AA Construction of Missoula, LLC v. Choice Land Corp.

2011 MT 262, 264 P.3d 709, 362 Mont. 264, 2011 Mont. LEXIS 365
CourtMontana Supreme Court
DecidedOctober 25, 2011
DocketDA 10-0629
StatusPublished
Cited by11 cases

This text of 2011 MT 262 (AA Construction of Missoula, LLC v. Choice Land Corp.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AA Construction of Missoula, LLC v. Choice Land Corp., 2011 MT 262, 264 P.3d 709, 362 Mont. 264, 2011 Mont. LEXIS 365 (Mo. 2011).

Opinion

JUSTICE MORRIS

delivered the Opinion of the Court.

¶1 Waynco Construction, Inc. (Waynco) appeals from the order and the findings of fact and conclusions of law entered by the Fourth Judicial District Court, Missoula County. The District Court concluded that Waynco materially had breached a contract with AAA Construction of Missoula, LLC (AAA). CLR Properties, Inc., and Choice Land Corp. (collectively CLR) appeal the denial of their claim for *266 attorney fees. We affirm.

¶2 Waynco raises the following issues:

¶3 Did the District Court properly conclude that AAA’s bid constituted a binding contract between the parties?

¶4 Did the District Court properly deny CLR’s claim for attorney fees ?

¶5 This case arises from a commercial real estate improvement project in Missoula, Montana. CLR hired Waynco as the general contractor. Waynco selected all subcontractors. Waynco supervised all work performed at the project. Waynco also controlled access to the site.

¶6 Waynco solicited a bid from AAA to perform concrete work. Brady Nelson, AAA’s member/manager, and Robert Rozier, Waynco’s president, walked through the site before AAA submitted its bid. Rozier explained the scope of work to Nelson. Rozier specifically advised Nelson not to bid on demolition and reconstruction for the front of the building.

¶7 Nelson submitted AAA’s bid on March 30,2007. The bid explicitly set forth the scope of work upon which AAA was bidding, including costs and measurements of work to be performed. AAA’s bid estimated the total cost at $94,918.25. Nelson submitted the bid to Chris Wright, the project’s supervisor for Waynco.

¶8 Wright signed AAA’s bid under the section entitled “Acceptance of Proposal.”Wright made interlineations to the proposal, however, by crossing out the words “Acceptance of Proposal” and handwriting on the form ‘Pending contract with owner. Final scope/subcontract to follow. Thanks!”Waynco used AAA’s bid to formulate Waynco’s general contract bid to CLR. CLR accepted Waynco’s bid.

¶9 AAA began work at the project site on May 1, 2007. Waynco requested that AAA perform additional demolition and paving work on the building’s west side. The parties agreed that Waynco would pay AAA an additional $13,500 for this extra work on top of the $94,918.25 bid, for a total contract price of $108,419.25.

¶10 Waynco sent AAA a document entitled ‘Subcontract Agreement” on May 17, 2007-two weeks after AAA had begun work. The Subcontract Agreement contained work beyond what AAA had agreed to perform, including demolition and construction work for the front of the building. The Subcontract Agreement contemplated no increase in compensation for AAA.

¶11 AAA responded with a new bid of $206,858.25 for all the work contained in the Subcontract Agreement. AAA assumed that the Subcontract Agreement had expanded the scope of work in light of *267 Waynco’s directive in the site walk through to omit work for the front of the building. Waynco rejected AAA’s $206,858.25 offer for the scope of work set forth in the Subcontract Agreement. AAA refused, in turn, to perform the additional work without increased compensation. The parties failed in several attempts to negotiate a resolution on price for the additional work.

¶12 Rozier called Nelson on June 6, 2007, to advise Nelson to Tg]et your ... ass into the building and sign the contract, or you’ll never receive a nickel, and I’ll refer this to my lawyer.” AAA left the project that same day as AAA feared that it would not be paid for any of its work. AAA had completed a majority of the work outlined in AAA’s bid by the time that it left the project. Waynco never paid AAA for any labor or materials.

¶13 AAA filed a construction lien on the property in the amount of $88,720.63. CLR petitioned the District Court to substitute a surety bond for the construction lien. The District Court discharged the lien and replaced it with the surety bond.

¶14 AAA filed a complaint against CLR and Waynco. AAA alleged that Waynco had breached the contract. AAA further alleged that CLR had been unjustly enriched from AAA’s work. Waynco filed a counterclaim in which it alleged that AAA had breached the contract.

¶15 All parties filed cross motions for summary judgment. The District Court granted CLR’s motion for summary judgment for the unjust enrichment claims, but both AAA’s and Waynco’s breach of contract claims proceeded to a non-jury trial. The District Court determined that AAA’s bid constituted a binding contract between the parties. Waynco materially had breached the contract by failing to pay AAA for any goods or services that it had provided. The District Court awarded AAA the full amount of its $88,720.63 lien. The District Court also awarded AAA costs of $2,300.22 and attorney’s fees of $23,318.13.

¶16 CLR sought its attorney fees for the lien foreclosure action pursuant to §71-3-124, MCA. CLR argued that the lien was not valid because the District Court discharged the lien in September 2007. The District Court rejected CLR’s claim that AAA’s lien had been invalid. The court noted that it found the lien valid in its November 2009 order, and had discharged the lien only when CLR substituted the surety bond. Waynco and CLR appeal. AAA cross-appeals the District Court’s grant of summary judgment to CLR on its unjust enrichment claim. We need not address this issue in light of our result of the direct appeal issues.

*268 STANDARD OF REVIEW

¶17 We review the factual findings of a District Court sitting without a jury to determine whether they are clearly erroneous. Eldredge v. Asarco Inc., 2011 MT 80, ¶ 30, 360 Mont. 112, 252 P.3d 182. A District Court’s findings are clearly erroneous if they are not supported by substantial evidence, if the District Court has misapprehended the effect of the evidence, or if a review of the record leaves this Court with the definite and firm conviction that a mistake has been committed. Eldredge, ¶ 30. We review the evidence in the light most favorable to the prevailing party when determining whether substantial credible evidence supports the District Court’s findings. Eldredge, ¶ 30. We review for correctness a District Court’s conclusions of law .Eldredge, ¶ 30. We note that whether a contract exists-a central issue in this case-presents a combined issue of fact and law. Johnston v. Palmer, 2007 MT 99, ¶ 38, 337 Mont. 101, 158 P.3d 998.

DISCUSSION

¶18 Issue 1: Did the District Court properly conclude that AAA’s bid constituted a binding contract between the parties?

¶19 Identifiable parties capable of contracting, consent, a lawful object, and sufficient consideration comprise the essential elements of any contract. Zier v. Lewis, 2009 MT 266, ¶ 19, 352 Mont. 76,218 P.3d 465. Consent must be mutual, and the parties must agree upon the same thing, in the same sense. Zier, ¶ 19. Acceptance of an offer on terms that vary from those offered represents a rejection of the offer. Zier, ¶ 19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kratzer Const. v. Hardy Const.
2025 MT 140 (Montana Supreme Court, 2025)
Haffner-Lynn v. Annala
2021 MT 234N (Montana Supreme Court, 2021)
Marriage of Phillips & Bucknum
2020 MT 294N (Montana Supreme Court, 2020)
Vintage Construction, Inc. v. Feighner
2017 MT 109 (Montana Supreme Court, 2017)
Covenant Investments, Inc. v. First Security Bank
2014 MT 14 (Montana Supreme Court, 2014)
Owen v. Skramovsky
2013 MT 348 (Montana Supreme Court, 2013)
Olsen v. Johnston
2013 MT 25 (Montana Supreme Court, 2013)
Robertson v. Steele
2012 MT 127N (Montana Supreme Court, 2012)
Pastimes, LLC v. Clavin
2012 MT 29 (Montana Supreme Court, 2012)
Fronk v. Collins
2011 MT 315 (Montana Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2011 MT 262, 264 P.3d 709, 362 Mont. 264, 2011 Mont. LEXIS 365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aa-construction-of-missoula-llc-v-choice-land-corp-mont-2011.