Blake Construction Co. v. C. J. Coakley Co.

431 A.2d 569, 1981 D.C. App. LEXIS 299
CourtDistrict of Columbia Court of Appeals
DecidedMay 27, 1981
Docket79-1225, 79-1229
StatusPublished
Cited by47 cases

This text of 431 A.2d 569 (Blake Construction Co. v. C. J. Coakley Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blake Construction Co. v. C. J. Coakley Co., 431 A.2d 569, 1981 D.C. App. LEXIS 299 (D.C. 1981).

Opinion

KERN, Associate Judge:

This case is, in essence, a dispute between a subcontractor and a contractor concerning a partially completed subcontract on a major construction project. We affirm the trial court’s decision on all issues except the calculation of the award of damages.

Appellees in No. 79-1229 and appellants in No. 79-1225, Blake Construction Co., Inc. (Blake) and U.S. Industries, Inc. (USI), as joint venturers, bid on and were awarded a contract as the general contractor by the United States, Department of the Army, Baltimore District, Corps of Engineers (the government), for the construction of the “New Walter Reed Hospital” in the District of Columbia. Blake was the managing partner of the joint venture. The contract (also referred to as the “prime contract”) was entered into on July 28, 1972, in the amount of $102,321,000.

The remaining appellee in No. 79 — 1229 and appellant in No. 79-1225, the Aetna Casualty and Surety Company (Aetna), executed performance and payment bonds regarding this contract as surety for Blake and USI.

Appellant in No. 79-1229 and appellee in No. 79-1225, C. J. Coakley Co., Inc. (Coak-ley), is engaged in the business, inter alia, of fireproofing structural steel in buildings under construction. Blake had obtained a bid from Coakley, prior to submitting its bid for the prime contract to the government, for $638,500 for the spray fire-proofing work called for under the government’s specifications for the Hospital.

After entering into the prime contract with the government, Blake informed Coak-ley that its initial bid was too high and that work to be performed now included the installation and fireproofing of tubes around hangar rods in the interstitial floors. 1

After a physical inspection of the job site by its President, Cornelius Coakley, Coakley executed a subcontract with Blake-USI for the fireproofing work on July 9,1974, in the amount of $570,000.

None of the above facts have been contested by any party in this litigation, which resulted in a trial without a jury and then the instant appeal.

*572 The trial court, after a lengthy trial, issued Findings of Fact, Conclusions of Law and Order dated November 5, 1979, which, in brief, found Blake, et al., in breach of contract. The trial judge made a number of findings of fact concerning provisions in the various contractual documents involved in this case.

Specification 9K of the prime contract required that the structural steel be fireproofed in accordance with the details contained in the specifications. Specification 9K/6.6 provided:

Ducts, piping or conduit or other suspended equipment that could interfere with the uniform application of the fireproofing material are to be positioned after the application of the sprayed fireproofing. [Record at 806; emphasis added.]

Article 1(a) of Coakley’s subcontract with Blake-USI expressly incorporated the provisions of Specification 9K of the government specifications in the prime contract. (Record at 806.)

Coakley’s subcontract contained a provision, at Article 1(a), that required it to perform in “full and complete accordance” with the “Contract Documents,” which included all the specifications and drawings, including addenda thereto, prepared by the architect which form a part of the prime contract. (Record at 806.)

The subcontract also obligated Blake to provide all heat free of charge that was necessary to heat tarpaulin enclosures provided by Coakley. (Record at 817; no subcontract provision cited.)

Blake was obligated to Coakley, if “satisfactory progress is being made in the execution of this contract,” to make “partial payments in accordance therewith as payments are made by the Owner [the government] (Subcontract Article 4(a)).” (Record at 819.)

In Article 2(b), the subcontract said, “[N]o such delay [caused by reasons beyond the Subcontractor’s control] shall give rise to any right to the Subcontractor to claim damages therefor from the Contractor.” (Record at 816.)

Article 2(a) required Coakley to prosecute its work “in accordance with progress schedules prepared and issued to the Subcontractor by the Contractor” and Article 2(b) provided that the progress schedules might be changed from time to time and afforded the Subcontractor a right to request in writing from the Contractor extensions of time in which to perform under the subcontract. (Record at 815-16.)

Article 23(a) of the Subcontract stated: The Contractor, without in any way invalidating this contract, shall have the right to make contemplated and/or actual changes, additions, and/or omissions in the work, upon written order to the Subcontractor. The Subcontractor shall thereupon promptly submit an itemized estimate of the value of the work involved and shall, if so directed by the Contractor, proceed diligently to prosecute the work so ordered. Upon determination, by the Contractor, of the value of the work involved, the Contractor will issue a Change Order to the Subcontractor, adjusting the contract sum accordingly. (Record 816.)

The trial court also found that fireproofing is a process of spraying a water-saturated mixture of gypsum, vermiculite and other additives onto structural steel, rods and tubes. This substance dries into a soft material which is quite susceptible to abrasion and water damage. The application of fireproofing should be made with spray nozzles at a uniform optimum distance from the structural steel. Interrupted application of the fireproofing causes the material to congeal inside the spray nozzle, which in turn makes the spray nozzle less efficient or inoperable until it is cleaned.

Fireproofing spray that does not adhere to the applied surface falls to the ground and must be removed. Spraying at a greater or less than optimum distance increases the amount of fireproofing that does not adhere, thus increasing both material and clean-up costs. Several applications of fireproofing were generally required to satisfy government requirements. The fireproofing material will dry on the structural steel *573 at a rate that is determined by the temperature and humidity. (Record at 811, 812 and 817.)

The incorporation of interstitial floors (see note 1, infra), is provided for in the design of the Hospital. Neither Blake nor Coakley had ever had experience with a building which had interstitial floors. The structural steel supports of the interstitial floors were to be fireproofed under the subcontract. Coakley assumed in preparing, at the request of Blake, its revised bid on the subcontract that its workmen could stand on the interstitial floors while applying the fireproofing to certain surfaces. (Record at 805-06 and 318.)

After signing the subcontract with Coak-ley and in accordance with Article 9(a) of the prime contract, Blake prepared a Critical Path Method work progress and sequence plan (CPM). (Record at 806-08.) The work sequence on the Hospital soon was at considerable variance with that projected by the CPM prepared by Blake.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Landis v. Tailwind Sports Corp.
234 F. Supp. 3d 180 (District of Columbia, 2017)
A Love of Food I, LLC v. Maoz Vegetarian USA, Inc.
70 F. Supp. 3d 376 (District of Columbia, 2014)
ARMENIAN ASSEMBLY OF AMERICA, INC. v. Cafesjian
746 F. Supp. 2d 55 (District of Columbia, 2010)
Jones v. HARTFORD LIFE AND ACCIDENT INSURANCE COMPANY
443 F. Supp. 2d 3 (District of Columbia, 2006)
Hirth v. Estate of Warris
77 Pa. D. & C.4th 449 (Bucks County Court of Common Pleas, 2005)
American Service Center Associates v. Helton
867 A.2d 235 (District of Columbia Court of Appeals, 2005)
Kwang Dong Pharmaceutical Co. v. Myun Ki Han
205 F. Supp. 2d 489 (D. Maryland, 2002)
Keeney Construction v. James Talcott Construction Co.
2002 MT 69 (Montana Supreme Court, 2002)
Manganaro Corp. v. HITT Contracting, Inc.
193 F. Supp. 2d 88 (District of Columbia, 2002)
Souci v. William C. Smith & Co.
763 A.2d 96 (District of Columbia Court of Appeals, 2000)
Goldsmith v. Tapper
748 A.2d 416 (District of Columbia Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
431 A.2d 569, 1981 D.C. App. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blake-construction-co-v-c-j-coakley-co-dc-1981.