreme Court, 1980)
Foremost Ins. Co. v. ALLIED FIN. SERVICES
286 N.W.2d 740 (Nebraska Supreme Court, 1980)
Yunghans v. O'TOOLE
258 N.W.2d 810 (Nebraska Supreme Court, 1977)
Stungis v. Union Packing Co. of Omaha, Inc.
241 N.W.2d 660 (Nebraska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W.2d 660, 196 Neb. 126, 1976 Neb. LEXIS 753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stungis-v-union-packing-co-of-omaha-inc-neb-1976.