Fair v. Uhr

310 S.W.2d 125, 1958 Tex. App. LEXIS 1765
CourtCourt of Appeals of Texas
DecidedJanuary 24, 1958
Docket15866
StatusPublished
Cited by8 cases

This text of 310 S.W.2d 125 (Fair v. Uhr) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fair v. Uhr, 310 S.W.2d 125, 1958 Tex. App. LEXIS 1765 (Tex. Ct. App. 1958).

Opinion

MASSEY, Chief Justice.

From a judgment in behalf of Uhr, plaintiff in a suit to recover for personal services, defendant Pair appealed.

Judgment affirmed.

The situation posed in the controversy between Messrs. Uhr and Fair is not unusual. Reduced to simplification their oral contract was one whereunder Uhr was to render personal services incident to remodeling and reconstructing Fair’s sizeable house.

For these services Fair agreed to pay an amount in cash, determinable by calculating 10% of the total amount necessary to be expended for labor and materials incident to the remodeling and reconstruction. Whenever it pleased him to do so Fair took charge of negotiating and contracting associated contracts ordinarily the obligation of a general contractor. Examples of contracts so negotiated were: the electrical contract, the plumbing contract, and the air conditioning contract.

On his part Uhr agreed to furnish certain small tools for use on the job, such as power tools, electric saws, etc., and a small truck, in addition to his services in conducting general supervision of the work. In relation to the general supervision he agreed to correlate the work of the various subcontractors (meaning the contractors with whom Fair had contracted and any with whom he had contracted in behalf of Fair) along with that of the general workmen. Also, he agreed to check the work as it was being done and as it was completed to see that it was done in a good and workmanlike manner and in accordance with instructions and plans.

The house was completed and Fair moved into it. Uhr was of the opinion that he had fully discharged the obligations cast upon him by the contract and that he was entitled to be paid the full amount in money which Fair had agreed to deliver upon completion. He had been paid approximately one-half of this sum by way of advancements, and the remaining approximate one-half claimed to be owed was something in excess of $15,000.

Fair withheld payment. His reasons therefor were premised upon two main complaints. One of these was his dispute with the air conditioning contractor, with whom he had personally contracted. He was dissatisfied with the performance of the air conditioning units installed pursuant to that contract, which was for an amount certain in money. A suit was pending between Fair and the air conditioning contractor who had not yet been paid. The other of the reasons was the matter of claimed defects in certain workmanship. A part thereof was workmanship performed by contractors with whom Fair himself had contracted and who had been paid in full by him. Examples of these alleged defects were: (1) In at least two places the hot water and cold water pipes had been mis-connected so that hot water flowed from cold water taps and vice versa; (2) a “water-hammer” existed in at least one pipe which made a noise when the water was running; (3) flooring in a “play-room” was caused to warp, etc., because of an excess in humidity resulting from the air conditioning; (4) some doors did not fit closely as the result of being improperly hung in their frames or because not cut so as to properly fit in their frames; (5) some glass “thermo-panes” were either defective or defectively installed since they frosted over contrary to the purpose for which installation had been ordered; (6) insulation in a part of the attic not completed.

While not necessary to this opinion it is to be noted that there was an additional defect created by the sinking of a part of the foundation under a carport. The cause was the location thereof near an abandoned *127 cesspool. The cost of remedying this defect was established in the evidence and a deduction made by reason thereof from the amount awarded Uhr in the judgment, of which Uhr does not complain.

Shortly after the time when Uhr believed his performance to have been complete, and after Fair had moved into the premises, Uhr and the architect were called out to the premises. At that time Fair demonstrated certain defects which he believed should be remedied, in particular the doors. Uhr agreed to get to work correcting the defects complained of. Fair asked that he delay any corrective action until the following month when he and his wife would be away from the house. Thereafter Fair discovered other defects and circumstances relative to the construction of' his house which caused him to lose confidence in Uhr, and, as he testified, he had no further contact with Uhr other than through the exchange of letters. Workmen who went to correct certain defects were told not to proceed when their services were proffered.

Within a month or two written demand and notice in the form of a letter was served upon Fair by Uhr showing the amount of his claim. Fair replied stating that “once you complete the job in a workmanlike manner, I will be glad to make a settlement with you.” To this letter Uhr replied in an answer to Fair stating, “Would you be kind enough by return mail to enumerate for me the things that you believe to be incomplete, and not done in a workmanlike manner?” Fair did not respond.

Shortly thereafter the entire matter was turned over to their attorneys by the respective parties. Through his attorney Uhr filed suit for the balance owing for personal services plus attorneys’ fees. For our purposes it is to be noted that Fair’s answer contained a general denial plus allegations of defective workmanship and defective performance, particularized only in the matter of the air conditioning system, with a counter-plea for damages in the sum of $100,000.

After the suit was filed and before trial Uhr’s attorneys took the deposition of Fair. During the course of its taking, Fair was asked to supply a list detailing work, etc., he contended should be attended in order that the job on his house would be complete. Fie was unable to give information relative thereto other than in the most general terms, and in response to the request represented that he would furnish the list. This was not furnished to date of the trial. At time of the foregoing promise he stated that he should have such a list from his “engineer” in a few days. At date of the trial he admitted that the promise had been made and that the list had not been furnished. He reiterated in the course of testifying on trial that he would furnish the list, using the following words, “I still hope to, but unfortunately the engineer is sick this morning and he can’t be here.” He testified that his engineer had such a list and that he had seen it, but that he did not have the list, having hired the engineer to make it and to present it to the court. The list was never forthcoming during the course of the trial, and other than for the description of defects in the most general terms on the part of Fair and his witnesses the record leaves the conditions complained of in a highly nebulous and undetermined state.

In our view the contentions of Fair embrace allegations of defective workmanship and materials, which if proved would at least entitle him to a credit upon the amount, if any, owing to Uhr. Yet he fails to disclose what such defects are contended to be in a way and manner whereby they and the cost of any remedy thereof could be ascertained and weighed and tested according to the forms of law. He relies upon the case of Atkinson v. Jackson Bros., Tex. Com.App.1925, 270 S.W. 848, 38 A.L.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clear Lake City Water Authority v. Friendswood Development Co.
344 S.W.3d 514 (Court of Appeals of Texas, 2011)
ACG, INC. v. Southeast Elevator, Inc.
912 S.W.2d 163 (Court of Appeals of Tennessee, 1995)
Kemmons Wilson, Inc. v. Allied Bank of Texas
836 S.W.2d 104 (Court of Appeals of Tennessee, 1992)
Opinion No.
Texas Attorney General Reports, 1988
Burditt v. Sisk
710 S.W.2d 114 (Court of Appeals of Texas, 1986)
Hopkins Construction Co. v. Reliance Insurance Co.
475 P.2d 223 (Alaska Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
310 S.W.2d 125, 1958 Tex. App. LEXIS 1765, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fair-v-uhr-texapp-1958.