Keeney Construction v. James Talcott Construction Co.

2002 MT 69, 45 P.3d 19, 309 Mont. 226, 2002 Mont. LEXIS 83
CourtMontana Supreme Court
DecidedApril 4, 2002
Docket01-430
StatusPublished
Cited by3 cases

This text of 2002 MT 69 (Keeney Construction v. James Talcott Construction Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keeney Construction v. James Talcott Construction Co., 2002 MT 69, 45 P.3d 19, 309 Mont. 226, 2002 Mont. LEXIS 83 (Mo. 2002).

Opinion

JUSTICE REGNIER

delivered the Opinion of the Court.

¶1 Keeney Construction filed a complaint against James Talcott Construction Company, Inc. (Talcott), for delay, disruption and extra work. Keeney filed an Amended Complaint seeking similar damages *227 against the project owner, the University of Montana (the “UM”), and against Safeco Insurance Company (Safeco) under Safeco’s surety bond issued to Talcott. The Fourth Judicial District Court, Missoula County, granted partial summary judgment in favor of Talcott and Safeco on all of Keeney’s delay, disruption and interference claims that Keeney based on an allegation that it had an early completion date of October 31,1996, and on a claim of an additional manhole. Keeney appeals and we affirm.

¶2 The following issues are dispositive of this appeal:

¶3 1. Did the parties intend that Keeney should complete its work under the Subcontract by late December 1996?

¶4 2. Do the express terms of the Subcontract bar Keeney’s claims for delay?

¶5 3. Did Keeney provide proper notice of its claims under the dispute resolution provision of the contract?

BACKGROUND

¶6 On August 14, 1996, the University of Montana, in Missoula, Montana, solicited bids from contractors for a project known as the Family Housing Phase II (“Phase II”). On that same day, Keeney faxed a bid for site work items under the General Contract to Talcott. The UM awarded the General Contract to Talcott on August 23,1996. The General Contract contained an initial completion date of May 31,1997.

¶7 On August 27, 1996, representatives from Keeney and Talcott attended a preconstruction meeting to discuss issues that could affect the project’s success. At the meeting, Talcott’s project manager presented a prehminary bar chart schedule that showed a September 3 start date and a December 1996 finish date. Two days later, on August 29, 1996, Keeney and Talcott entered into a Standard Subcontract Agreement (the “Subcontract”). Under the Subcontract, Keeney agreed to prepare the initial site, install water and sewer lines, prepare subgrade for roads and parking areas and pour concrete curbs, gutters and sidewalks.

¶8 Jerry Taylor, the project architect, sent a letter, dated September 10, 1996, to Talcott stating that the UM did not want an early completion date. In the letter, Taylor also requested that Talcott prepare a schedule to reflect the full contract period. On October 24, 1996, the UM and Talcott entered into a change order, which added three additional four-plex units to the project (“Phase III”) and extended the overall completion date to July 31, 1997. The change order also extended the completion date for Phase II by a month, to June 30,1997. Keeney did not do any work on Phase III. Some dispute remains about when Keeney finally completed its portion of the work, *228 but Taylor ultimately issued a Certificate of Substantial Completion on October 1,1997.

¶9 On July 23, 1998, Keeney filed a complaint against Talcott for various damages, including delay and extra work. Talcott filed an Answer on September 30, 1998 and an Amended Answer on October 9, 1998. On February 24, 1999, Keeney amended its Complaint to include the State of Montana, through the UM, and Safeco as defendants. On August 3, 2000, Talcott and Safeco filed a Motion for Partial Summary Judgment against Keeney’s claims that it had an early completion date of October 31, 1996, and three claims that it performed extra work. The UM subsequently filed a Motion for Summary Judgment on September 22,2000. In an order dated October 11, 2000, the District Court granted the Motion for Partial Summary Judgment and the UM’s Motion for Summary Judgment. Keeney appeals the portion of the court’s Order granting partial summary judgment to Talcott and Safeco but does not appeal the portion granting summary judgment to the UM.

STANDARD OF REVIEW

¶10 We review a district court’s order granting summary judgment de novo, applying the same evaluation as the district court pursuant to Rule 56, M.R.Civ.P. See Vivier v. State Dep’t of Transp., 2001 MT 221, ¶ 5, 306 Mont. 454, ¶ 5, 35 P.3d 958, ¶ 5; Bruner v. Yellowstone County (1995), 272 Mont. 261, 264, 900 P.2d 901, 903. In Bruner, we stated that:

The movant must demonstrate that no genuine issues of material fact exist. Once this has been accomplished, the burden then shifts to the non-moving party to prove, by more than mere denial and speculation, that a genuine issue does exist. Having determined that genuine issues of fact do not exist, the court must then determine whether the moving party is entitled to judgment as a matter of law. We review the legal determinations made by a district court as to whether the court erred.

Bruner, 272 Mont. at 264-65, 900 P.2d at 903 (citations omitted).

ISSUE ONE

¶11 Did the parties intend that Keeney should complete its work under the Subcontract by late December 1996?

¶12 We must interpret the intent of parties to a contract from only the contract when the terms are unambiguous. See Habets v. Swanson, 2000 MT 367, ¶ 13, 303 Mont. 410, ¶ 13, 16 P.3d 1035, ¶ 13. “An ambiguity exists when the contract taken as a whole in its wording or phraseology is reasonably subject to two different interpretations.” *229 Wray v. State Compensation Ins. Fund (1994), 266 Mont. 219, 223, 879 P.2d 725, 727 (quoting Morning Star Enters, v. R.H. Grover, Inc. (1991), 247 Mont. 105, 111, 805 P.2d 553, 557). Whether a contract is ambiguous is a question of law that a court must decide. See Carelli v. Hall (1996), 279 Mont. 202, 209, 926 P.2d 756, 761.

¶13 Here, the language of the Subcontract contains no ambiguity. The Subcontract stated that Keeney agreed “[t]o complete the work of this Subcontract as required by job progress or within the following time limits: As directed by James Talcott Construction, Inc. Time is of the essence on this project.” The Subcontract, therefore, clearly states that Keeney agreed to work at the direction of Talcott. Although the General Contract initially set May 31,1997, as the overall completion date of Phase II, the Subcontract governs “[w]here any provision of the General Contract Documents between the Owner and the Contractor is inconsistent with any provision of this [Subcontract].” Thus, the Subcontract clearly authorized Talcott to set Keeney’s completion schedule. Cf. McDaniel v. Ashton-Mardian Co. (9th Cir. 1966), 357 F.2d 511

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zirkelbach Construction, Inc. v. DOWL, LLC
2017 MT 238 (Montana Supreme Court, 2017)
Hajenga v. Schwein
2007 MT 80 (Montana Supreme Court, 2007)
King Resources, Inc. v. Oliver
2002 MT 301 (Montana Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2002 MT 69, 45 P.3d 19, 309 Mont. 226, 2002 Mont. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keeney-construction-v-james-talcott-construction-co-mont-2002.