Dept of Transportation v. Adrian & Blissfield Railroad Company

CourtMichigan Court of Appeals
DecidedSeptember 3, 2015
Docket321176
StatusUnpublished

This text of Dept of Transportation v. Adrian & Blissfield Railroad Company (Dept of Transportation v. Adrian & Blissfield Railroad Company) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dept of Transportation v. Adrian & Blissfield Railroad Company, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

DEPARTMENT OF TRANSPORTATION, UNPUBLISHED September 3, 2015 Plaintiff-Appellee,

v No. 321176 Ingham Circuit Court ADRIAN & BLISSFIELD RAILROAD LC No. 13-001338-CZ COMPANY, JACKSON & LANSING RAILROAD COMPANY, and CHARLOTTE SOUTHERN RAILROAD COMPANY,

Defendants-Appellants.

Before: SAWYER, P.J., and M. J. KELLY and SHAPIRO, JJ.

PER CURIAM.

In this case involving the Michigan Railroad Code (MRC), MCL 462.101 et seq., defendants appeal by right from the circuit court’s grant of summary disposition to plaintiff and judgment based thereon. We reverse and remand for further proceedings.

Plaintiff Michigan Department of Transportation (“MDOT” or “the department”) filed suit against defendant railroad companies (“the railroads”) alleging that they failed to comply with the department’s regulatory orders to repair several railroad crossings. The parties reached a settlement agreement and the case was dismissed without prejudice under its terms. As to twelve of the subject crossings, the railroads agreed that “[b]y October 15, 2013, [they] must complete all ordered work and identified work the scope of which is detailed in the attachments referenced above and correct all maintenance deficiencies to ensure the crossing complies with the Railroad Code . . . .” As to five other crossings, they agreed to fill potholes by October 15, 2013, and to complete all ordered work by August 31, 2014. When each maintenance deficiency was fixed, the railroads were required to execute and submit an “Affidavit of Completed Maintenance Work” form to MDOT, which was to re-inspect the crossings as they received the affidavits. The department was to notify the railroads of any problems and allow them an additional 30 days to fix those problems. For its part, the department agreed to dismiss its complaint without prejudice “and refrain from collecting contempt or statutory penalties unless there is a default in this Agreement.” The agreement also provided the following penalties for a “substantial[] default” by defendants:

• Railroads will pay MDOT contempt penalties of $60,000;

-1- • Railroads will waive any defense to the Action based on any applicable statute of limitations; provided, however, that the Railroads retain any and all defenses it has to any of MDOT’s claims;

• MDOT may refile its Complaint to enforce the regulatory orders;

• MDOT may refile its Complaint for statutory penalties of up to $1,000 per day for each day of noncompliance for each crossing identified above; and

• MDOT may seek any other remedy allowed by law.

Asserting that the railroads failed to make the ordered repairs even after the expiration of the October deadline, MDOT filed the instant complaint which alleged a contractual breach of the settlement agreement and restated the original claims asserting violations of the department’s regulatory orders. The department asked the trial court to: (a) assess the $60,000 contempt sanction provided for in the settlement agreement; (b) sanction defendants $7,500 for violation of the department’s order of repair pursuant to MCL 462.153 as to each of four crossings (for a total of $30,000); and (c) order defendants to pay statutory penalties of $1,000 per day for each crossing that remained unrepaired pursuant to MCL 462.441(2).

The trial court concluded, as a matter of summary disposition, that the railroads substantially breached the agreement and that, having done so, were subject to all the penalties referenced in the agreement regardless of any legal defenses to MDOT’s action to enforce its repair orders. The trial court also issued an injunction requiring that the railroads repair the crossings by August 1, 2014. Following a motion for reconsideration, the trial court issued a separate opinion clarifying that the $1,000 per day penalty would be calculated from the date of the repair orders. The railroads appealed.

We begin our review by considering the scope and effect of the settlement agreement. “An agreement to settle a pending lawsuit is a contract, governed by the legal rules applicable to the construction and interpretation of other contracts.” Reicher v SET Enterprises, Inc, 283 Mich App 657, 663; 770 NW2d 902 (2009). Interpretation of a contract is a question of law subject to de novo review on appeal. Arcambo v Lawyers Title Ins Corp, 466 Mich 402, 408; 646 NW2d 170 (2002). A party claiming a breach of contract must establish the existence of a contract, that the other party breached the contract, and that it suffered damages as a result. Dunn v Bennett, 303 Mich App 767, 774; 846 NW2d 75 (2013).

The goal of contract construction is to enforce the parties’ intent. Harbor Park Market, Inc v Gronda, 277 Mich App 126, 130; 743 NW2d 585 (2007).

[I]t is a court’s obligation to determine the intent of the parties by examining the language of the contract according to its plain and ordinary meaning. If the contractual language is unambiguous, courts must interpret and enforce the contract as written, because an unambiguous contract reflects the parties’ intent as a matter of law. However, if the contractual language is ambiguous, extrinsic evidence can be presented to determine the intent of the parties. [In re Egbert R

-2- Smith Trust, 480 Mich 19, 24; 745 NW2d 754 (2008) (citation footnotes omitted).]

The trial court erred in finding that each of the penalties sought by MDOT in this case were remedies for breach of the settlement agreement. By the terms of the settlement agreement, defendants accepted the obligation to repair the crossings as specified in that agreement and to pay $60,000 if they substantially failed to do so. However, the agreement did not provide that the railroads would be further penalized unless and until MDOT reinitiated its enforcement litigation and prevailed on the merits. Further, if and when such litigation was reinitiated, the agreement explicitly provided that the railroads would be permitted to raise any and all defenses to enforcement other than the statute of limitations.

With this understanding, we review the basis for each of the three types of sanctions imposed on the railroads by the trial court.

First, the court directed that the railroads pay MDOT a contempt sanction of $60,000. The railroads do not dispute that they agreed to pay this penalty if they “substantially defaulted” on any part of the settlement agreement. They argue, however, that the trial court erred in granting MDOT’s motion for summary disposition under MCR 2.116(C)(10) because there is a question of fact whether they did substantially default on that agreement.1 We agree.

It appears that the trial court failed to consider the meaning of “substantially default” and instead concluded that only absolute compliance would be consistent with the settlement agreement. However, substantial, not absolute, compliance was required by the terms of the settlement. Moreover, absolute compliance is not required under Michigan contract law. Notably, “Michigan follows the substantial performance rule,” P & M Constr Co v Hammond Ventures, Inc, 3 Mich App 306, 315; 142 NW2d 468, 473 (1966), which, when dealing with construction contracts, generally involves a finding of fact:

1 A motion brought pursuant to MCR 2.116(C)(10) tests the factual support of a plaintiff’s claim. Walsh v Taylor, 263 Mich App 618, 621; 689 NW2d 506 (2004).

In presenting a motion for summary disposition, the moving party has the initial burden of supporting its position by affidavits, depositions, admissions, or other documentary evidence. The burden then shifts to the opposing party to establish that a genuine issue of disputed fact exists.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Couzens
747 N.W.2d 849 (Michigan Supreme Court, 2008)
In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
Archambo v. Lawyers Title Ins. Corp.
646 N.W.2d 170 (Michigan Supreme Court, 2002)
P & M CONST. CO., INC. v. Hammond Ventures, Inc.
142 N.W.2d 468 (Michigan Court of Appeals, 1966)
Harbor Park Market, Inc v. Gronda
743 N.W.2d 585 (Michigan Court of Appeals, 2008)
Miller v. Irwin
476 N.W.2d 632 (Michigan Court of Appeals, 1991)
Quinto v. Cross and Peters Co.
547 N.W.2d 314 (Michigan Supreme Court, 1996)
Knight v. Limbert
427 N.W.2d 637 (Michigan Court of Appeals, 1988)
Walsh v. Taylor
689 N.W.2d 506 (Michigan Court of Appeals, 2004)
Reicher v. Set Enterprises, Inc
770 N.W.2d 902 (Michigan Court of Appeals, 2009)
Heather Lynn Hannay v. Department of Transportation
497 Mich. 45 (Michigan Supreme Court, 2014)
Dunn v. Bennett
846 N.W.2d 75 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Dept of Transportation v. Adrian & Blissfield Railroad Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dept-of-transportation-v-adrian-blissfield-railroad-company-michctapp-2015.