Gutov v. Clark

157 N.W. 49, 190 Mich. 381, 1916 Mich. LEXIS 881
CourtMichigan Supreme Court
DecidedMarch 30, 1916
DocketDocket No. 110
StatusPublished
Cited by13 cases

This text of 157 N.W. 49 (Gutov v. Clark) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gutov v. Clark, 157 N.W. 49, 190 Mich. 381, 1916 Mich. LEXIS 881 (Mich. 1916).

Opinion

Brooke, J.

The following statement of fact is quoted from brief of counsel for the appellant:

“On May 31, 1913, the three plaintiffs, who are themselves all carpenters and builders, executed a contract with the defendant, by the terms of which the defendant was to furnish all material and erect for the plaintiffs for the sum of $5,800, according to the plans and specifications,-a four-family frame flat building on a lot 40x112 feet owned by the plaintiffs on Crane avenue, Detroit. The plaintiffs deeded this lot to the defendant who was to negotiate a construction loan, and, after the erection of the flat, give a land contract back to the plaintiffs for the purchase of the premises at $6,700, the value of the lot being put at $900. The defendant at once began the construction of the building and had it practically completed, when, on November 14, 1913, the plaintiffs took possession of the building and moved into the flat, occupying continuously since then three of the four apartments- themselves, and renting continuously since then the fourth apartment for the first two months at $16 a month, and thereafter at $14 a month. The plaintiffs took possession of the building under protest, claiming that it was not properly completed according to plans and speci[383]*383fications, but that the defendant had threatened to sell the building and they were obliged to move in to protect their rights.
“The contract provides that the building should be completed by September 1, 1913, but no claim is made for delay, the entire claim of the plaintiffs being based on alleged defects in material and workmanship. There is no serious dispute but that the building substantially fulfills the purpose for which it was intended —that is, a four-family flat building to be used entirely for residential purposes.
_ “The defendant claims that the building is substantially what the plans andN specifications call for, and that any variances were caused by changes made at the request of the plaintiffs. The contract provides that Mr. Swirsky, the architect, was to be the superintendent of construction, but the plaintiffs did not furnish an architect, claiming that the defendant said, that he didn’t need an architect. The defendant claims that the plans and specifications were faulty, and did not clearly indicate what was to be done and that this fact caused some of the alleged variances from the plans and specifications. The defendant also claims that the plaintiffs definitely accepted the building as complying with the plans and specifications when they moved into it. The defendant claims further that certain extras were used for which he has not been paid, but he has withdrawn these from consideration in this case.
“The defects claimed by the plaintiffs are chiefly as follows: The pier foundations under the building are 9x9 in size and made of cement instead of 12x12 of brick, and the pier foundations are not deep enough causing the building proper to settle 1% inches to 1% inches, and causing the front porch to slope back toward the building 2 inches to "3 inches, instead of sloping away from the building. The cement used is not properly mixed and crumbles. The inside finish was not properly sandpapered. Some of the siding was put on crooked, and much of it is poplar instead of white pine. Single-coil heaters were used instead of double-coil, and two-piece sinks instead of one-piece. The joists are not bridged. Four windows and frames in the front of the building are left out. The [384]*384roof sags in the middle. A decorative wooden circle is left off the front of the building, and the cornice returns are not properly extended, and there is artificial stone instead of cut stone used for chimney coping. The front doors are 1% inches pine instead of 2 inches oak, and double strength American glass was used instead of plate glass. The water pipes are exposed in one kitchen. The back porches have a cheaper grade of flooring than specified, and the back stairs were flimsy and had to be removed. The doors are left off the closets. The water pipe connection with the water main is a % inch instead of 1 inch. The studding are 22 feet instead of 24 feet.”

Plaintiffs secured a verdict and judgment for $1,900. Defendant reviewing said judgment in this court, discusses the following questions:

(1) The charge of the court on the rule for the measure of damages was misleading.

(2) The verdict is contrary to the great weight of evidence, and a new trial should have been granted on this ground.

(3) The verdict is grossly excessive, and a new trial should have been granted on this ground.

(4) There was error in the ruling made on the admission and rejection of certain testimony.

1. Excerpts from the charge of the court upon the measure of damages follow:

“If the building varied from the plans and specifications to such an extent that the building would have to be destroyed and rebuilt practically so as to make it conform to the terms of the contract, including the terms and specifications, then the rule of damages would be as follows:
“The plaintiff would be entitled to recover (the difference between) the value of the building actually taken possession of by the plaintiffs on November 14, 1913,' at a value not exceeding the contract price and the value of the building as it would have been had it been completed in accordance with the contract which includes the plans and specifications not exceeding the contract price.
[385]*385“Now the plaintiffs in this case do not claim that the building when completed would exceed the contract price, consequently the contract price will determine the value of the building which should have been furnished by the defendant to the plaintiffs. If you find that there was a breach of contract on the part of the defendant, the plaintiffs in this case will be entitled to recover under their theory or claims the difference between the value of the building not exceeding the contract price actually furnished,; that is, the building as it was on the grounds on November 14, 1913, and the building which would have been there had the contract been literally complied with.
“In other words, it is practically the difference between what the value of the building would have been , had it been built in accordance with the terms of the contract for them actually at the contract price, and the building which was actually presented, which they actually took'possession of November 14, 1913, and you could not consider the value of the building of which they took possession as being worth more than the contract price. Plaintiffs claim it would be worth much less than the contract price; the defendant claims that it was worth the contract price. It is the claim of the defendant that even under the rule given you as the measure of damages, if you find for the plaintiffs, that the building they actually furnished the plaintiffs was equal in value to the contract price of it, that the house which plaintiffs took possession of was worth the contract price for the house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kokkonen v. Wausau Homes, Inc.
289 N.W.2d 382 (Michigan Court of Appeals, 1980)
Baranowski v. Strating
250 N.W.2d 744 (Michigan Court of Appeals, 1976)
Lindhout v. Ingersoll
228 N.W.2d 415 (Michigan Court of Appeals, 1975)
Schultz v. Sapiro
178 N.W.2d 521 (Michigan Court of Appeals, 1970)
Caradonna v. Thorious
169 N.W.2d 179 (Michigan Court of Appeals, 1969)
P & M CONST. CO., INC. v. Hammond Ventures, Inc.
142 N.W.2d 468 (Michigan Court of Appeals, 1966)
Jones v. Elliott
108 N.W.2d 742 (Nebraska Supreme Court, 1961)
Carter v. State Farm Mutual Automobile Insurance
87 N.W.2d 105 (Michigan Supreme Court, 1957)
Antonoff v. Basso
78 N.W.2d 604 (Michigan Supreme Court, 1956)
Turnbull v. Roseland Park Cemetery Ass'n
68 N.W.2d 753 (Michigan Supreme Court, 1955)
Phelps v. Grand Rapids Growers, Inc.
67 N.W.2d 59 (Michigan Supreme Court, 1954)
Karlinski v. P. R. & H. Lumber & Construction Co.
281 N.W. 898 (North Dakota Supreme Court, 1938)
Snider v. Peters Home Building Co.
167 N.W. 108 (Supreme Court of Minnesota, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
157 N.W. 49, 190 Mich. 381, 1916 Mich. LEXIS 881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gutov-v-clark-mich-1916.