Habets v. Swanson

2000 MT 367, 16 P.3d 1035, 303 Mont. 410, 57 State Rptr. 1567, 2000 Mont. LEXIS 370
CourtMontana Supreme Court
DecidedDecember 28, 2000
Docket99-269
StatusPublished
Cited by11 cases

This text of 2000 MT 367 (Habets v. Swanson) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Habets v. Swanson, 2000 MT 367, 16 P.3d 1035, 303 Mont. 410, 57 State Rptr. 1567, 2000 Mont. LEXIS 370 (Mo. 2000).

Opinions

JUSTICE REGNIER

delivered the opinion of the Court.

¶1 John K. and Jeanne T. Swanson (hereinafter “Swansons”) appeal from the Order Determining Pre-Trial Questions of Law issued by the Ninth Judicial District, Toole County. Swansons contend that the District Court erred when it excluded extrinsic evidence of their 1984 contract with Farmers Union Central Exchange, Inc. (hereinafter “Cenex”). We affirm.

BACKGROUND

¶2 On February 1, 1990, Cenex sold Glen Habets approximately seven miles of subsurface 6-inch diameter pipeline, stretching from Kevin to Sunburst, Montana, that was no longer in use by Cenex. The contract provided that Cenex grants all “right, title and interest in [412]*412and to seven (7) miles of 6 inch diameter inactive pipeline running from Sunburst, Montana to Kevin, Montana in Toole County, as shown in red on the map which is attached... together with all leases, rights-of-way, easements, and permits or grants for the pipeline which may be owned by Cenex, if any.” In August 1996, Habets began to excavate and remove the subsurface pipeline that he had purchased from Cenex.

¶3 In October 1996, during his removal operations, Habets reached the boundary of real property owned by the Swansons. The Swansons refused to allow Habets to enter the land and remove any section of pipeline. Habets attempted to enter the Swansons’ property on an additional occasion but was denied access. It is undisputed that the sale documents covering the transfer of the seven-mile section of 6-inch pipeline from Cenex to Habets included the necessary easements, leases, right-of-ways, grants, or permits for salvage of the pipeline.

¶4 On June 30,1997, Habets filed an application for preliminary injunction, naming John K. and Jeanne T. Swanson as Defendants, seeking to enjoin the Swansons from refusing to permit him access so that he could excavate and remove the pipe. On October 3, 1997, Habets filed an amended application and complaint, naming Joette L. Swanson as an additional Defendant as owner of a section of the land containing the pipeline, seeking damages for wrongful conversion, and raising other claims.

¶5 On January 21, 1998, the Swansons served their Answer and Counterclaim, alleging that they had purchased the same pipeline, as well as a section of real property on which part of the pipeline was buried, from Cenex on July 1, 1984. The counterclaim sought dismissal of Habets’ lawsuit, recovery of the reasonable value of the pipe already removed and sold by Habets, trespass damages, and other claims. The Swansons’ counterclaim is based on the following facts. On July 1,1984, the Swansons entered into a contract with Cenex to purchase approximately 35 miles of various diameter inactive pipelines situated in Toole County. The 1984 contract provides that the Swansons/Cenex “[ajgreement embodies the entire agreement and understanding between the parties hereto and supersedes all prior agreements and understandings relating to the subject matter hereof.” The pipelines to be conveyed were identified in the contract by attaching and specifically referencing maps that marked in red the pipeline that was included in the transfer. Although the 6-inch pipeline in question running from Sunburst to Kevin, Montana, is not [413]*413marked in red on the maps referenced in the contract, the Swansons contend that parol evidence will establish that the parties intended that the pipeline in question was to be included in the sale and that, therefore, they are the legal owners of the pipeline.

¶6 On February 4,1998, the Swansons filed a third-party complaint against Cenex, alleging breach of the contract for selling Habets the same line of pipe that Swansons claim they purchased on July 1,1984. On March 26,1999, the District Court entered an Order Determining Pretrial Questions of Law, holding that the Swansons’ third-party complaint against Cenex was barred pursuant to the applicable statute of limitations, § 27-2-202(1), MCA, because the complaint was filed more than eight years after the parties had entered into the written contract for the sale of the pipeline. The District Court also ruled that the July 1, 1984 contract between the Swansons and Cenex, is clear and unambiguous, and thus parol evidence was not admissible to prove that the Swansons had purchased the pipeline between Kevin and Sunburst from Cenex prior to Cenex selling the same section of pipeline to Habets.

¶7 On April 5,1999, the District Court entered a final judgment, dismissing with prejudice the Swansons’ third-party claim against Cenex. The District Court also held that the contract between the Swansons and Cenex did not convey the disputed seven-mile segment of 6-inch pipeline to the Swansons. From this order the Swansons appeal.

STANDARD OF REVIEW

¶8 Whether extrinsic evidence is admissible is a question of law. See Carelli v. Hall (1996), 279 Mont. 202, 209, 926 P.2d 756, 761. We review a district court’s conclusion of law as to whether the court’s interpretation of the law is correct. Carbon County v. Union Reserve Coal Co. (1995), 271 Mont. 459, 469, 898 P.2d 680, 686.

DISCUSSION

¶9 Whether the District Court erred when it barred the Swansons from relying on parol evidence to contest the terms of their 1984 written contract with Cenex?

¶10 The Swansons do not contest that the District Court properly dismissed Cenex by virtue of the applicable statute of limitations, nor do they challenge the District Court’s ruling that the parol evidence rule precludes extrinsic evidence concerning the pipeline sale as between Cenex and the Swansons. However, the Swansons claim that [414]*414extrinsic evidence as to the pipeline sale should be admitted in the pending litigation between Habets and the Swansons because Habets is a “stranger” to the 1984 contract between Cenex and the Swansons.

¶ 11 Asa preliminary matter we note that all parties to this appeal question the status and propriety of their opponents’ arguments from a procedural perspective. Cenex claims there is no final appealable order between Habets and the Swansons and, therefore, this appeal should be dismissed as premature. Habets argues that the Swansons never raised their “stranger to the contract” argument in the District Court and should be barred from raising it here. The Swansons contend that Habets should be barred from raising a “successor in interest” claim because it was not raised below. We find none of these arguments persuasive. The District Court ruled as a matter of law in its order entering final judgment that “the contract entered into between the Swansons and Cenex on July 1, 1984, did not convey the disputed seven mile segment of six-inch pipeline to the Swansons. There remains for trial the claim of Glen Habets against the Swansons ....’’By concluding that the 1984 contract did notconveythe disputed pipeline to the Swansons and that only Habets’ claims remained for trial, the court’s final order essentially dismissed Swansons’ counterclaims for trespass and conversion. We will review these legal conclusions to determine whether they are correct.

¶12 The District Court concluded that the 1984 contract between the Swansons and Cenex did not include the sale of the disputed section of 6-inch pipeline.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Towe Farms v. Corbett
2017 MT 131N (Montana Supreme Court, 2017)
Underhill Holdings, LLC v. Travelsuite, Inc.
137 A.D.3d 533 (Appellate Division of the Supreme Court of New York, 2016)
State v. Martinez
New Mexico Court of Appeals, 2012
Kruer v. Three Creeks Ranch of Wyoming, L.L.C.
2008 MT 315 (Montana Supreme Court, 2008)
K & R Partnership v. City of Whitefish
2008 MT 228 (Montana Supreme Court, 2008)
In Re the Marriage of Olson
2005 MT 57 (Montana Supreme Court, 2005)
Tvedt v. Farmers Insurance Group of Companies
2004 MT 125 (Montana Supreme Court, 2004)
Keeney Construction v. James Talcott Construction Co.
2002 MT 69 (Montana Supreme Court, 2002)
Habets v. Swanson
2000 MT 367 (Montana Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2000 MT 367, 16 P.3d 1035, 303 Mont. 410, 57 State Rptr. 1567, 2000 Mont. LEXIS 370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/habets-v-swanson-mont-2000.