Nathan Construction Company, a Corporation v. Fenestra, Incorporated, a Corporation, Julius Novak v. Fenestra, Incorporated, a Corporation

409 F.2d 134, 1969 U.S. App. LEXIS 12885
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 10, 1969
Docket19217_1
StatusPublished
Cited by2 cases

This text of 409 F.2d 134 (Nathan Construction Company, a Corporation v. Fenestra, Incorporated, a Corporation, Julius Novak v. Fenestra, Incorporated, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nathan Construction Company, a Corporation v. Fenestra, Incorporated, a Corporation, Julius Novak v. Fenestra, Incorporated, a Corporation, 409 F.2d 134, 1969 U.S. App. LEXIS 12885 (8th Cir. 1969).

Opinion

BLACKMUN, Circuit Judge.

Fenestra, Incorporated, instituted this diversity suit against Nathan Construction Company to recover a balance of $49,817.84 claimed to be due from Nathan under a 1962 construction subcontract for windows and a curtain wall for an Omaha building. Fenestra alleged full performance on its part.

Nathan’s answer asserted that the curtain wall which Fenestra supplied was of inferior design and workmanship and did not comply with the controlling specifications in that it permitted excessive air, water and dust infiltration, it did not move freely with changing temperature and created excessive stresses and distortions, and it was improperly sealed and subject to abnormal deterioration. Nathan counterclaimed for $395,000 in damages based upon its alleged inability to fulfill its obligations to Julius Novak, the building’s owner, or, in the alternative, for indemnification against any liability on its part to Novak. Novak was permitted to intervene, under Civil Rule 24(b), as having a claim with questions of law and fact in common with Nathan. Jurisdiction is established.

The case went to trial before Chief Judge Robinson without a jury. He found that Fenestra had demonstrated substantial performance of its obligations under the subcontract; that, with substantial performance thus shown, Nathan and Novak had the burden of proving any damages which they had incurred; and that they had not sustained this burden and were not entitled to any setoff. Accordingly, judgment was entered in favor of Fenestra for the $49,817.84 balance and dismissing Nathan’s counterclaim and Novak’s claim with prejudice. Nathan and Novak appeal.

The building in question was an existing one at 3002 Farnam Street in Omaha. Novak contemplated a complete remodeling of this structure into a luxury type apartment and office building to be known as the Twin Towers Apartments. Nathan was the primary contractor for the work. Its agreement with owner Novak contained the usual provisions for compliance with specifications and, in particular, called for the installation of a curtain wall. In due course, and preliminarily, the structure’s brick facing was removed and the building reduced to its structural shell.

By the subcontract between Nathan and Fenestra the latter agreed to furnish and install windows and the curtain wall. The stated consideration was $105,000. The subcontract contained provisions, pertinent here and set forth in the footnote, * relating to workmanship, infiltration, and thermal expansion.

*136 Nathan and Novak urge that Fenestra failed to prove performance or even substantial performance according to the specifications; that even if substantial performance was shown, Fenestra did not prove the cost of remedying the difference between substantial performance and complete performance; and that the burden of proof of that cost was upon Fenestra.

Plaintiff Fenestra’s opposing argument is that if it has fully performed its contract, it is entitled to the contract price; that if it has only substantially performed, it is entitled to the contract price reduced by any damage sustained by Nathan and Novak; that the district court’s findings that Fenestra had shown substantial compliance are amply supported by the evidence; that the burden of proving damage is on Nathan and Novak; and that they have failed to sustain that burden.

The record is fairly substantial and it would serve no good purpose to review all the evidence in detail. The parties have set it forth in their briefs and are thoroughly familiar with it. It suffices for us to note and emphasize the following:

1. The curtain wall was not anything new in Omaha. Curtain walls had been used in other renovation work in the area. As Judge Robinson noted in his unreported memorandum, “Photographic

exhibits show an attractive siding material without patent deficiencies.” The exterior design was by Novak’s architect and was determined before Fenestra acquired its status as subcontractor. Fenestra prepared shop drawings. Certain adjustments in these were made in accord with conditions encountered on the site. Fenestra’s superintendent on the job worked with the contractor’s superintendent there.

2. Fenestra’s work was open and obvious. It was never told to stop its work. Representatives of the contractor and Novak himself inspected the project frequently.

3. Fenestra regarded its work as complete by June 1963. Its personnel inspected the curtain wall and detected no infiltration of air or weather.

4. Nathan, however, refused to pay the balance due on the subcontract amount. Initial meetings were held between representatives of Fenestra and Nathan and Novak to ascertain the basis of complaints which were being made and what might be done to remedy those complaints.

5. Another meeting was held in Omaha in January 1964. It was attended by Mr. Novak and representatives of Nathan and Fenestra. The building was inspected. No evidence of leakage was found.

*137 6. Another meeting took place in April. Fenestra had a weather-stripping man present to install an aluminum sample on vents. Novak watched the installation and spoke favorably of it.

7. Fenestra ordered enough material to weather strip the vents. It was instructed to install it in vacant units first. These then constituted about 25 per cent of the building. When the weatherstripping work was completed in the unoccupied apartments and in one which was occupied, a Nathan representative ordered Fenestra to stop the work and remove its crews from the building. Novak stated that a reason for this was that there was a continuous hum from the stripping. There is some dispute as to whether the stripping so installed was ever removed. Shortly after the work was stopped and during a heavy wind and rain storm Fenestra representatives inspected the building and vents. Again they found no water or air infiltration.

8. Still other meetings took place in July, August, and September 1964. These produced nothing by way of specific demonstration to Fenestra that the complaints of water and air infiltration were supported.

9. At a May 1966 meeting a complaint was made that caulking had failed. Fenestra people were unable to find evidence of caulking failure. They did note that some neophrene was loose. They also found some cracking in surface paint which they attributed to the caulking’s elastic ability to “move” with the grid system. Paint does not have this characteristic. There was also a complaint that snow had come in around one vent in an unoccupied apartment. Inspection disclosed that the vent was open. It was not known how it came to be open.

10. A final meeting took place in November 1966, almost 3% years after Fenestra’s work was completed. One sagging neophrene member and a few loose ones on the outside of the building were observed. A complaint was made that light was coming through the curtain wall. Fenestra representatives claimed the light came up into the ceiling plenum from the room below through space between the ceiling and the curtain wall. A card was inserted and pulled through the opening. Fenestra had not installed the ceiling.

11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hopkins Construction Co. v. Reliance Insurance Co.
475 P.2d 223 (Alaska Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
409 F.2d 134, 1969 U.S. App. LEXIS 12885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nathan-construction-company-a-corporation-v-fenestra-incorporated-a-ca8-1969.