United States Ex Rel. E & R Construction Co. v. Guy H. James Construction Co.

390 F. Supp. 1193, 21 Cont. Cas. Fed. 84,094, 20 Fed. R. Serv. 2d 572, 1972 U.S. Dist. LEXIS 12110
CourtDistrict Court, M.D. Tennessee
DecidedSeptember 5, 1972
DocketCiv. A. 504
StatusPublished
Cited by26 cases

This text of 390 F. Supp. 1193 (United States Ex Rel. E & R Construction Co. v. Guy H. James Construction Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. E & R Construction Co. v. Guy H. James Construction Co., 390 F. Supp. 1193, 21 Cont. Cas. Fed. 84,094, 20 Fed. R. Serv. 2d 572, 1972 U.S. Dist. LEXIS 12110 (M.D. Tenn. 1972).

Opinion

MEMORANDUM OPINION

MORTON, District Judge.

This action was commenced on September 28, 1967, by plaintiff E & R Construction Co., Inc. based upon the provisions of the Miller Act, 40 U.S.C. §§ 270a and 270b. The plaintiff is an Ohio corporation. Defendant, Guy H. James Construction Company, is an Oklahoma corporation, and defendant Federal In *1199 surance Company is a New Jersey corporation which is authorized by the United States to write performance and payment bonds under the terms of the Miller Act.

On June 26, 1964, defendant Guy H. James Construction Company (hereinafter “James”) entered into a prime contract with the United States Corps of Engineers providing for the construction of a project in Tennessee known as Cor-dell Hull Lock and Dam, consisting of a lock and dam on the Cumberland River, including items applicable to this action as follows:

(1) Construction of a lock with cofferdam surrounding the entire work-site, with an elevation of 480 feet around the lock excavation area, referred to as Stage I.
(2) Construction of a cofferdam around lower approach channel to an elevation of 456 feet, referred to as Stage II.
(3) Common excavation, consisting of removal of all earth, including the cofferdam, to final elevations, according to plans of U. S. Corps of Engineers.

The James contract was a successor to earlier contracts held by other parties for the initial excavation and construction of a cellular cofferdam in the dam area, and for road construction and site preparation, and preceded a subsequent contract for the completion of the dam and for construction of the powerhouse.

James, as principal, and Federal Insurance Company (hereinafter “Federal”), as surety, executed to the United States separate bonds, each in a penalty sum of $2,500,000, with performance bond conditioned for faithful performance of the contract, and payment bond conditioned for payment of all labor and material used in prosecution of the contract work.

On July 1, 1964, E & R Construction Company (hereinafter “E & R”) entered into a subcontract with James for what may be described generally as the execution of the earth-moving or dirt excavation items under the prime contract. (A copy of the subcontract is included in the Appendix to this ^ninion.)

The position of the prime contract undertaken by plaintiff can be more particularly described as follows:

Item No. Description Estimated Quantity Unit Price Amount

1 Mobilization & Preparatory Work Lump Sum $ 17,900

2 Lock Cofferdam 100,000 c.y. 0.64 64,000

5 Clearing & Grubbing Lump Sum 11,000

6 Common Excavation 1,480,000 c.y. 0.64 947,200

15 Filter Drainage Layer 5,200 c.y. 5.28 27,456

16a Compacted Impervious Fill 86,000 c.y. 0.14 12,040

17 Random Fill 103,000 c.y. 0.08 8,240

18 Coarse Rock Fill 8,100 c.y. 2.00 16,200

19 Fine Rock Fill 2,000 c.y. 2.00 4,000

20 12-inch Concrete Pipe 200 l.f. 4.00 1,040

21 15-inch Concrete Pipe 240 l.f. 5.00 1,200

22 Bedding for Riprap 7,500 c.y. 5.28 39,000

23 Riprap 24,500 c.y. 1.50 36,750

$1,187,266 1

*1200 The cofferdam system which was utilized on the project was referred to as being in four parts: the “upstream” 480 dike, meaning an elevation of 480 feet; the “downstream” 480 dike; the downstream 456 dike (sometimes referred to as the 460 dike); and the cross-dike. The terms “upstream” and “downstream” are used in relation to a cellular cofferdam that had been constructed under a preceding contract. Stage I of the project refers to the upstream portion of the work; Stage II refers to the downstream portion of the work. 2 The removal of the 456 and 480 dikes, which was accomplished during the latter part of the work, is sometimes referred to as Stage III.

During the first part of the job E & R was responsible for the removal or excavation of the overburden on the rock underlying the Stage I area and the construction of the 480 dike; during the second part of the job E & R was responsible for the excavation or removal of the overburden on the rock underlying the Stage II area and the construction of the 456 dike; during the final part of the job E & R was responsible for the general maintenance of the dike system, and the eventual removal of the 456 dike, the 480 dikes, and the cross-dike.

The excavation or removal operations by E & R were planned as a use of certain mobile equipment and a dredge that E & R had purchased for this purpose. Stage I excavation was primarily completed with automotive-type earth-moving equipment, although towards the end of this stage a dredge was used to assist in the disposal of Stage I material. Stage II excavation, although begun at higher elevations with automotive-type equipment, was primarily a dredging operation. Stage III, the removal of cofferdams and dikes, was also primarily done by dredge. Stage II was begun before Stage I was completed, but there was a substantial time interval between the completion of Stage II and the commencement of Stage III.

This action is based on twelve separate claims or “items.” Plaintiff claims James materially breached the parties’ contract and that plaintiff is entitled to recover in quantum meruit, or, in the alternative, entitled to recover for the damages incurred.

STATUTE OF LIMITATIONS DEFENSE

Defendants maintain that several items, i.e., Items (b), (c), .(e), (f), (g), (h), (j), and (1) of No. 7 of plaintiff’s amended complaint were asserted as claims against defendants for the first time in the amended complaint, filed on September 22, 1971, and they are barred by the one-year statute of limitations, 40 U.S.C. § 270b. Therefore, the threshold question for the court’s determination is whether the alleged new claims asserted by plaintiff in the amended complaint are barred by the one-year statute of limitations provision in 40 U.S.C. § 270b which provides, in part:

“(b) ... no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied . . . .”

Defendants contend that in the original complaint filed in this action on September 28, 1967, plaintiff was proceeding on a theory of breach of contract and sought damages therefor. On September 22, 1971, plaintiff filed a motion to amend the complaint and specifically referred to seeking damages and recovery against the defendants for several items of claim on the basis of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waste Servs. of Decatur, LLC v. Decatur Cnty.
367 F. Supp. 3d 792 (W.D. Tennessee, 2019)
United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)
Sparton Technology, Inc. v. Util-Link, LLC
248 F. App'x 684 (Sixth Circuit, 2007)
D.H. Blattner & Sons, Inc. v. N.M. Rothschild & Sons, Ltd.
55 P.3d 37 (Alaska Supreme Court, 2002)
AMC-Tennessee, Inc. v. Hillcrest Healthcare
Court of Appeals of Tennessee, 1997
ACG, INC. v. Southeast Elevator, Inc.
912 S.W.2d 163 (Court of Appeals of Tennessee, 1995)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)
W.S.A. Inc. v. Stratton
680 F. Supp. 375 (S.D. Florida, 1988)
Federal Deposit Insurance v. Chizner
110 F.R.D. 114 (E.D. New York, 1986)
Hartford Accident & Indemnity Co. v. District of Columbia
441 A.2d 969 (District of Columbia Court of Appeals, 1982)
Action Engineering v. Alumina
18 V.I. 485 (Virgin Islands, 1981)
Blake Construction Co. v. C. J. Coakley Co.
431 A.2d 569 (District of Columbia Court of Appeals, 1981)
Knight v. Carlson
478 F. Supp. 55 (E.D. California, 1979)
Newark Motor Inn Corp. v. Holiday Inns, Inc.
472 F. Supp. 1143 (D. New Jersey, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
390 F. Supp. 1193, 21 Cont. Cas. Fed. 84,094, 20 Fed. R. Serv. 2d 572, 1972 U.S. Dist. LEXIS 12110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-e-r-construction-co-v-guy-h-james-construction-tnmd-1972.