Eaton v. Gladwell

80 N.W. 292, 121 Mich. 444, 1899 Mich. LEXIS 595
CourtMichigan Supreme Court
DecidedOctober 3, 1899
StatusPublished
Cited by8 cases

This text of 80 N.W. 292 (Eaton v. Gladwell) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eaton v. Gladwell, 80 N.W. 292, 121 Mich. 444, 1899 Mich. LEXIS 595 (Mich. 1899).

Opinion

Long, J.

It appears that December 15, 1892, the defendant entered into a written contract 'with plaintiffs for the construction by them of a certain building for defendant. The contract referred to certain plans and specifications which were annexed thereto. The plaintiffs entered upon the work, and on March 10, 1894, notified the defendant that the building was completed according to the contract. No payments, so far as shown by this record, had been made on the contract, and defendant hád not accepted or taken possession of the building. Suit was then commenced by plaintiffs against defendant [446]*446to recover upon the contract for the contract price, and for some extra work and material. In that case plaintiffs had verdict and judgment, which was subsequently reversed in this court. Eaton v. Gladwell, 108 Mich. 678. That case was subsequently discontinued by the plaintiffs. On April 6, 1895, the defendant took possession of the building under protest, in which he stated that, in taking possession,, he did not accept the building as having been built in accordance with the terms of the contract, and that he would hold the plaintiffs responsible for all sums it might cost to put it in shape for use, and for loss of rent of the premises since the time it should have been finished under the contract; also, the difference in the value of the building as it then was and what it would be worth if constructed and finished according to the contract. Soon after the defendant took' possession of the building, the present suit was commenced. The action is brought to recover on the quantum meruit.

The defendant claimed upon the trial that the work and materials did not correspond in many particulars to those required by the contract. While there is a contest over some of these matters, it is not seriously contended that the building, was in all respects as required; but it is claimed here, as it was in the former case, that the defendant waived his right to insist on strict compliance with / the contract terms. The plaintiffs, to maintain the case j upon the quantum meruit, introduced three witnesses, ,! two of whom testified that the building was worth in the ; spring of 1895 $1,327, and the third put it as $1,387.25, • while the plaintiffs stated the value at $1,400. Plaintiffs’ witnesses say, however, that they did not estimate the value of the building on the basis of the specifications, but ¡"took the building as it was. Defendant called several - witnesses who testified to the difference in the value of the building as it was constructed and what it would have been worth if built according to the specifications. Mr. Spitzley placed the difference in value at $400; Mr. Golden, at from $500 to $600; Mr. Shepler, at the same [447]*447•amount; Mr. Lee placed the value of the building as it then was at $900, or over $400 less than it would have been worth if built according to the contract. Testimony was also introduced by the defendant showing what these defects in the building were. They are too numerous to mention here, but many of them, according to this testimony, were glaring, and not easily remedied without a total rebuilding of the structure. The defendant also made another claim of defense as a set-off to the amount claimed by plaintiffs. It appears that the contract was made December 15, 1892. The work was commenced in January, 1893, but was stopped by the city authorities because it was within the fire limits. The limits were changed, and work was again commenced May 17, 1893. No complaint is made by the defendant of this delay, however; but Mr. Eaton, one of the plaintiffs, testified that two months would have been a reasonable time to complete the building after work commenced the second time, and that it could have been finished in May and June, and ready for occupancy by July, 1893. The notice of its completion was served on defendant on March 10, 1894; and defendant claims for the rental value of the building from the time it should have been completed, .July 1, 1893, to the time he took possession of it, in April, 1895. His testimony tended to show that the rental value for this time was from $45 to $54 per month.

The questions involved, as stated by counsel for defendant, are:

1. What is the proper measure of plaintiffs’ recovery in quantum meruit for the .construction of the building, which they admit does not conform to the contract and ■specifications ?
2. Was the defendant bound at anytime to take possession of the defective. building before the plaintiffs had ■completed it according to the provisions of the contract F
3. If the defendant was not bound to take possession of the building, was he responsible for injury to it occasioned by dampness and general deterioration arising from ■vacancy during the time preceding his actually taking possession, and while the building was unoccupied ?
[448]*448' 4. Cannot the defendant recoup against the plaintiffs the damages he has suffered on account of the loss of the use of such a building as he contracted for ?

Upon the question of the measure of damages, the defendant called Mr. Spitzley as a witness, and asked him .- “ How much would it cost to make the necessary changes in that building to make it conform to the plans and specifications ? ” This was objected to, and objection sustained, upon the ground that it would be a practical impossibility to make the building, in the manner in which it was constructed, conform to the plans and specifications. Similar questions were put to other witnesses, and objections sustained by the court. It was and is the contention of counsel for defendant that these questions were proper, and that the measure of damages which should be permitted, under the circumstances here stated, is what the building was reasonably worth as defendant took possession of it, not exceeding the contract price, less what it would reasonably cost to complete it and make it comply with the contract and specifications. On the other hand, counsel for plaintiffs contend that the proper measure of damages in a case like the present is the value of the building as it is, not exceeding the contract price, less the difference in its value as it now stands and as it would be were it such a building as contracted for; that, to this difference in value to be deducted in the case at bar, there should be added the damage suffered by the defendant by reason of the delay, if any, in constructing the building, and the net result would be the measure of recovery. The court below stated the rule as to the measure of damages substantially as it is claimed by counsel for plaintiffs.

While it is apparent that the rule claimed by counsel for plaintiffs and as given by the court is not the correct rule, the defendant had no reason 'to complain of it. It gave him a greater amount of damages than he was entitled to. In fact, it gave him double damages; that is, under it he could take the building erected at its then value, not exceeding the contract price, deducting from [449]*449that value the difference between such value and what it would be worth if it had been such a building as contracted for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Independent Shope Brick Co. v. Dugger
281 S.W. 600 (Court of Appeals of Texas, 1926)
Falk v. Nitz
189 N.W. 921 (Michigan Supreme Court, 1922)
Ginsberg v. Myers
183 N.W. 749 (Michigan Supreme Court, 1921)
Pierson v. Smith
178 N.W. 659 (Michigan Supreme Court, 1920)
Gutov v. Clark
157 N.W. 49 (Michigan Supreme Court, 1916)
Pennsylvania Rubber Co. v. Detroit Shipbuilding Co.
152 N.W. 1071 (Michigan Supreme Court, 1915)
Germain v. Union School District
122 N.W. 524 (Michigan Supreme Court, 1909)
Mosaic Tile Co. v. Chiera
95 N.W. 537 (Michigan Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
80 N.W. 292, 121 Mich. 444, 1899 Mich. LEXIS 595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eaton-v-gladwell-mich-1899.