Dalakow v. Geery

318 P.2d 253, 132 Mont. 457, 1957 Mont. LEXIS 58
CourtMontana Supreme Court
DecidedNovember 18, 1957
Docket9613
StatusPublished
Cited by14 cases

This text of 318 P.2d 253 (Dalakow v. Geery) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dalakow v. Geery, 318 P.2d 253, 132 Mont. 457, 1957 Mont. LEXIS 58 (Mo. 1957).

Opinion

MR. CHIEF JUSTICE HARRISON:

This is an appeal from a money judgment of the District Court of Lewis and Clark County, Montana, in favor of the plaintiff, E. A. Dalakow, and against the defendant, Glenn Geery.

The present controversy arose out of the following set of facts. In August 1950, the defendant, a road construction contractor, was the successful bidder on a United States road construction project near Troy, Montana. The contract, which we will hereafter refer to as the “prime contract,” awarded to him was in the sum of $267,903.65. Prior to making the bid defendant had consulted the plaintiff, a specialist in bridge construction, for the purpose of estimating certain bridge, head-wall, and guardrail items on the project with the ultimate purpose in mind of subcontracting those items to plaintiff for construction if defendant was the successful bidder.

Pursuant to the above arrangement the defendant and plaintiff on August 24, 1950, entered into a written subcontract, by the terms of which plaintiff agreed to construct the headwalls, bridges and guardrail items under the-prime contract. The prime contract called for the construction' of some thirty-one items of work. The first eighteen were agreed to be constructed *459 by defendant and the remaining thirteen plaintiff, under the subcontract, agreed to construct according to the terms and specifications of the prime contract.

The prime coiitract called for the completion of certain items by January 1, 1951, among these, by the testimony of the plaintiff, was the construction of 7,875 linear feet of guardrail; other items were to be completed by April 1. It was admitted on trial that the erection of plaintiff’s bridges fell within this time limitation, and finally that the whole construction project was to be completed by July 1, 1951.

Plaintiff and defendant commenced work on their respective portions of the contract in the latter part of August 1950. Plaintiff testified that late in August defendant approached him on the streets of Troy, Montana, and stated that the United States wanted the work completed by December 31, 1950. He inquired of plaintiff how much he, plaintiff, thought they should charge for the accelerated completion date. Plaintiff replied no less than 20 percent of the contract price. Defendant then stated he would take the matter up with the United States and subsequently he sent his office manager, Peter Wanderer, to Seattle to negotiate the matter. These negotiations resulted in a modification of the prime contract in two respects: (1) The contract price was changed from $267,903.65 to $341,-347.65 to reflect the addition of Item 32 in the prime contract, described as “Accelerated program to complete entire project by 31 December, 1950,” at a price of $73,444; and (2) Completion of the work was changed to read that all work would be completed by December 31, 1950.

The court found that shortly after the acceleration agreement was entered into the defendant met plaintiff and plaintiff’s foreman, Mike Cinker, at the construction site and told plaintiff that he would get his share of the bonus if the job was finished by January 1, 1951. Plaintiff went to defendant’s office in Troy, where Wanderer was in charge and asked him about the bonus (acceleration payment). Wanderer told *460 plaintiff it was over 21.5 percent of the over-all figure in the prime contract.

Dalakow then proceeded to accelerate the progress of his thirteen items of work by bringing in more men, working his crews overtime, and providing special accommodations for the men. All the plaintiff’s items were completed before December 31; the last item, the guardrail installation, having been completed on December 23.

Plaintiff then went to see defendant on several occasions, asking that he be paid his proportionate share of the “bonus,” plus other compensation allegedly due under the subcontract. Defendant put him off until finally plaintiff initiated this suit.

The complaint states four causes of action, but since proof at trial was confined to proving only one of these, the other three are unimportant for purposes of this opinion. In the third cause of action plaintiff pleads that he entered into the afore-mentioned subcontract; that subsequently plaintiff and defendant entered into an oral modification thereof by the terms of which plaintiff obligated himself to accelerate certain items of work in consideration for which he was to be paid a proportionate share of the afore-mentioned bonus; that in furtherance of the oral modification he incurred additional expense in accelerating his performance; and that he completed all of the work he contracted to do by December 31, 1950, in pursuance to the oral modification. The complaint then alleges that contrary to the oral modification defendant has not paid him any part of the bonus by reason of which there is now due and owing to plaintiff the sum of $19,279.78 with interest.

Defendant in his answer denied the oral modification, and denied that there was any sum due and owing the plaintiff.

The ease was tried to the court; counsel expressly waiving a jury trial. At the conclusion of the trial the court made findings of fact and conclusions of law in accordance with plaintiff’s complaint, in effect finding that there had been an oral modification of the subcontract and that such oral modifica *461 tion was fully executed pursuant to the terms of section 13-907, R.C.M. 1947.

Judgment was entered for plaintiff in the sum of $17,782.91, plus 6 percent interest thereon from March 1, 1951, and the defendant perfected this appeal.

The defendant sets out twenty-five specifications of error in his brief. However he elected to resolve them into two main issues. He expressly states that no argument will be made as to the existence of the oral agreement. These two issues are: (1) Was the written contract legally modified? (2) Was the oral contract performed?

Before examining the two issues set out above, several observations with regard to the evidence in this case should be made. First, all factual matters with regard to the alleged oral modification were disputed by the defendant and his witnesses. It should be observed that it is the trial court’s office to resolve these inconsistencies in the testimony, and where the evidence is fully considered and furnishes reasonable grounds for different conclusions the findings of the trial court will not be disturbed. Dalbey v. Equitable Life Assur. Soc. of U. S., 105 Mont. 587, 74 Pac. (2d) 432; Orton v. Bender, 43 Mont. 263, 115 Pac. 406. Second, in entering upon a review of the evidence on appeal this court indulges the presumption that the judgment is correct, and will draw every legitimate inference therefrom to support the presumption. Thomas v. Ball, 66 Mont. 161, 213 Pac. 597.

With these observations in mind we will now examine the two main issues in this case. As was noted before, the plaintiff under the subcontract was required to build 7,875 linear feet of guardrail. This amount was subsequently decreased to only 3,603 feet. The fact that the guardrail was completed within the time limitation is uncontested. However the defendant claims, and plaintiff admits, that this work was not completed by the plaintiff alone, but only with the help of defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewistown Miller Construction Co. v. Martin
2011 MT 325 (Montana Supreme Court, 2011)
Winkel v. Family Health Care, P.C.
668 P.2d 208 (Montana Supreme Court, 1983)
Mathis v. Daines
639 P.2d 503 (Montana Supreme Court, 1982)
Matzinger v. Remco, Inc.
558 P.2d 650 (Montana Supreme Court, 1976)
Murray v. Hicks
418 P.2d 12 (Hawaii Supreme Court, 1966)
Poepping v. Monson
354 P.2d 183 (Montana Supreme Court, 1960)
Schulz v. Fox
345 P.2d 1045 (Montana Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
318 P.2d 253, 132 Mont. 457, 1957 Mont. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dalakow-v-geery-mont-1957.