Kratzer Const. v. Hardy Const.

2025 MT 140
CourtMontana Supreme Court
DecidedJuly 1, 2025
DocketDA 24-0320
StatusPublished
Cited by3 cases

This text of 2025 MT 140 (Kratzer Const. v. Hardy Const.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kratzer Const. v. Hardy Const., 2025 MT 140 (Mo. 2025).

Opinion

07/01/2025

DA 24-0320 Case Number: DA 24-0320

IN THE SUPREME COURT OF THE STATE OF MONTANA

2025 MT 140

BUCK KRATZER, d/b/a KRATZER CONSTRUCTION,

Plaintiff and Appellee,

v.

HARDY CONSTRUCTION CO., INC.,

Defendant and Appellant.

APPEAL FROM: District Court of the Sixteenth Judicial District, In and For the County of Carter, Cause No. DV 2023-9 Honorable Nickolas C. Murnion, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Brandon Hoskins, Bryce Burke, Moulton Bellingham PC, Billings, Montana

For Appellee:

Alex W. Hamman, Calton Hamman & Wolff, P.C., Billings, Montana

Submitted on Briefs: February 5, 2025

Decided: July 1, 2025

Filed: ' ,--6••--•f __________________________________________ Clerk Justice Jim Rice delivered the Opinion of the Court.

¶1 Hardy Construction Co., Inc. (Hardy) appeals the order of the Sixteenth Judicial

District Court, Carter County, granting summary judgment to Plaintiff Buck Kratzer

(Kratzer), and denying summary judgment to Defendant Hardy. The dispute arose out of

a construction subcontract (the Subcontract) between Hardy, as contractor, and Kratzer, as

subcontractor, under which Kratzer was to perform work related to Hardy’s contract to

construct a building addition for the Ekalaka Public Schools (the Project). We address the

following issues:

1. Whether the District Court erred by granting summary judgment to Kratzer, including requiring Hardy to pay Kratzer interest and attorney fees, and by failing to grant summary judgment to Hardy.

2. Whether the District Court erred in establishing the amount owed by Hardy under the Subcontract.

We affirm in part, reverse in part, and remand for further proceedings consistent herewith.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 On March 23, 2021, Kratzer and Hardy entered into the Subcontract, under which

Kratzer agreed to complete work for Hardy related to the Project, including site demolition,

earthwork, utility installation, and concrete work. Kratzer began the contemplated work

and, in March and April, submitted to Hardy two “pay applications” for progress payments,

which Hardy timely paid. Construction quality issues thereafter developed with Kratzer’s

work, related to hot and dry wind conditions at the time Kratzer poured concrete, which

caused uneven drying and dips in the concrete surfaces and required repair work to bring

2 the concrete slab up to industry standards. This issue affected the work of other trade

subcontractors and delayed Hardy’s overall progress on the Project.

¶3 On October 24, 2021, Kratzer submitted Pay Application 3 for the amount of

$92,856.45, which included change orders in the amount of $28,852.94 that had not been

approved by Hardy. Hardy notified Kratzer that it disapproved of Pay Application 3. On

November 12, 2021, Kratzer texted Adam Petersen (Petersen), the project manager for

Hardy, and demanded that Pay Application 3 be paid in full, including the unapproved

change orders, by the end of the month or he would file suit. Petersen responded, stating

“[u]nfortunately that is not how we see it or understand it. Please call us Monday and we

can discuss and come to a resolution.” After some discussion by the parties, on

November 23, 2021, Kratzer submitted to Hardy a reduced amount of $25,332.94 for his

change orders. Petersen verbalized his disapproval with that amount as well, and asked

Kratzer for additional supporting documentation related to the amount requested, as

Kratzer had submitted only line-item amounts.

¶4 On December 6, 2021, Hardy submitted its final pay application to Ekalaka Public

Schools for payment on the entire Project. In the meantime, Kratzer provided some of the

information requested by Hardy pertaining to the change orders included in Pay

Application 3. Hardy promptly requested further information about items contained within

Kratzer’s change orders—specifically, breakdowns of the days and hours Kratzer had

worked. After Kratzer provided these, Hardy notified Kratzer on December 15, 2021, that

Kratzer’s breakdowns were incorrect because they conflicted with the daily progress

reports prepared on the Project. On December 22, 2021, Petersen emailed Kratzer

3 regarding Pay Application 3, stating that Hardy would agree to an additional $4,275 for the

change orders, denying the remaining change order charges because they were for work

that was already within Kratzer’s scope of work under the Subcontract, and that, upon

Kratzer signing a release and waiver, Hardy would issue final payment to Kratzer in the

amount of $81,153. This figure included the amounts for the remaining work under the

Subcontract ($69,878), the approved change orders ($4,275), and retainage ($7,000).

Petersen’s email included an attached “Release and Waiver” and specified that the sum of

$80,341.471 would be paid to Kratzer upon Kratzer’s signing the release and waiver.

Petersen’s correspondence did not require a release and waiver form signed by Kratzer’s

subcontractors and suppliers.

¶5 Six months later, in May 2022, Jason Arrowsmith (Arrowsmith), president of

Hardy, emailed Kratzer, stating “I haven’t heard back from you in months, and would like

to get you paid the $80,341.47 we owe you. Please sign the release and waiver and we’ll

get the check sent out immediately.” Kratzer requested Hardy resend the release form with

the corrected amount of $81,153, which Hardy did. However, Kratzer ultimately

responded that he would not sign the release and waiver, and requested, through legal

counsel, payment of the full amount he had submitted in Pay Application 3, or $92,856.45.

More time passed, and in October 2022, Kratzer conveyed to Hardy that he was waiving

disputed amounts he had requested in Pay Application 3, and instead demanding payment

1 This amount was initially utilized by Hardy as the amount Kratzer was owed. As noted herein, Kratzer later indicated that the correct calculation would be $81,153. Hardy acknowledged that Kratzer was correct and that it had made a math error. It thereafter utilized $81,153 as its calculation of the amount it believed Kratzer was owed. 4 of $81,153 plus 18% per annum interest commencing November 21, 2021, or $13,326.66,

for a total amount of $94,479.66.

¶6 On January 17, 2023, Hardy sent Kratzer a check for $81,153 along with a release

and waiver for Kratzer to sign, but maintained that Kratzer was not owed the requested

interest. On January 24, 2023, Kratzer again declined payment, reiterating that he was

entitled to the interest. On January 26, 2023, Hardy once again tendered payment to

Kratzer for $81,153, and this time indicated that Kratzer’s acceptance of the payment was

not conditioned upon his signing of a release and waiver, and that, further, Hardy would

not view Kratzer’s acceptance of the payment as a waiver of his claim to interest. However,

Kratzer again rejected the proffered payment.

¶7 On February 17, 2023, Kratzer filed this action to collect the amount owed under

the Subcontract, as well as interest and attorney fees, alleging breach of contract. As the

matter progressed, Hardy’s counsel argued that Kratzer’s pleadings improperly utilized

statements made by Hardy’s employees to establish the amount owed, in contravention of

M. R. Evid. 408, because the referenced statements were part of settlement offers Hardy

had conveyed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monarch v. Petra
2025 MT 184 (Montana Supreme Court, 2025)
State v. M. Walton
2025 MT 184 (Montana Supreme Court, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2025 MT 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kratzer-const-v-hardy-const-mont-2025.