Topco, Inc. v. State, Dept. of Highways

912 P.2d 805, 275 Mont. 352, 53 State Rptr. 175, 1996 Mont. LEXIS 35
CourtMontana Supreme Court
DecidedMarch 11, 1996
Docket94-301
StatusPublished
Cited by20 cases

This text of 912 P.2d 805 (Topco, Inc. v. State, Dept. of Highways) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Topco, Inc. v. State, Dept. of Highways, 912 P.2d 805, 275 Mont. 352, 53 State Rptr. 175, 1996 Mont. LEXIS 35 (Mo. 1996).

Opinion

*355 JUSTICE NELSON

delivered the Opinion of the Court.

Topeo, Inc. (Topeo) appeals from the Findings of Fact, Conclusions of Law and Order of the First Judicial District Court, Lewis and Clark County, awarding certain damages to Topeo under a clearing and grubbing contract with the State of Montana, Department of Highways (State). The State cross-appeals on the assignment of the contract to Topeo. We affirm in part, reverse in part and remand.

We address the following issues on appeal:

1. Whether the District Court erred in failing to find that the assignment to Topeo from Washington Construction violated the terms of the contract.

2. Whether the District Court erred in awarding damages to Topeo at the subcontract price rather than at the contract price.

3. Whether the District Court erred in determining that acreage measurement should use horizontal rather than slope distances.

4. Whether the District Court erred in failing to award Topeo consequential damages as a result of the State’s breach of contract.

5. Whether the District Court erred in failing to award Topeo payment for acres cleared but not paid for by the State.

6. Whether the District Court erred in changing venue from Missoula County to Lewis and Clark County.

Background Facts

On October 7, 1988, the State awarded a highway construction contract to Washington Construction Co. (Washington) for reconstruction of 16 miles of highway between Libby and Troy, Montana. The project involved realignment of the existing roadway through a canyon and bordering a river. The State prepared plans and cross-section drawings that showed the actual profile of the construction site.

Under the contract, clearing and grubbing, the process of clearing trees, tree stumps and brush from the construction site, was to extend 10 feet beyond the construction limits. The plans and specifications prepared by the State did not indicate any exclusion for the 50 acres of old highway or paved travel way (PTW) from the clearing and grubbing area.

John Richards (Richards), the sole shareholder of Topeo, inspected the construction site prior to submitting a bid to Washington for the clearing and grubbing. Only a few of the stakes showing the clearing limits were in place at the time Richards inspected the site. Richards submitted Topco’s bid to Washington taking into account that some *356 areas of the construction site would require little or no clearing and grubbing and other areas would require substantial clearing and grubbing.

On November 1, 1988, Topeo entered into a subcontract with Washington for clearing and grubbing of 183.7 acres at $1725 per acre. Washington had been awarded the prime contract with a clearing and grubbing price of $3600 per acre. The 1987 edition of the Standard Specifications for Road and Bridge Construction (Standard Specifications) was made a part of Washington’s contract with the State.

Topeo commenced clearing and grubbing in November 1988. A short time later, a dispute arose between Topeo and the State with respect to the measurements for payment of the clearing and grubbing. The contract between Washington and the State required that all claims of subcontractors be made through Washington as the general contractor. On June 27, 1989, Topeo, through Washington, asserted a claim against the State regarding inclusion of the PTW and the method of measurement of the acreage cleared and grubbed. The State denied Topco’s claim.

On February 6, 1990, Topeo made a formal claim for payment of additional acreage, including the PTW. This claim was denied by the District Engineer in March 1990. Topeo then appealed to the Board of Contract Appeals. On July 23,1990, the Board affirmed the District Engineer’s decision without comment. On August 1, 1990, the State affirmed that all administrative remedies had been exhausted by Washington and Topeo.

Washington assigned all right, title and interest in and to the clearing and grubbing portion of the contract to Topeo on October 24, 1990, so that Topeo could pursue the contract claims directly. On November 14, 1990, Topeo filed a complaint against the State in Missoula County. On the State’s motion, venue was changed to Lewis and Clark County in October 1991.

Abench trial was held in November 1993. The District Court issued its Findings of Fact, Conclusions of Law and Order on March 17,1994, wherein the court ordered the State to pay Topeo for the 50 acres of PTW at $1750 per acre (even though the subcontract specified $1725 per acre). Topeo appeals the District Court’s decision in several respects and the State cross-appeals on the assignment of the contract to Topeo.

*357 Standard of Review

We review a district court’s findings of fact to determine whether they are clearly erroneous. Daines v. Knight (1995), 269 Mont. 320, 324, 888 P.2d 904, 906 (citing Columbia Grain International v. Cereck (1993), 258 Mont. 414, 417, 852 P.2d 676, 678). A finding is clearly erroneous if it is not supported by substantial evidence, if the district court misapprehended the effect of the evidence, or if, after reviewing the record, this Court is left with a firm conviction that a mistake has been made. Interstate Production Credit v. DeSaye (1991), 250 Mont. 320, 323, 820 P.2d 1285, 1287. 1

We review a district court’s conclusions of law to determine whether the court’s interpretation of the law is correct. Carbon County v. Union Reserve Coal Co., Inc. (1995), 271 Mont. 459, 469, 898 P.2d 680, 686 (citing Steer, Inc. v. Department of Revenue (1990), 245 Mont. 470, 474-75, 803 P.2d 601, 603-4).

Issue 1.

Whether the District Court erred in failing to find that the assignment to Topeo from Washington Construction violated the terms of the contract.

In its March 17,1994, Findings of Fact, Conclusions of Law and Order, the District Court concluded that there was an assignment of Washington’s contract to Topeo. The State, in its cross-appeal, argues that this assignment is invalid because it violates the terms of the contract and the Standard Specifications which had been made a part of the contract. Contrary to the State’s argument that any assignment of the contract required the written consent of the State, Topeo argues that the Standard Specifications only require written consent if the portion of the contract transferred is more than 50 percent of the potential earnings under the contract.

Standard Specification § 108.01(A) states:

The Contractor shall assign not more than 50 percent of the potential earnings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brauweiler v. National Jewish
Colorado Court of Appeals, 2025
Marriage of Macaluso
Colorado Court of Appeals, 2025
Coronado-Arrascue v. Golka
Colorado Court of Appeals, 2025
In re Donald C. Taylor and Margaret Ann Taylor Trust
2016 COA 100 (Colorado Court of Appeals, 2016)
Riverview Homes, II, Ltd. v. Canton
2001 MT 309 (Montana Supreme Court, 2001)
Eschenbacher v. Anderson
2001 MT 206 (Montana Supreme Court, 2001)
Maloney v. Home and Investment Center, Inc.
2000 MT 34 (Montana Supreme Court, 2000)
Delaware v. K-Decorators, Inc.
1999 MT 13 (Montana Supreme Court, 1999)
State v. Wayne Spotted Blanket
1998 MT 59 (Montana Supreme Court, 1998)
Hove v. Mullin
Montana Supreme Court, 1997
Basta v. Crago, Inc.
930 P.2d 78 (Montana Supreme Court, 1996)
Travelers Insurance v. Holiday Village Shopping Center Ltd.
931 P.2d 1292 (Montana Supreme Court, 1996)
Matter of Estate of Brooks
927 P.2d 1024 (Montana Supreme Court, 1996)
State Ex Rel. State Compensation Mutual Insurance Fund v. Berg
927 P.2d 975 (Montana Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
912 P.2d 805, 275 Mont. 352, 53 State Rptr. 175, 1996 Mont. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/topco-inc-v-state-dept-of-highways-mont-1996.