ACG, INC. v. Southeast Elevator, Inc.

912 S.W.2d 163, 1995 Tenn. App. LEXIS 452
CourtCourt of Appeals of Tennessee
DecidedJuly 13, 1995
StatusPublished
Cited by45 cases

This text of 912 S.W.2d 163 (ACG, INC. v. Southeast Elevator, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACG, INC. v. Southeast Elevator, Inc., 912 S.W.2d 163, 1995 Tenn. App. LEXIS 452 (Tenn. Ct. App. 1995).

Opinion

OPINION

McMURRAY, Judge.

In this contract dispute, the trial judge found that ACG, Inc., the general contractor for construction of the “Courts Building” in Chattanooga, had breached its duty to Southeast Elevator, a subcontractor, and awarded damages. On appeal ACG argues, inter alia, that the trial court erred in finding that it breached its contract by violation of an implied condition of good faith. We affirm the trial court.

The chancellor issued his memorandum opinion and order. Our view of the case persuades us that the memorandum opinion and order of the chancellor accurately reflects the facts of the case. We therefore, adopt his introductory statement and the statement of the facts which in pertinent part are as follows:

INTRODUCTION
... Each of the parties were involved with the construction of the Courts Building in Chattanooga, Hamilton County, Tennessee. (1989-1991). Two suits were filed in regard to this dispute and there were *165 counterclaims and/or cross-claims filed in each. Thus, the court will refer to the parties in the capacity in which they were involved with the construction of the Courts Building
Monies are sought against ACG, Inc., the general contractor, by both Southeast Elevator, Inc., a subcontractor, and Murphy-Adcock Elevator Shaft Drilling, a drilling contractor brought in to expedite necessary drilling work. Murphy-Adcock also makes a claim for payment against Southeast either jointly or alternatively. Both ACG and Southeast concede Murphy-Adcoek should be paid, but each contends the other should be responsible for payment. Southeast Elevator also seeks recovery from ACG the retainage that was never paid to it and seeks $16,000.00 in damages. 1 ACG, Inc., seeks indemnity from Southeast in the event it is held liable to Murphy-Adcock. It also claims that it is entitled to attorney’s fee from Southeast.
Murphy-Adcock was not involved in the original contract nor any of the subcontracts on this project. It was brought into the work at a later time upon the direct request of Southeast with the knowledge and, at least, acquiescence and the indirect request of ACG, Inc. It performed its specialized drilling work on three of the elevator sites in the Courts Building expeditiously and without complaint from any other involved parties.

FACTS

In June, 1989, ACG, Inc., was awarded the general contract to construct the Hamilton County Courts Building. It entered into a subcontract with, among others, Southeast Elevator Company, Inc. This subcontract involved the necessary work to install five hydraulic elevators in the building for a total contract price of $229,346.00.
The installation of the hydraulic elevators required the drilling of rather deep (45' — 65') holes into the ground for the hydraulic cylinders. Such drilling can be accomplished by “outside” drilling prior to the construction of the building or by “inside” drilling after the building has been roofed and dried in. “Outside” drilling is performed early in the overall construction and must be done soon after the site is brought to grade and before any real construction begins on the structure itself. It can be done by a well drilling rig mounted on the back of a truck which is driven onto the site over the location of the hole to be drilled. But it cannot be performed if portions of the building have been completed so as to block or substantially impede the drilling rig’s access to the site of the holes to be dug. It must then be done by inside drilling with a portable drill rig suspended in the constructed elevator shaft.
After signing its subcontract, Southeast Elevator made arrangements to obtain the necessary holes by “outside” drilling by an experienced well driller, Mr. Jack Terry. :jc
Despite Southeast Elevator’s expectations, construction proceeded to the point where outside drilling became impossible. No notice had been given Southeast Elevator to begin its work.
% sji sj: #
Due to the progress at the job site, Southeast Elevator, Inc. had to wait until the building was erected before they could commence drilling the necessary cylinder holes. ‡ $
Southeast Elevator, Inc. had done some inside drilling previously at other sites, but investigated the possibility of bringing in another contractor to do the inside drilling when they realized outside drilling was no longer possible. Mr. Clark, President of Southeast Elevator, Inc., contacted Murphy-Adcock and ascertained that it had the capability to perform inside drilling *166 much more efficiently and quickly than Southeast. The price, however, would have been $230.00 per foot and Southeast Elevator, Inc. had made its original bid based upon a cost factor of $120.00 per foot that Mr. Terry had given.
At the appropriate time, Southeast Elevator commenced inside drilling and it completed two of the holes before starting the hole for elevator number 3. The inside drilling process is slow and rock was encountered in the holes and such had not been anticipated. Thus, Southeast got behind schedule. At the same time, the entire project was months behind schedule and ACG was putting pressure on the various subcontractors, including Southeast Elevator, to expedite the work. Southeast Elevator advised Mr. Middleton, Vice President of ACG, of the capabilities of Murphy-Adcock to drill the holes much faster than it could. The preponderance of the evidence, at the very least, establishes that Mr. Middleton was advised of the prices of Murphy-Adcock and of the fact that Southeast Elevator would be unable to pay the prices of Murphy-Adcock. Nevertheless, Mr. Middleton told Mr. Clark to get Murphy-Adcock on the job.
Hs # # # sH ^
Murphy-Adcock was promptly contacted and brought on to the job; it finished drilling the holes in a reasonable amount of time. Considerable difficulties were encountered, however, at the hole for number 3 which had been started by Southeast Elevator, Inc. Such was out of plumb and it required three additional drillings by Murphy-Adcock to make the holes perfectly in line. When an “out of plumb” hole occurs, usually the drilling contractor suffers the loss of the increased expense. Hole # 3 had to be “straightened” by Murphy-Adcock and additional “daily” charges were made as it was not the original contractor.
Murphy-Adcock stated that it came on to the job site to drill the holes because of the representations by Southeast Elevator that ACG would pay the bill or reimburse them for their services. Nevertheless, after Murphy-Adcock finished its drilling, it made out invoices to Southeast Elevator and mailed them to Southeast Elevator. Rather than forwarding the invoices to ACG and requesting payment thereof, Southeast Elevator submitted such as a part of an application, or request, for a change order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BILL W. GENTRY v. CINCO RESEARCH CORPORATION
Court of Appeals of Tennessee, 2025
F & M Bank v. George Raymond Fleming, Jr.
Court of Appeals of Tennessee, 2021
Carl Allen v. Joseph S. Ozment
Court of Appeals of Tennessee, 2018
Damon Holland v. Brian Sullivan
Court of Appeals of Tennessee, 2017
Chuck's Package Store v. City of Morristown
Court of Appeals of Tennessee, 2016
Hanna (John) Nazi v. Jerry's Oil Company Inc.
Court of Appeals of Tennessee, 2014
Young ex rel. estate of Young v. Kennedy
429 S.W.3d 536 (Tennessee Supreme Court, 2013)
Eddie C. Pratcher, Jr. v. Methodist Healthcare Memphis Hospitals
407 S.W.3d 727 (Tennessee Supreme Court, 2013)
Dick Broadcasting Company, Inc. of Tennessee v. Oak Ridge FM, Inc.
395 S.W.3d 653 (Tennessee Supreme Court, 2013)
Hometown Folks, LLC v. S & B WILSON, INC.
643 F.3d 520 (Sixth Circuit, 2011)
Moody Realty Co., Inc. v. Huestis
237 S.W.3d 666 (Court of Appeals of Tennessee, 2007)
Moody Realty Company, Inc. v. Ronald L. Huestis
Court of Appeals of Tennessee, 2007
Harper-Wittbrodt Automotive Group, LLC v. Sam Teague
Court of Appeals of Tennessee, 2006
Faust v. Metropolitan Government of Nashville
206 S.W.3d 475 (Court of Appeals of Tennessee, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
912 S.W.2d 163, 1995 Tenn. App. LEXIS 452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acg-inc-v-southeast-elevator-inc-tennctapp-1995.