Kratzer Const. v. Hardy Const.

2025 MT 140
Montana Supreme Court·Decided July 1, 2025·No. DA 24-0320·Published·Cited by 3 cases

Opinion

07/01/2025

DA 24-0320

Case Number: DA 24-0320

IN THE SUPREME COURT OF THE STATE OF MONTANA 2025 MT 140

BUCK KRATZER, d/b/a KRATZER CONSTRUCTION,

Plaintiff and Appellee,

v.

HARDY CONSTRUCTION CO., INC., Defendant and Appellant.

APPEAL FROM: District Court of the Sixteenth Judicial District, In and For the County of Carter, Cause No. DV 2023-9 Honorable Nickolas C. Murnion, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Brandon Hoskins, Bryce Burke, Moulton Bellingham PC, Billings, Montana

For Appellee:

Alex W. Hamman, Calton Hamman & Wolff, P.C., Billings, Montana

Submitted on Briefs: February 5, 2025 Decided: July 1, 2025

Filed:

' ,--6••--•f

Clerk

Justice Jim Rice delivered the Opinion of the Court.

¶1 Hardy Construction Co., Inc. (Hardy) appeals the order of the Sixteenth Judicial District Court, Carter County, granting summary judgment to Plaintiff Buck Kratzer (Kratzer), and denying summary judgment to Defendant Hardy. The dispute arose out of a construction subcontract (the Subcontract) between Hardy, as contractor, and Kratzer, as subcontractor, under which Kratzer was to perform work related to Hardy’s contract to construct a building addition for the Ekalaka Public Schools (the Project). We address the following issues:

1. Whether the District Court erred by granting summary judgment to Kratzer, including requiring Hardy to pay Kratzer interest and attorney fees, and by failing to grant summary judgment to Hardy.

2. Whether the District Court erred in establishing the amount owed by Hardy under the Subcontract.

We affirm in part, reverse in part, and remand for further proceedings consistent herewith.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 On March 23, 2021, Kratzer and Hardy entered into the Subcontract, under which Kratzer agreed to complete work for Hardy related to the Project, including site demolition, earthwork, utility installation, and concrete work. Kratzer began the contemplated work and, in March and April, submitted to Hardy two “pay applications” for progress payments, which Hardy timely paid. Construction quality issues thereafter developed with Kratzer’s work, related to hot and dry wind conditions at the time Kratzer poured concrete, which caused uneven drying and dips in the concrete surfaces and required repair work to bring

the concrete slab up to industry standards. This issue affected the work of other trade subcontractors and delayed Hardy’s overall progress on the Project.

¶3 On October 24, 2021, Kratzer submitted Pay Application 3 for the amount of $92,856.45, which included change orders in the amount of $28,852.94 that had not been approved by Hardy. Hardy notified Kratzer that it disapproved of Pay Application 3. On November 12, 2021, Kratzer texted Adam Petersen (Petersen), the project manager for Hardy, and demanded that Pay Application 3 be paid in full, including the unapproved change orders, by the end of the month or he would file suit. Petersen responded, stating “[u]nfortunately that is not how we see it or understand it. Please call us Monday and we can discuss and come to a resolution.” After some discussion by the parties, on November 23, 2021, Kratzer submitted to Hardy a reduced amount of $25,332.94 for his change orders. Petersen verbalized his disapproval with that amount as well, and asked Kratzer for additional supporting documentation related to the amount requested, as Kratzer had submitted only line-item amounts.

¶4 On December 6, 2021, Hardy submitted its final pay application to Ekalaka Public Schools for payment on the entire Project. In the meantime, Kratzer provided some of the information requested by Hardy pertaining to the change orders included in Pay Application 3. Hardy promptly requested further information about items contained within Kratzer’s change orders—specifically, breakdowns of the days and hours Kratzer had worked. After Kratzer provided these, Hardy notified Kratzer on December 15, 2021, that Kratzer’s breakdowns were incorrect because they conflicted with the daily progress reports prepared on the Project. On December 22, 2021, Petersen emailed Kratzer

regarding Pay Application 3, stating that Hardy would agree to an additional $4,275 for the change orders, denying the remaining change order charges because they were for work that was already within Kratzer’s scope of work under the Subcontract, and that, upon Kratzer signing a release and waiver, Hardy would issue final payment to Kratzer in the amount of $81,153. This figure included the amounts for the remaining work under the Subcontract ($69,878), the approved change orders ($4,275), and retainage ($7,000). Petersen’s email included an attached “Release and Waiver” and specified that the sum of $80,341.471 would be paid to Kratzer upon Kratzer’s signing the release and waiver. Petersen’s correspondence did not require a release and waiver form signed by Kratzer’s subcontractors and suppliers.

¶5 Six months later, in May 2022, Jason Arrowsmith (Arrowsmith), president of Hardy, emailed Kratzer, stating “I haven’t heard back from you in months, and would like to get you paid the $80,341.47 we owe you. Please sign the release and waiver and we’ll get the check sent out immediately.” Kratzer requested Hardy resend the release form with the corrected amount of $81,153, which Hardy did. However, Kratzer ultimately responded that he would not sign the release and waiver, and requested, through legal counsel, payment of the full amount he had submitted in Pay Application 3, or $92,856.45. More time passed, and in October 2022, Kratzer conveyed to Hardy that he was waiving disputed amounts he had requested in Pay Application 3, and instead demanding payment

1 This amount was initially utilized by Hardy as the amount Kratzer was owed. As noted herein, Kratzer later indicated that the correct calculation would be $81,153. Hardy acknowledged that Kratzer was correct and that it had made a math error. It thereafter utilized $81,153 as its calculation of the amount it believed Kratzer was owed.

of $81,153 plus 18% per annum interest commencing November 21, 2021, or $13,326.66, for a total amount of $94,479.66.

¶6 On January 17, 2023, Hardy sent Kratzer a check for $81,153 along with a release and waiver for Kratzer to sign, but maintained that Kratzer was not owed the requested interest. On January 24, 2023, Kratzer again declined payment, reiterating that he was entitled to the interest. On January 26, 2023, Hardy once again tendered payment to Kratzer for $81,153, and this time indicated that Kratzer’s acceptance of the payment was not conditioned upon his signing of a release and waiver, and that, further, Hardy would not view Kratzer’s acceptance of the payment as a waiver of his claim to interest. However, Kratzer again rejected the proffered payment.

¶7 On February 17, 2023, Kratzer filed this action to collect the amount owed under the Subcontract, as well as interest and attorney fees, alleging breach of contract. As the matter progressed, Hardy’s counsel argued that Kratzer’s pleadings improperly utilized statements made by Hardy’s employees to establish the amount owed, in contravention of M. R. Evid. 408, because the referenced statements were part of settlement offers Hardy had conveyed. Kratzer amended the allegations of his complaint, and in subsequent discovery, Hardy agreed that, upon satisfaction of the conditions of the Subcontract for provision of waiver and release of his subcontractors, Kratzer would be entitled to $81,153, less recoverable damages under Hardy’s counterclaims for breach of contract for work defects, and attorney fees. Hardy continued to oppose Kratzer’s claims for interest and attorney fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Kratzer Const. v. Hardy Const., 2025 MT 140 (Mo. 2025).

2025 MT 140 (Kratzer Const. v. Hardy Const.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Monarch v. Petra
2025 MT 184 (Montana Supreme Court, 2025)
State v. M. Walton
2025 MT 184 (Montana Supreme Court, 2025)