Matzinger v. Remco Inc.

CourtMontana Supreme Court
DecidedDecember 29, 1976
Docket13064
StatusPublished

This text of Matzinger v. Remco Inc. (Matzinger v. Remco Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matzinger v. Remco Inc., (Mo. 1976).

Opinion

No. 13064

I N T E SUPREME C U T O THE STATE O M N A A H OR F F OTN

R. P. MATZINGER, d /b /a MATZINGER ELECTRIC,

P l a i n t i f f and A p p e l l a n t ,

-vs - REMCO, I N C . , a Utah Corporation,

Defendant and Respondent.

Appeal from: D i s t r i c t Court of t h e Eighteenth J u d i c i a l D i s t r i c t , Honorable W. W. L e s s l e y , Judge p r e s i d i n g .

Counsel of Record:

For Appellant:

tandoe and Gary, Bozeman, Montana Joseph B. Gary argued, Bozeman, Montana

For Respondent :

Berg, Angel, Andriolo and Morgan, Bozeman, Montana Charles F. Angel argued, Bozeman, Montana C a r l T. Smith, Ogden, Utah

Submitted: March 1, 1976 -. . Decided :-J? -

Filed : M r . J u s t i c e Gene B . Daly delivered t h e Opinion of t h e Court.

This appeal i s from a judgment entered by t h e d i s t r i c t c o u r t ,

G a l l a t i n County, s i t t i n g without a j u r y .

Remco I n c . , and Matzinger E l e c t r i c entered i n t o a w r i t t e n

subcontract agreement providing Matzinger was t o f u r n i s h necessary

m a t e r i a l s and l a b o r f o r a sixty-one u n i t apartment complex and

laundry b u i l d i n g , known a s t h e "Village Apartments" being con-

s t r u c t e d by Remco i n Bozeman, Montana. The p r i c e f o r t h e work by

Matzinger pursuant t o t h i s subcontract was $46,000. F i n a l payment

was t o be made 30 days a f t e r completion of t h e p r o j e c t . This con-

t r a c t was signed by t h e p a r t i e s on January 15, 1973 and work

started shortly thereafter.

The p r o j e c t was completed f o r f i n a l i n s p e c t i o n by October 1,

1973. A s of January 1, 1974 Remco had paid Matzinger $41,440.

O January 3, 1974 Matzinger f i l e d a mechanic's l i e n on t h e a p a r t - n

ment complex f o r $23,538.27 claimed due f o r t h e balance owed under

t h e subcontract plus e x t r a s and modifications claimed t o have been

ordered by ~ e m c o ' spersonnel. This l i e n was r e l e a s e d i n May,

1974 a f t e r Remco paid Matzinger t h e sum of $4,560 t h e balance

owed under t h e subcontract and placed an a d d i t i o n a l $11,400 i n

escrow with a l o c a l t i t l e company pending t h e outcome of l i t i g a t i o n

of t h i s m a t t e r .

Matzinger claims he i s e n t i t l e d t o payment f o r e x t r a work

performed f o r Remco n o t contemplated by t h e p a r t i e s a t t h e time

t h e c o n t r a c t was signed. This claim includes work a l l e g e d l y author-

ized by Thomas Haggerty, Remco's job superintendent i n Bozeman, and

by Robert Richins, p r o j e c t superintendent, who commuted t o t h e

Bozeman s i t e from Remco's S a l t Lake C i t y headquarters one o r two days each week during construction.

Specifically Matzinger claimed extra compensation due for

these items:

1) Installation of weatherproof outlets on apartment

building ;

2) Air conditioner outlet installation;

3) Temporary lights installed for night watchmen after

a fire at project during construction;

4 Hook-up of water well pump for use during construction ) and for repair of boilers;

5) Wiring for electric sign in front of project;

6) Installation of ground lights in area; 7) Furnishing hoods for kitchen ranges in each apartment; 8 Wiring of outlets for soft drink dispensers; ) 9) Wiring of swimming pool building not included in original plan;

10) Pool furnace and venting system wiring;

11) Grounding system for pool;

12) Installation of additional outlets beyond those contemplated in the contract in order to comply with local and

national electrical code standards;

13) Installation of additional phone conduit omitted from

the original plans and specifications;

14) Lowering of bathroom overhead fixtures and fans after installation upon discovery plumbers were unable to install plumbing according to plans;

15) Move of main electrical service from the exterior of

building after installation to an interior closet to accommodate

Montana Power Company plan alteration regarding location of power transformer pad; and

16) Miscellaneous items n o t covered by c o n t r a c t and done

by Matzinger a t request of Remco's supervisory personnel.

These e x t r a items t o t a l a claimed amount of $13,181.71, i n a d d i t i o n

t o t h e amount due under t h e c o n t r a c t .

A l e t t e r was s e n t t o Matzinger by Richins, t h e p r o j e c t

superintendent, on January 4 , 1974, d i s c u s s i n g t h e claim and noting

Remco's w i l l i n g n e s s t o pay t h e amount claimed f o r a m a j o r i t y of

t h e items. Remco's p o s i t i o n i n t h e l e t t e r was t h a t r e l o c a t i o n of

t h e e l e c t r i c a l s e r v i c e panel and movement of bathroom c e i l i n g

f i x t u r e s was n e c e s s i t a t e d by Matzinger's f a i l u r e t o coordinate h i s

work with t h e o t h e r subcontractors. The l e t t e r a l s o i n d i c a t e d

Remco's opinion t h a t any e x t r a expense incurred i n i n s t a l l a t i o n

of telephones was covered by t h e c o n t r a c t and must be borne by

Matzinger. Remco's agent s t a t e d he would r e q u i r e a d d i t i o n a l informa-

t i o n regarding t h e expenses of wiring and grounding t h e pool and

pool b u i l d i n g before any claims f o r such work would be allowed.

I n t o t a l , Remco conceded i t would pay $5,485.25 plus whatever was

determined t o be e q u i t a b l e f o r work done on t h e pool, i n r e t u r n

f o r t h e r e l e a s e of t h e mechanic's l i e n .

The d i s t r i c t c o u r t found Matzinger was e n t i t l e d t o t h e

$1,245 claimed f o r i n s t a l l a t i o n of t h e a i r - c o n d i t i o n e r o u t l e t s

and t o $847 f o r t h e weatherproof o u t l e t s . The c o u r t held a l l

o t h e r claims were covered by t h e o r i g i n a l c o n t r a c t between t h e

parties. The court a l s o disallowed Matzinger recovery of any

a t t o r n e y f e e s f o r recovery on t h e mechanic's l i e n . Matzinger's

recovery was a l s o reduced by $1173.75, t h e amount t h e d i s t r i c t

c o u r t found t o be due a s an allowance on l i g h t f i x t u r e s t o Remco.

M t z i n g e r appealed. a The primary issue is: Whether a written contract such as

was entered into between the parties here, may be amended or modified

by oral agreement?

Section 13-907, R.C.M. 1947, provides:

"A contract in writing may be altered by a contract in writing, or by an executed oral agreement, and not other- wise. 11

Section 13-727, R.C.M. 1947, defines an executed contract:

"An executed contract is one, the object of which is fully performed. All others are executory."

The parties agree the work for which extra compensation is sought

was performed as claimed by Matzinger. This work was done for the benefit of Remco and enhanced the value of the finished apartment

complex. The disagreement between the parties is in regard to compensation for this extra work. This Court in Dalakow v. Geery,

132 Mont. 457, 464, 465, 318 P.2d 253, summarized the law in

Montana and said:

"Roberts v. Sinnott, 55 Mont. 369, 177 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gramm v. Insurance Unlimited
378 P.2d 662 (Montana Supreme Court, 1963)
Dalakow v. Geery
318 P.2d 253 (Montana Supreme Court, 1957)
Magelssen v. Atwell
451 P.2d 103 (Montana Supreme Court, 1969)
Jenson v. Olson
395 P.2d 465 (Montana Supreme Court, 1964)
Continental Oil Co. v. Bell
21 P.2d 65 (Montana Supreme Court, 1933)
Roberts v. Sinnott
177 P. 252 (Montana Supreme Court, 1918)
Webber v. Killorn
212 P. 852 (Montana Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
Matzinger v. Remco Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/matzinger-v-remco-inc-mont-1976.