08/19/2025
DA 24-0760 Case Number: DA 24-0760
IN THE SUPREME COURT OF THE STATE OF MONTANA 2025 MT 184
MONARCH HEATING AND COOLING, LLC,
Plaintiff and Appellee,
v.
PETRA, INC.,
Defendant and Appellant,
BOZEMAN WEST APARTMENTS LP; SACCOCCIA LANDS III LLC; BCRH AVION VENTURE LLC; STOCKMAN BANK OF MONTANA; WCW OLYMPUS BOZEMAN LLC; and JOHN DOES 1-10,
Defendants. _______________________________________________
BOZEMAN WEST APARTMENTS LP, SACCOCCIA LANDS III LLC, and PETRA, INC.,
Counterclaimants,
Counter-Defendant. ____________________________________
BOZEMAN WEST APARTMENTS LP; and SACCOCCIA LANDS III LLC,
Cross-Claimants
v. PETRA, INC.,
Cross-Defendant.
APPEAL FROM: District Court of the Eighteenth Judicial District, In and For the County of Gallatin, Cause No. DV 24-126 Honorable Andrew Breuner, Presiding Judge
COUNSEL OF RECORD:
For Appellants:
Edward J. Guza, Lance F. Carl, E.J. Guza & Associates, Bozeman, Montana
For Appellee:
Trent Baker, Datsopoulos, MacDonald & Lind, PC, Missoula, Montana
Cherche Prezeau, Jackson Maynard, Christensen & Prezeau, PLLP, Helena, Montana
Jon A. Wilson, Nathan A. Burke, Brown Law Firm, P.C., Billings, Montana
Submitted on Briefs: May 7, 2025
Decided: August 19, 2025
Filed:
__________________________________________ Clerk
2 Justice James Jeremiah Shea delivered the Opinion of the Court.
¶1 Petra, Inc. (“Petra”) appeals from the Eighteenth Judicial District Court, Gallatin
County’s December 10, 2024 order denying its motion to stay proceedings and compel
arbitration. Petra appeals the District Court’s determination that it had waived its right to
compel arbitration. We affirm.
¶2 We restate the issue on appeal as follows:
Whether the District Court erred when it determined that Petra had waived its right to compel arbitration.
FACTUAL AND PROCEDURAL BACKGROUND
¶3 On May 13, 2021, Petra contracted with Bozeman West Apartments LP to serve as
the primary contractor on an apartment complex building project. On July 23, 2021, Petra
entered into a subcontract with Monarch Heating and Cooling, LLC (“Monarch”) for
Monarch to install the HVAC systems in the complex. Article 22.2 of the subcontract
between Petra and Monarch contained an arbitration clause providing that “[a]ll other
claims, disputes, and other matters in question between [Petra] and [Monarch] arising out
of, or relating to, the Main Contract or this Subcontract . . . shall be decided by arbitration
at [Petra’s] sole and exclusive option.” Monarch asserts that it began performance of the
subcontract immediately, incurring costs in the process.
¶4 The relationship between Petra and Monarch deteriorated over the next three years,
and on February 2, 2024, Monarch filed suit against Petra,1 alleging breach of contract,
1 Monarch also named several other defendants in its Complaint and Amended Complaint, but those defendants are not involved in this appeal. 3 breach of the covenant of good faith and fair dealing, negligent misrepresentation, unjust
enrichment, and a violation of Montana’s Prompt Payment Act. Monarch filed an
Amended Complaint on April 25, 2024, and served it on Petra’s registered agent on May 1,
2024. For reasons not clear from the record, Petra’s registered agent did not forward the
Amended Complaint on to Petra, and Petra did not file a timely answer to Monarch’s
Amended Complaint. On May 29, 2024, the District Court entered a default against Petra
at Monarch’s request.
¶5 After learning that Petra’s agent had not provided Petra with the Amended
Complaint, Monarch served Petra at its offices in Idaho on July 1, 2024. At Petra’s request,
Monarch stipulated to setting aside the entry of default and on July 25, 2024, Monarch and
Petra filed a joint Stipulated Motion to Set Aside Entry of Default, which the District Court
granted on July 30, 2024. Petra filed its Answer to Monarch’s Amended Complaint,
Counterclaim, and Request for Jury Trial on August 20, 2024. The Answer included 14
affirmative defenses, including “any and all affirmative defenses alleged by any other
party.” Monarch filed an answer to Petra’s counterclaims on September 9, 2024. Petra
filed an Amended Answer on September 10, 2024, which contained 16 affirmative
defenses, including that “Monarch’s claims in this litigation are subject to a valid and
binding agreement to arbitrate.”
¶6 On October 25, 2024, Petra moved to stay the proceedings and compel arbitration,
citing Article 22.2 of the subcontract. The District Court denied Petra’s motion on
December 10, 2024. In its order, the District Court reasoned that Petra had “acted in a
4 deliberate manner that was inconsistent with invoking its right to demand arbitration”
based, in part, on the facts that “Monarch did not have the right to invoke the arbitration
requirement,” “Petra secured and then filed its stipulated motion to set aside default”
without asserting the right, and it did not assert the right until “nearly six (6) months after
it was lawfully served with” the Amended Complaint. The District Court determined that
Petra’s delay in asserting its arbitration right prejudiced Monarch based on the costs
Monarch incurred after it “was compelled to move for default; arrange for a second service
of its complaint in Idaho; stipulate to setting aside default; wait nearly four (4) months for
an answer to its [Amended Complaint]; be served with counterclaims; answer
counterclaims; and then litigate the present motion to compel arbitration.”
STANDARD OF REVIEW
¶7 We review district court rulings on motions to compel arbitration de novo for
correctness under the governing standards of the Federal Arbitration Act (“FAA”), 9
U.S.C. §§ 2–402, or the Montana Uniform Arbitration Act (“MUAA”), Title 27, chapter 5,
MCA, as applicable. Peeler v. Rocky Mountain Log Homes Can., Inc., 2018 MT 297, ¶ 11,
393 Mont. 396, 431 P.3d 911.
DISCUSSION
¶8 Whether the District Court erred when it determined that Petra had waived its right to compel arbitration.
¶9 A party asserting that another party has waived the right to arbitrate bears the burden
of demonstrating (1) the other party’s knowledge of the right to arbitrate, (2) acts by the
other party that are inconsistent with the right to arbitrate, and (3) resulting prejudice.
5 Mont. Pub. Emps. Ass’n v. City of Bozeman, 2015 MT 69, ¶ 15, 378 Mont. 337, 343 P.3d
1233 (MPEA) (citing Downey v. Christensen, 251 Mont. 386, 389, 825 P.2d 557, 558
(1992)). At the outset, Monarch asserts that we ought to modify the Downey factors in
light of the United States Supreme Court’s recent decision in Morgan v. Sundance, Inc.,
596 U.S. 411, 142 S. Ct. 1708 (2022). Petra responds that Morgan is inapplicable because
it concerned the proper factors for courts to consider when deciding a motion to compel
arbitration under the FAA, and this case is governed by the MUAA.
¶10 Because we ultimately agree with the District Court’s determination that Monarch
met its burden under Downey, we need not address Morgan’s application to this case, and
we decline to consider Monarch’s argument on this point. The parties do not dispute that
Free access — add to your briefcase to read the full text and ask questions with AI
08/19/2025
DA 24-0760 Case Number: DA 24-0760
IN THE SUPREME COURT OF THE STATE OF MONTANA 2025 MT 184
MONARCH HEATING AND COOLING, LLC,
Plaintiff and Appellee,
v.
PETRA, INC.,
Defendant and Appellant,
BOZEMAN WEST APARTMENTS LP; SACCOCCIA LANDS III LLC; BCRH AVION VENTURE LLC; STOCKMAN BANK OF MONTANA; WCW OLYMPUS BOZEMAN LLC; and JOHN DOES 1-10,
Defendants. _______________________________________________
BOZEMAN WEST APARTMENTS LP, SACCOCCIA LANDS III LLC, and PETRA, INC.,
Counterclaimants,
Counter-Defendant. ____________________________________
BOZEMAN WEST APARTMENTS LP; and SACCOCCIA LANDS III LLC,
Cross-Claimants
v. PETRA, INC.,
Cross-Defendant.
APPEAL FROM: District Court of the Eighteenth Judicial District, In and For the County of Gallatin, Cause No. DV 24-126 Honorable Andrew Breuner, Presiding Judge
COUNSEL OF RECORD:
For Appellants:
Edward J. Guza, Lance F. Carl, E.J. Guza & Associates, Bozeman, Montana
For Appellee:
Trent Baker, Datsopoulos, MacDonald & Lind, PC, Missoula, Montana
Cherche Prezeau, Jackson Maynard, Christensen & Prezeau, PLLP, Helena, Montana
Jon A. Wilson, Nathan A. Burke, Brown Law Firm, P.C., Billings, Montana
Submitted on Briefs: May 7, 2025
Decided: August 19, 2025
Filed:
__________________________________________ Clerk
2 Justice James Jeremiah Shea delivered the Opinion of the Court.
¶1 Petra, Inc. (“Petra”) appeals from the Eighteenth Judicial District Court, Gallatin
County’s December 10, 2024 order denying its motion to stay proceedings and compel
arbitration. Petra appeals the District Court’s determination that it had waived its right to
compel arbitration. We affirm.
¶2 We restate the issue on appeal as follows:
Whether the District Court erred when it determined that Petra had waived its right to compel arbitration.
FACTUAL AND PROCEDURAL BACKGROUND
¶3 On May 13, 2021, Petra contracted with Bozeman West Apartments LP to serve as
the primary contractor on an apartment complex building project. On July 23, 2021, Petra
entered into a subcontract with Monarch Heating and Cooling, LLC (“Monarch”) for
Monarch to install the HVAC systems in the complex. Article 22.2 of the subcontract
between Petra and Monarch contained an arbitration clause providing that “[a]ll other
claims, disputes, and other matters in question between [Petra] and [Monarch] arising out
of, or relating to, the Main Contract or this Subcontract . . . shall be decided by arbitration
at [Petra’s] sole and exclusive option.” Monarch asserts that it began performance of the
subcontract immediately, incurring costs in the process.
¶4 The relationship between Petra and Monarch deteriorated over the next three years,
and on February 2, 2024, Monarch filed suit against Petra,1 alleging breach of contract,
1 Monarch also named several other defendants in its Complaint and Amended Complaint, but those defendants are not involved in this appeal. 3 breach of the covenant of good faith and fair dealing, negligent misrepresentation, unjust
enrichment, and a violation of Montana’s Prompt Payment Act. Monarch filed an
Amended Complaint on April 25, 2024, and served it on Petra’s registered agent on May 1,
2024. For reasons not clear from the record, Petra’s registered agent did not forward the
Amended Complaint on to Petra, and Petra did not file a timely answer to Monarch’s
Amended Complaint. On May 29, 2024, the District Court entered a default against Petra
at Monarch’s request.
¶5 After learning that Petra’s agent had not provided Petra with the Amended
Complaint, Monarch served Petra at its offices in Idaho on July 1, 2024. At Petra’s request,
Monarch stipulated to setting aside the entry of default and on July 25, 2024, Monarch and
Petra filed a joint Stipulated Motion to Set Aside Entry of Default, which the District Court
granted on July 30, 2024. Petra filed its Answer to Monarch’s Amended Complaint,
Counterclaim, and Request for Jury Trial on August 20, 2024. The Answer included 14
affirmative defenses, including “any and all affirmative defenses alleged by any other
party.” Monarch filed an answer to Petra’s counterclaims on September 9, 2024. Petra
filed an Amended Answer on September 10, 2024, which contained 16 affirmative
defenses, including that “Monarch’s claims in this litigation are subject to a valid and
binding agreement to arbitrate.”
¶6 On October 25, 2024, Petra moved to stay the proceedings and compel arbitration,
citing Article 22.2 of the subcontract. The District Court denied Petra’s motion on
December 10, 2024. In its order, the District Court reasoned that Petra had “acted in a
4 deliberate manner that was inconsistent with invoking its right to demand arbitration”
based, in part, on the facts that “Monarch did not have the right to invoke the arbitration
requirement,” “Petra secured and then filed its stipulated motion to set aside default”
without asserting the right, and it did not assert the right until “nearly six (6) months after
it was lawfully served with” the Amended Complaint. The District Court determined that
Petra’s delay in asserting its arbitration right prejudiced Monarch based on the costs
Monarch incurred after it “was compelled to move for default; arrange for a second service
of its complaint in Idaho; stipulate to setting aside default; wait nearly four (4) months for
an answer to its [Amended Complaint]; be served with counterclaims; answer
counterclaims; and then litigate the present motion to compel arbitration.”
STANDARD OF REVIEW
¶7 We review district court rulings on motions to compel arbitration de novo for
correctness under the governing standards of the Federal Arbitration Act (“FAA”), 9
U.S.C. §§ 2–402, or the Montana Uniform Arbitration Act (“MUAA”), Title 27, chapter 5,
MCA, as applicable. Peeler v. Rocky Mountain Log Homes Can., Inc., 2018 MT 297, ¶ 11,
393 Mont. 396, 431 P.3d 911.
DISCUSSION
¶8 Whether the District Court erred when it determined that Petra had waived its right to compel arbitration.
¶9 A party asserting that another party has waived the right to arbitrate bears the burden
of demonstrating (1) the other party’s knowledge of the right to arbitrate, (2) acts by the
other party that are inconsistent with the right to arbitrate, and (3) resulting prejudice.
5 Mont. Pub. Emps. Ass’n v. City of Bozeman, 2015 MT 69, ¶ 15, 378 Mont. 337, 343 P.3d
1233 (MPEA) (citing Downey v. Christensen, 251 Mont. 386, 389, 825 P.2d 557, 558
(1992)). At the outset, Monarch asserts that we ought to modify the Downey factors in
light of the United States Supreme Court’s recent decision in Morgan v. Sundance, Inc.,
596 U.S. 411, 142 S. Ct. 1708 (2022). Petra responds that Morgan is inapplicable because
it concerned the proper factors for courts to consider when deciding a motion to compel
arbitration under the FAA, and this case is governed by the MUAA.
¶10 Because we ultimately agree with the District Court’s determination that Monarch
met its burden under Downey, we need not address Morgan’s application to this case, and
we decline to consider Monarch’s argument on this point. The parties do not dispute that
Monarch met the first Downey factor because Petra concedes that it has always been aware
of its option to insist on arbitration of Monarch’s claims. Therefore, the outcome of this
case hinges on whether Petra acted inconsistently with its right to insist on arbitration, and
whether it would prejudice Monarch to grant Petra’s motion.
¶11 Petra argues that the District Court erred when it determined that Petra acted
inconsistently with its right to arbitrate because the District Court based its determination
on Petra’s inaction rather than inconsistent action. In MPEA, we determined that MPEA
had not acted inconsistently with its right to arbitrate by failing to bring an action to compel
arbitration for over four years. MPEA, ¶ 18. Petra’s reliance on MPEA is misplaced. In
MPEA, MPEA’s first action out of the gate was to file a case specifically to compel
arbitration. MPEA, ¶ 4. MPEA not only acted consistently with its right to insist on
6 arbitration from the start of the case, it filed the case in order to enforce that right. As the
District Court noted, Petra did not insist on its right to arbitrate until six months after it was
lawfully served and almost four months after it was served at its Idaho headquarters.
¶12 Petra asserts that the actions it did take once it was aware of the case were at least
as consistent with its insistence on its right as the actions we found sufficient in Downey
itself. In opposing the motion to compel arbitration in Downey, the Downeys asserted four
inconsistent actions demonstrated waiver:
(1) [The opposing parties’] filing of formal answers rather than motions to dismiss or stay proceedings; (2) [opposing parties’] filing of a counterclaim; (3) [opposing parties’] participation in preparing a discovery schedule; and (4) [opposing parties’] participation in discovery before they filed motions to compel arbitration.
Downey, 251 Mont. at 390, 825 P.2d at 558. Petra asserts that it took even less inconsistent
action than the opposing parties in Downey because it did not engage in the discovery
process at all, even though its first response after the default was set aside to file an answer
and counterclaims. But Petra leaves out of its narrative a critical distinction between this
case and Downey—the Stipulated Motion to Set Aside Entry of Default. Monarch asserts,
and Petra does not dispute, that Petra did not mention its intent to compel arbitration when
it reached out to Monarch to secure its consent to set aside the default. Petra asserts that
its failure to mention its intent to compel arbitration is immaterial because Monarch and
the District Court both agreed that there was good cause to set aside the default. But we
cannot know what arguments Monarch might have made against setting aside the default
since Monarch did not feel the need to make them because Petra did not alert Monarch of
7 its intent to compel arbitration when it secured Monarch’s stipulation. What we do know
is that Petra sought to reenter the litigation with no mention of its intent to leave it again
by compelling arbitration.
¶13 Yet another factor distinguishing this case from Downey is the Answer Petra filed
almost a month later. In Downey, we found that the opposing parties’ explicit invocation
of arbitration in their answers excused their later participation because it put the Downeys
on notice at the outset that the opposing parties intended to exercise their right. Downey,
251 Mont. at 390, 825 P.2d at 558. Although Petra’s Answer identified 14 affirmative
defenses it intended to rely on, the subcontract’s arbitration clause was not among them.
Petra asserts that the Answer implicitly included an arbitration defense by incorporating
“any and all affirmative defenses alleged by any other party,” because its co-defendants
had asserted “[a]ll affirmative defenses set forth in M. R. Civ. P. 8(c)(1),” which includes
arbitration. Petra’s three-layered incorporation-by-reference argument hardly evinces a
clear intent to invoke arbitration at a later date. Petra evidently did not think so either
because it filed an Amended Answer in order to explicitly list arbitration among its
defenses. The District Court did not err when it determined that Petra had acted
inconsistently with its right to arbitrate because Petra sought to reenter the litigation with
no mention of its intent to leave the litigation at a later date and reinforced that position
with its subsequent Answer.
¶14 Petra argues that the District Court erred by determining that its invocation of its
right to arbitrate would prejudice Monarch. We have found prejudice in this context where
8 the non-moving party has been forced to “spend both time and money in trial preparation,”
and lost a tactical advantage as a result of the moving party’s actions inconsistent with its
arbitration right. Holm-Sutherland Co. v. Town of Shelby, 1999 MT 150, ¶ 33, 295
Mont. 65, 982 P.2d 1053. There is no question that Monarch was forced to spend time and
money responding to Petra’s counterclaims, as evidenced by its September 9, 2024 answer.
But the most significant prejudice consideration is Monarch’s voluntary surrender of its
default when it was under the impression that Petra would engage in the litigation. By
stipulating to set aside the default, Monarch surrendered its right to argue under M. R.
Civ. P. 55(c) that it would be prejudiced. While we may never know what Monarch might
have argued had it known that Petra intended to raise the arbitration provision, there is no
dispute that Monarch surrendered Petra’s default before Petra advised that it intended to
seek to compel arbitration. The District Court did not err when it determined that Petra’s
attempt to compel arbitration would prejudice Monarch.
CONCLUSION
¶15 The District Court did not err when it determined that Petra had waived its right to
compel arbitration after Petra reentered the litigation without asserting this right in either
its Stipulated Motion to Set Aside Entry of Default or its Answer.
/S/ JAMES JEREMIAH SHEA
9 We Concur:
/S/ CORY J. SWANSON /S/JIM RICE /S/INGRID GUSTAFSON /S/LAURIE MCKINNON