Lewistown Miller Construction Co. v. Martin

2011 MT 325, 271 P.3d 48, 363 Mont. 208, 2011 Mont. LEXIS 439
CourtMontana Supreme Court
DecidedDecember 30, 2011
DocketDA 11-0151
StatusPublished
Cited by9 cases

This text of 2011 MT 325 (Lewistown Miller Construction Co. v. Martin) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lewistown Miller Construction Co. v. Martin, 2011 MT 325, 271 P.3d 48, 363 Mont. 208, 2011 Mont. LEXIS 439 (Mo. 2011).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 Gary Martin (Martin) appeals from the judgment entered by the Tenth Judicial District, Fergus County, in an action by Lewistown Miller Construction Co., Inc., (LMCC) to foreclose a construction lien. LMCC cross-appeals from the denial of statutory attorney fees. We affirm in part, reverse in part, and remand. We address the following issues:

¶2 1. Did the District Court err in ordering foreclosure of the construction lien?

¶3 2. Did the District Court err in denying attorney fees to the parties?

FACTUAL AND PROCEDURAL BACKGROUND

¶4 Martin owns land near Roy, Montana. Martin hired Baywood Homes (Baywood), a professional design and building company, to create a design concept for a dwelling to be constructed on his property. This dwelling was designed with a three-car garage on the lower level and upper living quarters. Custom dog kennels, similar to those Martin had constructed on three of his other properties, were also designed. Martin described the dwelling as a ‘hunting cabin.” Baywood helped Martin solicit bids from contractors for construction *210 of the dwelling, and LMCC was one of three contractors that submitted a bid. The bid request required an immediate start. Richard Miller, sole shareholder of LMCC, testified that he felt rushed when he calculated the bid but acknowledged that he could have declined to submit a bid. LMCC’s bid was for $338,400.00, and Martin accepted the bid. LMCC and Martin then entered into a written contract that incorporated by reference the ‘Bid and Specifications” provided by LMCC.

¶5 The exact costs of labor and materials on some components of the building were undetermined at the time the parties entered into the contract. Rather, LMCC included estimates of product and installation costs of these components. The estimates are called “allowances.” Included in the contract price were the following allowances:

(a) Plumbing: $4,000.00
(b) Cabinets, counter tops, and vanities: $7,000.00
(c) Walk doors, handles, and locks: $500.00
(d) Wood stove: $3,000.00
(e) Lighting fixtures: $5,000.00

If actual costs exceeded these allowances during construction, such overruns were considered to be in excess of the agreed contract price of $338,400.00.

¶6 The contract required that changes must be in writing (referred to herein as “the change order process”). The contract included the following provisions:

(5) In the event Owner desires materials which exceed the specifications and drawings attached thereto, such materials shall be the subject of a separate written agreement in the form of a Change Order between the parties with respect to additional compensation due Contractor for the purpose and installation of such items.
(6) It is expressly understood that any changes, additions and deductions from the drawings and specifications herein must be agreed upon in writing by both parties hereto before the same can be effected.
(7) Attached hereto and by this reference fully incorporated herein, is the Bid and Specifications which, unless specifically altered in writing between the parties hereto and unless contrary to the express provisions of this agreement, are binding and controlling upon the parties with respect to design and materials to be used. [Emphasis in original.]

*211 As the project progressed, many changes were made. According to the parties, the written change order process was used only once, adding the installation of cultured stone on the walls behind the stove, a 30-inch raised hearth, a one-ton capacity electric hoist and railing, and application of epoxy on the new concrete garage floor. These changes increased the bid price by $5,145.00. However, this “change order” was attached to and signed at the same time as the construction contract. The contract price for the cabin was $343,545.00, which is the sum of the bid price ($338,400.00) plus the cost of the additions specified in the change order ($5,145.00). Thus, the “change order” was in name only, and in reality constituted additional negotiation of the terms of the original contract, not a modification of it. Because the original contract incorporated these requests and increased the price accordingly, the actual change order process was never used.

¶7 Martin requested many changes, which LMCC implemented during construction. Although not in the Bid and Specifications, Martin requested that the handles on the cabinets and doors be changed to special deer antler handles, made by hand. Martin testified, ‘I saw some of the antler work ... and I got the idea for antler pulls on the cabinets and doors. I asked [Miller] if he could have those made....” Martin requested that LMCC install a water filtration system. He testified, "... I wanted a five micron filter and a UV and ultraviolet light to make sure the water was pure that I would be consuming in the house.” Martin requested that LMCC line the closets with cedar, install Plexiglas on the railings on the deck to reduce the wind, install log handrails on the stairs, and install a painted air conditioning unit because "... the air conditioning unit, as purchased, was white and I wanted it to match the décor in the room ....” Martin requested installation of a “buck pole” for hoisting game, which required a pulley system, the pouring of a concrete base, and finishing to match the pole to the other wood used in the construction. Martin requested additional tile work that was not included in the allowances. Martin testified that he selected lights and heaters that exceeded the allowances. Other changes or additions that LMCC implemented included the use of hand-pounded, blacksmithed bolts on the decorative trusses along the cathedral ceiling, additional materials for the dog kennels, a firewood pulley system that was changed from bid *212 to antique, 1 revising the wiring for the lighting, decorative outlets and light switches, a different wood stove, and the addition of ghost wood wainscoting on the bedroom walls, among other items. Martin testified that he made payments above the contract price for some of these changes, but LMCC disputed the sufficiency of the payments. The change order process was never used.

¶8 In addition to the changes Martin acknowledges, LMCC claimed that Martin requested further changes, which Martin disputed. One item was a custom cupola for the top of the cabin. LMCC claimed the original cupola was to be a standard structure but that Martin required LMCC to custom-build the cupola, which was installed. LMCC claims it had to custom-build wooden vents for placement on the dormers to match the wood used for the siding. LMCC argued that the contract called for wooden garage doors but that Martin requested the doors be the same as those installed at his Canadian home, which were steel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Montana, 2026
Cline v. Kralich
2017 MT 187N (Montana Supreme Court, 2017)
Vintage Construction, Inc. v. Feighner
2017 MT 109 (Montana Supreme Court, 2017)
S & P Brake Supply, Inc. v. STEMCO LP
2016 MT 324 (Montana Supreme Court, 2016)
Masters Group International, Inc. v. Comerica Bank
2015 MT 192 (Montana Supreme Court, 2015)
Minks v. Gerttula
2013 MT 151N (Montana Supreme Court, 2013)
Mountain West Bank, N.A. v. Cherrad, LLC
2013 MT 99 (Montana Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2011 MT 325, 271 P.3d 48, 363 Mont. 208, 2011 Mont. LEXIS 439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lewistown-miller-construction-co-v-martin-mont-2011.