Hopkins Construction Co. v. Reliance Insurance Co.

475 P.2d 223, 1970 Alas. LEXIS 206
CourtAlaska Supreme Court
DecidedSeptember 21, 1970
Docket1088
StatusPublished
Cited by6 cases

This text of 475 P.2d 223 (Hopkins Construction Co. v. Reliance Insurance Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hopkins Construction Co. v. Reliance Insurance Co., 475 P.2d 223, 1970 Alas. LEXIS 206 (Ala. 1970).

Opinion

OPINION

CONNOR, Justice.

In May, 1964, Hopkins Construction Co., plaintiff-appellant, entered into a contract with Inlet Co., Inc., defendant-appellee, to do the major portion of construction work on the Kodiak Inn, in Kodiak, Alaska. The building was completed March 27, 1965. Reliance Insurance Co. is a surety of Inlet to secure payment for material and labor.

Suit was commenced by Hopkins Construction Co. September 15, 1965, to recover from Reliance $89,980.30 claimed to be due under the surety bond. In an amended complaint, defendant Inlet was also named and the amount prayed for was increased to $133,437.22. In its answer to the amend *224 ed complaint Reliance stated as a defense that:

“Defendants allege that plaintiff has failed and neglected to perform its subcontract with Inlet Company, Inc. in accordance with the terms thereof, and that by reason of said neglect and failure, there is no obligation on the part of this defendant to pay any sum of money to plaintiff.”

In its third-party complaint against Frank Irick, owner of Kodiak Inn, filed September 1, 1966, Inlet alleged that certain changes ordered by the owner, Irick, had caused delay whereby Inlet was damaged and that Irick had failed to tender progress payments, which failure caused Inlet in turn to default in tendering its payments to Hopkins, thus precipitating this suit. To this third-party complaint Irick answered that some changes in the original plan had been made by Irick and his architect. Irick counterclaimed against Inlet alleging that Inlet had failed to perform certain of its obligations under the contract with Irick. Among other defaults and deficiencies in performance, Irick alleged that the “corridor floors on both the second and third floors are squeaky.” Inlet answered this counterclaim by alleging that the changes and modifications instigated by Irick caused delays which increased the cost of performance; that Frank Irick was to perform the earth work and failed to do it in a timely and workmanlike manner and that portions of the work left unperformed were because of failure by Irick to provide sufficient funds. That portion of the suit involving Inlet and Irick was severed. The proceedings in question here concern only Hopkins, Inlet and Reliance.

Trial to the judge without jury commenced November 22, 1966, and on November 30, 1966, was continued until February 27, 1967. In the interim certain interrogatories to defendants were propounded by Hopkins:

“Interrogatory No. One: Do the Defendants claim that the construction of the Kodiak Inn so far as applicable to the subcontract between HOPKINS CONSTRUCTION COMPANY and the Defendant, INLET COMPANY, INC. was in any way deficient?
“Interrogatory No. Two: If the answer to the above Interrogatory is in the affirmative please state the specific deficiency or deficiencies and the estimated cost to correct or cure said deficiency or deficiencies.”

To Interrogatory No. One, Inlet answered “Yes.” To Interrogatory No. Two, Inlet answered in part:

“Defendant alleges deficiencies as follows :
(1) Improper nailing and installation of floor plywood. Estimated cost of correction' is $18,000.00, plus or minus, dependent upon the extent of carpet installation and replacement.”

Judgment was entered on November 12, 1968, under which Hopkins Construction Co. was awarded $39,801.50 less the sum of $15,164.80 as a set-off, plus interest from July 2, 1965. Hopkins was also awarded $21,789.81 for allowable extras, including overhead and profit, plus interest from December 29, 1964.

Hopkins Construction Co. has appealed, claiming that the trial court erred in allowing a set-off to Inlet. We agree with Hopkins that the set-off should not have been allowed.

The case before us raises two important issues: As between Hopkins and Inlet, who has the burden of establishing the facts upon which the set-off is based; and, resolving this, has that burden been met?

BURDEN OF PROOF

It is generally agreed that once substantial performance has been shown, a construction contractor is entitled to recover the contract price, less reasonable costs of remedying the defects in work or *225 materials. 1 This rule is designed to avoid forfeitures on the part of a contractor or subcontractor who has substantially, if not perfectly, performed his contractual obligations. The rule prevents unjust enrichment by the one procuring the work, who might otherwise point to slight deficiencies, the causes of which are difficult to prove, to avoid payment of the contract price. 2 Application of this rule is consonant with placing the burden of proof on either party.

While there is general agreement as to the soundness of the substantial performance rule, consensus as to which party must sustain the burden of proving the recoupment as well as the amount is not so readily available. We realize that there is ample authority to sustain Inlet’s claim that Hopkins must bear the burden. 3 We are convinced, however, that the better of the available rules is that which places upon Inlet the burden of establishing its recoupment. 4

In United States for Use of Acme Maintenance Engineering Co. v. Wunderlich Contracting Co., 228 F.2d 66 (10th Cir.1955), the court, in a factual setting similar to this one, stated the general rule as follows:

‘¾ js a settled rule that in a subcontractor’s action against the contractor, where a substantial performance of the contract is shown, the contractor, in order to avail himself of a set-off, has the burden of proving damages sustained 0n account of defective work done by the subcontractor.” (Citations omitted.) 228 F.2d, at 68.

The practical performance of building contracts can be fraught with some complexity. It may involve various interrelated duties and performances. The determination of whether recoupment should be allowed in a given case may turn on establishing an underlying performance on the part of a person other than the subcontractor or contractor who is seeking recovery. For example, the squeaky floors in the instant case may or may not have been caused by defects in performance of the work which was supervised by Hopkins. The squeaking may have been caused by faults in the earth-moving work attributable to the owner, Irick. These defects may either have caused the under *226 mining of the foundation, or have necessitated the structural alteration of the building which in turn may have weakened it, or allowed the flooring to become damp, in turn causing warping, shrinkage and attendant squeaking.

There are practical considerations which persuade that the burden should rest with Inlet. It was Inlet’s responsibility to establish the terms of the project as a whole.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
Alaska State Housing Auth. v. Walsh & Co., Inc.
625 P.2d 831 (Alaska Supreme Court, 1980)
Lewis v. Anchorage Asphalt Paving Co.
535 P.2d 1188 (Alaska Supreme Court, 1975)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
475 P.2d 223, 1970 Alas. LEXIS 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hopkins-construction-co-v-reliance-insurance-co-alaska-1970.