Westfork Construction Co. v. Nelcon, Inc.

877 P.2d 481, 265 Mont. 398, 51 State Rptr. 553
CourtMontana Supreme Court
DecidedJune 20, 1994
Docket93-489
StatusPublished
Cited by10 cases

This text of 877 P.2d 481 (Westfork Construction Co. v. Nelcon, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westfork Construction Co. v. Nelcon, Inc., 877 P.2d 481, 265 Mont. 398, 51 State Rptr. 553 (Mo. 1994).

Opinion

JUSTICE HUNT

delivered the Opinion of the Court.

Subcontractor Westfork Construction Company filed an action in the Fourth Judicial District, Missoula County, for contract damages *400 against contractor Nelcon, Inc., and its bonding company, United States Fidelity and Guaranty (Fidelity). Westfork alleged that it was entitled to damages arising out of its subcontract agreement with Nelcon for Westfork to clear acreage and retain the timber on the acreage, and the subsequent discovery that timber had been removed. Westfork appeals the directed verdict and judgment and attorney fee award entered for Nelcon and Fidelity.

We affirm.

The sole issue on appeal is whether the District Court erred when it granted respondents’ motion for a directed verdict on the basis that the evidence established that appellant received all the payment it was entitled to under the written agreement.

On October 5, 1987, Nelcon entered an agreement with the State of Montana to complete a highway construction project known as Elk Hills-Lyon Springs in Lincoln County, and granting Nelcon the standing timber within the right-of-way. The project required the highway to be straightened and widened. Prior to this agreement, in mid-September 1987, Nelcon inspected the project and found timber to be standing on the site.

Westfork placed a bid for a subcontract with Nelcon to clear and grub the project grounds in preparation for excavation. Westfork’s written bid dated October 2, 1987, offered a price of $1200 per acre on the approximately 70 acre project area, plus the right-of-way timber.

As a result of the bid, Nelcon and Westfork entered into a subcontract dated October 5, 1987, providing for payment of $84,000 for clearing and grubbing the approximately 70 acre area at $1200 per acre. The subcontract did not refer to the timber. However, Nelcon concedes that its representatives agreed that Westfork “could do with the timber” as it “pleased.”

In mid-October 1987, it became known to the State, Nelcon, and Westfork that the timber was owned by Champion International and had been removed from the area. In response to this information, Westfork sent a letter to Nelcon stating that it would complete the job for $1700 per acre due to the absence of timber. Although the letter was received by Nelcon, no response was ever given. Westfork commenced the job and completed the clearing and grubbing.

At about the same time that Westfork sent the letter to Nelcon, Nelcon filed a claim with the State concerning the missing timber. After negotiations, the State offered to settle the issue with Nelcon by paying them $22,359.63 for the missing timber, which included the *401 value of the timber, plus Nelcon’s costs in determining the amount of missing timber in the area. Of the $22,359.63 timber settlement, Nelcon paid Westfork $19,859.63 after retaining $2500 as markup costs.

Westfork filed an action against Nelcon and Fidelity alleging damages due to the modified contract terms wherein Nelcon agreed to pay at the rate of $1700 per acre due to the absence of timber, thus owing Westfork $15,277.47, plus interest. In the alternative, if the contract was found to have not been modified, then Westfork alleged it was entitled to receive damages for the missing right-of-way timber under the subcontract agreement with Nelcon.

A jury trial began February 10, 1993. At the close of Westfork’s case-in-chief, the District Court granted Nelcon’s and Fidelity’s motion for a directed verdict. In granting the directed verdict, the court noted that Westfork did not argue that the agreement should not be enforced because it was unconscionable or fraudulent, and found that the subcontract between Nelcon and Westfork constituted the entire agreement. The court found that Sections 7 and 8 of the subcontract between Nelcon and Westfork specifically provided for the resolution of any changed circumstances or construction claims, and Section 8 specifically provided that Westfork was bound to Nelcon to the same extent that Nelcon was bound to the State whenever any claims or disputes arise out of the performance of the contract. The court also found that the subcontract provided that Nelcon could not be liable to Westfork for its work on the project for any amount greater than the amount recovered from the State by Nelcon, less markup, and that Westfork received all the payments it was entitled to under the subcontract. Judgment was entered on March 22, 1993.

Did the District Court err when it granted respondent’s motion for a directed verdict on the basis that the evidence established that appellant received all the payment entitled to under the written agreement?

When this Court reviews a directed verdict granted pursuant to Rule 50(a), M.R.Civ.R, it looks to see if the evidence leads to only one conclusion. “If only one conclusion is reasonably proper, then the directed verdict is proper.” Semenza v. Leitzke (1988), 232 Mont. 15, 18, 754 P.2d 509, 511 (quoting Cremer v. Cremer Rodeo Land & Livestock Co. (1979), 181 Mont. 87, 92, 592 P.2d 485, 488). A directed verdict is properly granted when the “evidence is so insufficient in fact to be insufficient in law.” Semenza, 754 P.2d at 511 (quoting Parini v. Lanch (1966), 148 Mont. 188, 191, 418 P.2d 861, 863). In our *402 review of a directed verdict for a defendant, we will view the evidence in the light most favorable to the plaintiff, and if the evidence tends to establish the case according to the plaintiff’s pleading, this Court will reverse the district court’s order. Cremer, 592 P.2d at 488.

Both Westfork and Nelcon agree that although there is no written agreement concerning the grant of timber to Westfork, both parties understood that the main contract between Nelcon and the State provided that Nelcon could retain any merchantable timber on the right-of-way, and Nelcon conceded that Westfork “could do with the timber” as it “pleased.” Westfork argues that the parties resolved their dispute concerning the missing timber by modifying the subcontract price from $1200 per acre to $1700 per acre, as evidenced by the letter Westfork sent to Nelcon on October 28, 1987. Westfork also contends that Nelcon representatives were aware that Westfork was performing the job, and therefore, Nelcon impliedly accepted the $1700 modification by its failure to respond. Therefore, Westfork asserts that there was sufficient evidence for the jury to conclude that the parties resolved their dispute concerning the absent timber and agreed that the job would be completed for $1700 per acre.

Nelcon, on the other hand, argues that the written contract was clear and unambiguous and provided all the terms of the agreement between the parties, and that both Westfork and Nelcon are experienced in the area of bidding and contracting construction jobs. Nelcon also argues that there is no evidence in the record that Nelcon executed any acceptance of Westfork’s letter to modify the subcontract price terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewistown Miller Construction Co. v. Martin
2011 MT 325 (Montana Supreme Court, 2011)
MOUNTAIN SUPPLY COMPANY v. Forbes
222 P.3d 647 (Montana Supreme Court, 2009)
Richards v. JTL Group, Inc.
2009 MT 173 (Montana Supreme Court, 2009)
Keeney Construction v. James Talcott Construction Co.
2002 MT 69 (Montana Supreme Court, 2002)
Dvorak v. First Interstate Bank
1999 MT 236N (Montana Supreme Court, 1999)
Doble v. Bernhard
1998 MT 124 (Montana Supreme Court, 1998)
Topco, Inc. v. State, Dept. of Highways
912 P.2d 805 (Montana Supreme Court, 1996)
Tyner v. Park County
897 P.2d 202 (Montana Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
877 P.2d 481, 265 Mont. 398, 51 State Rptr. 553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westfork-construction-co-v-nelcon-inc-mont-1994.