P & M CONST. CO., INC. v. Hammond Ventures, Inc.

142 N.W.2d 468, 3 Mich. App. 306, 1966 Mich. App. LEXIS 650
CourtMichigan Court of Appeals
DecidedMay 24, 1966
DocketDocket 391
StatusPublished
Cited by8 cases

This text of 142 N.W.2d 468 (P & M CONST. CO., INC. v. Hammond Ventures, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & M CONST. CO., INC. v. Hammond Ventures, Inc., 142 N.W.2d 468, 3 Mich. App. 306, 1966 Mich. App. LEXIS 650 (Mich. Ct. App. 1966).

Opinion

Holbrook, J.

P&M Construction Company, Inc., contracted with Hammond Ventures, Inc., defend *308 ant, to perform certain basic construction work on defendant’s 9-hole golf course on the outskirts of Kalamazoo. This work was to be done on an equipment-rental basis with total amount to complete plaintiff’s contract not to exceed $18,400.

Plaintiff performed its work on the golf course in the spring and summer of 1962 and defendant paid plaintiff on account for such work from time to time. Plaintiff claimed complete performance of the contract in the month of September, 1962, and demanded payment of $2,090.55, the claimed balance due and in addition, $744.90 as an extra for constructing a practice green and the sums of $360 and $183.50 for other claimed extras performed at the request of defendant. Defendant refused payment claiming plaintiff breached the contract in that the work performed was not in accord with specifications for which defendant claimed damages.

Thereupon, plaintiff sued defendant for $3,378.95 and defendant answered denying plaintiff’s claims and counterclaimed for damages in the amount of $10,420.85.

The case was heard before the court without a jury and the trial judge ruled that plaintiff was entitled to $18,400 (balance $2,090.55) under the terms of the contract for rentals and materials furnished and $1,288.40 for extras. He further ruled that plaintiff did not complete the work in accordance with the terms of the contract and that defendant was entitled to recover on its cross-complaint in the sum of $2,495; resulting in a judgment for plaintiff in the amount of $883.95. Upon entry of this judgment, defendant appealed and plaintiff cross-appealed.

Defendant-appellant requests this Court to vacate and set aside the finding of the trial court for plaintiff for any sum in excess of $744.90 and that said amended amount be applied against the sum of *309 $2,495 found by the trial court due defendant from plaintiff on its cross-complaint. Plaintiff-appellee requests this Court to set aside the trial court’s finding for defendant and enter a judgment for plaintiff in the sum of $3,378.95 awarded plaintiff by the trial court, reduced by the amount of $249.25 to be allowed defendant on its cross-complaint. The pertinent facts appear to be as follows:

Plaintiff agreed to perform earth moving and grading work for defendant’s golf course by a proposal signed by plaintiff’s president, Rocco A. Martin, January 12, 1962, which proposal was accepted by defendant. The pertinent portions of the contract appear to be as follows:

“Phase A — Earthmoving and grading work for the construction of tees, greens, sandtraps, fairways, and adjacent areas. * * *
“For the necessary work to complete Phase A we propose the following: Work to be performed on an equipment rental basis with total amount to complete work of Phase A * * * not to exceed $18,400.00. * * *
“3. All work shall be done under the supervision of the golf course architect and to his satisfaction. He shall decide all questions which arise as to the quality and acceptability of materials furnished, work performed, manner of performance, rate of progress of work interpretation of the plans and specifications, acceptable fulfillment of the contract, and approvals of payments. * * *
“ 5. The golf course architect shall make a final inspection of all work included in the contract, as soon as practical after notification by the contractor that the work is complete and ready for acceptance. If the work is not acceptable to the golf course architect at the time of such inspection he shall inform the contractor as to the particular defects to be remedied before final acceptance can be made.”

*310 On the grading and dimension plan appears the following:

“All existing topsoil shall he saved and stockpiled and used to cover those areas disturbed by construction. All tees, and g’reen aprons, and fairway areas shall be covered with at least 6" of topsoil. Areas outside the fairways shall be covered with at least 4" of topsoil.”

In accordance with the contract, plans and specifications were furnished by defendant to plaintiff:.

Defendant admitted that the charge of $744.90 of plaintiff for the practice green, was an extra, and was a proper charge but claimed the other extras of plaintiff were in performance of plaintiffs contract. Defendant further claimed that plaintiff failed to perform said contract, in that it did not remove stone from the golf course, as required in the contract, and further failed to replace topsoil to the proper depth, where the topsoil was removed in performing the work.

Plaintiff actually expended $22,000 in doing the basic work required by the contract.

Mr. Pearson testified that at a meeting at the golf course September 28, 1962, with Mr. Pearson, secretary of plaintiff corporation, Mr. Spear, architect for defendant, and Mr. Hammond, representing the defendant, present, defendant accepted the work of plaintiff as having been completed by reason of Mr. Hammond and Mr. Spear authorizing plaintiff to do extra work on the golf course. Defendant denied that it ever approved the job. No written final approval was ever given by the architect. He did, however, approve various parts of the work, and nearly all of the basic contract price was paid for by defendant to plaintiff.

Plaintiffs exhibit number 6, a checklist dated 7 /25/62, indicated work to be corrected by plaintiff. *311 Plaintiff claims it performed in accordance with that checklist. The exhibit bears the typewritten initials of Mr. Spear; however, he disclaimed making it. On four occasions, a representative of plaintiff informed Mr. Spear, the architect, that plaintiff had completed the job and asked for a final inspection. Mr. Spear testified that upon each inspection, he found work yet to be accomplished in order to meet the specifications. On November 14, 1962, he wrote a letter to plaintiff stating in part as follows:

“Of major concern now is the lack of sufficient topsoil on the turf areas. Referring to my specifications ‘earth moving and grading work’ item 4: stripping and respreading topsoil — Existing topsoil shall be stripped in sufficient quantity to permit replacing six inches of topsoil over all proposed lawn areas disturbed by grading operations. All existing topsoil shall be saved. All topsoil shall be kept free of subsoil and debris.
“Your failure to abide by this specification, especially when more than adequate amounts of topsoil were available, is the most serious offense a contractor can make in the construction of a golf course since a thick, healthy turf is so essential to good maintenance. Prior to the start of your construction work on this site, Mr. Hammond had soil test borings made in various locations throughout the property. It was found the depth of topsoil averaged 12 to 13 inches.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franzel v. Kerr Manufacturing Co.
600 N.W.2d 66 (Michigan Court of Appeals, 1999)
Devalk Lincoln Mercury, Inc. v. Ford Motor Company
811 F.2d 326 (Seventh Circuit, 1987)
DeValk Lincoln Mercury, Inc. v. Ford Motor Co.
811 F.2d 326 (Seventh Circuit, 1987)
Zinchook v. Turkewycz
340 N.W.2d 844 (Michigan Court of Appeals, 1983)
Kokkonen v. Wausau Homes, Inc.
289 N.W.2d 382 (Michigan Court of Appeals, 1980)
Schultz v. Sapiro
178 N.W.2d 521 (Michigan Court of Appeals, 1970)
Gordon v. Great Lakes Bowling Corp.
171 N.W.2d 225 (Michigan Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
142 N.W.2d 468, 3 Mich. App. 306, 1966 Mich. App. LEXIS 650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-m-const-co-inc-v-hammond-ventures-inc-michctapp-1966.