Zirkelbach Construction, Inc. v. DOWL, LLC

2017 MT 238, 402 P.3d 1244, 389 Mont. 8, 2017 WL 4274179, 2017 Mont. LEXIS 591
CourtMontana Supreme Court
DecidedSeptember 26, 2017
DocketDA 16-0745
StatusPublished
Cited by1 cases

This text of 2017 MT 238 (Zirkelbach Construction, Inc. v. DOWL, LLC) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zirkelbach Construction, Inc. v. DOWL, LLC, 2017 MT 238, 402 P.3d 1244, 389 Mont. 8, 2017 WL 4274179, 2017 Mont. LEXIS 591 (Mo. 2017).

Opinion

JUSTICE WHEAT

delivered the Opinion of the Court.

*9 ¶1 Zirkelbach Construction, Inc. (Zirkelbach) appeals from the order of the Thirteenth Judicial District Court, Yellowstone County, granting DOWL, LLC’s (DOWL) motion for partial summary judgment. We affirm.

¶2 We restate the issue on appeal as follows:

Did the District Court err in granting DOWL’s motion for partial summary judgment ?

FACTUAL AND PROCEDURAL BACKGROUND

¶3 This case arises out of the construction of a F edEx Ground facility (Facility) in Billings, Montana. SunCap Billings, LLC (SunCap) is the owner of the real property upon which the Facility was to be constructed. SunCap hired Zirkelbach as the general contractor to construct the Facility. Zirkelbach is an experienced construction company maintaining offices in Florida, South Carolina and Montana. The construction of the Facility was Zirkelbach’s forty-second project for FedEx. Zirkelbach hired DOWL to provide design work for the Facility. Likewise, DOWL is an experienced, professional design company.

¶4 Zirkelbach and DOWL entered into an agreement 1 for professional services (Agreement). Both parties presented their own form contracts, but ultimately, DOWL’s form contract was agreed upon and signed by both parties. The Agreement provided for Zirkelbach to pay DOWL $122,967 for services rendered. Subsequently, the parties made several addenda to the Agreement. The subsequent addenda raised the fee for any additional services being rendered by DOWL. DOWL’s final fee for its services relating to the design of the Facility totaled approximately $665,000.

¶5 Sub-section 5(D) of the Agreement between Zirkelbach and DOWL provides as follows:

D. Consequential Damages/Limitation of Liability
To the fullest extent permitted by law, DOWL HKM and Client waive against each other, and the other’s employees, officers, directors, agents, insurers, partners, and consultants any and all claims for or entitlement to special, incidental, indirect, or consequential damages arising out of, resulting from, or in any way related to the Project and agree that DOWL HKM’s total liability to Client under this Agreement shall be limited to *10 $50,000.

This sub-section was set forth in the initial Agreement and no subsequent addenda altered this provision.

¶6 Initially, Zirkelbach filed suit on July 30, 2014, against Knife River, a subcontractor employed by Zirkelbach, over construction liens relating to the Facility. Nearly six months after filing suit, Zirkelbach filed a third-party complaint 2 against DOWL alleging claims of negligence and breach of contract. Zirkelbach claims that due to DOWL’s negligence and breach of contract, Zirkelbach incurred $1,218,197.93 resolving problems caused directly by DOWL’s design plans.

¶7 On August 22, 2016, DOWL filed a motion for partial summary judgment arguing, pursuant to the Agreement’s § 5(D) provision, that DOWL cannot be liable to Zirkelbach under the contract for any amount exceeding $50,000. Zirkelbach countered that the contractual limitation of liability found within § 5(D) violates § 28-2-702, MCA, and therefore is unenforceable. On November 16, 2016, the District Court granted DOWL’s motion for partial summary judgment. Zirkelbach filed a timely appeal.

STANDARD OF REVIEW

¶8 We review a district court’s grant of summary judgment de novo, applying the same criteria of M. R. Civ. P. 56 as the district court. Pilgeram v. GreenPoint Mortg. Funding, Inc., 2013 MT 354, ¶ 9, 373 Mont. 1, 313 P.3d 839. We review a district court’s conclusions of law to determine whether they are correct and its findings of fact to determine whether they are clearly erroneous. Pilgeram, ¶ 9. Under Rule 56(c), summary judgment will be granted if the moving party can show there is no genuine issue as to any material fact and the moving party is entitled to a judgment as a matter of law. Roe v. City of Missoula, 2009 MT 417, ¶ 14, 354 Mont. 1, 221 P.3d 1200.

DISCUSSION

¶9 Did the District Court err in granting DOWL’s motion for partial summary judgment ?

¶10 Zirkelbach argues on appeal that the District Court erred in granting partial summary judgment in favor of DOWL. Specifically, *11 Zirkelbach contends that Montana law clearly disfavors the limitation of liability clause found within the Agreement because it is against public policy. Zirkelbach further maintains that the contract is ambiguous because the limitation of liability clause reflects a lack of meeting of the minds as to who shall bear the burden of liability.

¶11 DOWL counters that the District Court correctly granted partial summary judgment concluding that the limitation of liability clause within the Agreement did not violate public policy. Further, DOWL argues Zirkelbach should be estopped from asserting the argument that the contract is ambiguous because Zirkelbach failed to present the same argument to the District Court. Moreover, DOWL asserts that § 5(D) is clear and unambiguous.

¶12 As a threshold matter, it is well-established we will not address an issue raised for the first time on appeal, nor will we address a party’s change in legal theory. Becker v. Rosebud Operating Servs., 2008 MT 285, ¶ 17, 345 Mont. 368, 191 P.3d 435. We will not address Zirkelbach’s arguments that were not raised to the District Court. However, we agree with the District Court that the limitation of liability clause is subject to only one interpretation and therefore the clause is clear and unambiguous. Section 28-3-401, MCA; Mary J. Baker Revocable Trust v. Cenex Harvest States, Coops., Inc., 2007 MT 159, ¶ 19, 338 Mont. 41, 164 P.3d 851.

¶13 “The fundamental tenet of modern contract law is freedom of contract; parties are free to mutually agree to terms governing their private conduct as long as those terms do not conflict with public laws.” Winter v. State Farm Mut. Auto. Ins. Co., 2014 MT 168, ¶ 26, 375 Mont. 351, 328 P.3d 665 (internal citations omitted). “This tenet presumes that parties are in the best position to make decisions in their own interest.” Arrowhead Sch. Dist. No. 75 v. Klyap, 2003 MT 294, ¶ 20, 318 Mont. 103, 79 P.3d 250. “A contract must be so interpreted as to give effect to the mutual intention of the parties as it existed at the time of contract, so far as the same is ascertainable and lawful.” Section 28-3-301, MCA; Mary J. Baker Revocable Trust, ¶ 21. “To permit the avoidance of a written contract because the terms of the contract now appear burdensome or unreasonable would defeat the very purpose of placing a contract into writing.” Marco & Co., LLC v. Deaconess/Billings Clinic Health Sys., 1998 MT 26, ¶ 16, 287 Mont. 293, 954 P.2d 1116.

¶14 Contract terms that violate § 28-2-702, MCA, are unenforceable. Miller v. Fallon Cnty., 222 Mont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Victory Ins. v. State
2025 MT 180 (Montana Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2017 MT 238, 402 P.3d 1244, 389 Mont. 8, 2017 WL 4274179, 2017 Mont. LEXIS 591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zirkelbach-construction-inc-v-dowl-llc-mont-2017.