Matos v. Rohrer

661 P.2d 443, 203 Mont. 162
CourtMontana Supreme Court
DecidedMarch 23, 1983
Docket82-242
StatusPublished
Cited by7 cases

This text of 661 P.2d 443 (Matos v. Rohrer) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matos v. Rohrer, 661 P.2d 443, 203 Mont. 162 (Mo. 1983).

Opinion

*164 MR. JUSTICE WEBER

delivered the opinion of the Court.

Plaintiff appeals from a judgment in the Nineteenth Judicial District Court, Lincoln County, in this action for lien foreclosure. We affirm the District Court, but remand for a redetermination of fees and costs.

Plaintiff presents the following issues for review:

1. Whether the District Court erred in admitting parol evidence to “modify” the written agreement between the parties.

2. Whether Matos is entitled to an equitable quantum meruit for services and materials of which respondents received the benefit.

3. Whether the District Court erred in ruling that Matos’ mechanic’s lien was insufficient.

4. Whether the trial court’s findings of fact and conclusions of law are supported by substantial credible evidence.

Defendants seek attorney’s fees on appeal. Plaintiff seeks to have the fees and costs assessed against him overturned.

In the winter and spring of 1980, defendants Dann and Paula Rohrer (Rohrers) discussed with plaintiff Edward Matos (Matos), a local building contractor, the possibility of his building them a passive solar home. Matos began construction on the Rohrer home in May of 1980. On June 23, 1980, at Rohrers’ request, Matos prepared a proposal, which stated in pertinent part:

“Rohrers agree on a cost & $16,000 with $86,000 as a total cost in mind using attached cost guide-lines
“Rohrer agrees to do complete plumbing and electrical work
“Contractor to buy materials
“All of the above work to be completed in a substantial and workmanlike manner for the sum of cost plus $16,000. . . Payments to be made each_ as the work progresses to the value of_(95%) per cent of all work completed. The entire amount of contract to be paid within 10 days after completion. Any alteration or deviation from *165 the above specifications involving extra cost of material or labor will only be executed upon written orders for same, and will become an extra charge over the sum mentioned in this contract. All agreements must be made in writing.” (Emphasis added)

Included with the contract was a list of cost guidelines, which the parties accept as part of the contract, and which stated in pertinent part:

“cost guide lines to < [less than] $86,000
not to exceed
Fireplace 4,000
Plumbing & electrical mat. 4,500
Roof $65 @ square $65 @ sq.
Siding $700 M $700 M
Grhouse. siding $400 M $400 M
FI. covering $12 yds.
Cabinets (kit. & bath) $4,000
Built-ins kept moderate Interior ceiling $400 M”
(Emphasis in original)

The parties signed the contract on June 30, 1980.

During the summer of 1980, the Rohrers talked with Matos on several occasions. Matos repeatedly assured them that the costs of lumber and certain other materials were lower than anticipated. During this period, the Rohrers requested a number of items for the home, which included extra built-in cabinets, a baywindow, hard-core instead of hollow-core doors, additional or more costly lighting and plumbing fixtures, various changes in windows and ceiling, and additional masonry work. There was no written agreement to charge extra for additional work, nor was there evidence of an explicit agreement, written or oral, to waive the contract provision requiring such a written agreement. Rohrers testified that they orally agreed to pay Matos $500 more to cover the extra cost of the electrical fixtures and doors, but that there were no other additional charges

*166 agreed upon.

As the building of the house progressed, Matos paid most of the bills for labor and materials and was paid in turn by Rohrers, “when needed”.

In September of 1980, Matos informed Rohrers that the house was costing more than anticipated, and that the final price would be between $95,000 and $100,000. Rohrers were very upset, and indicated they did not know where they would get the additional money. Matos insists the Rohrers neither ordered him to stop working nor put a ceiling on costs. Rohrers are equally adamant in their claim that they told Matos if he couldn’t finish the house for between $90,000 and $91,000, then “he and the workmen should just quit, and we would finish it as we could afford to.” According to Rohrers, Matos said “he would try and see what he could do.”

There was no further contact between the parties until the second week in October, when, upon Rohrers’ return from a trip to Chicago, Matos informed them the house would cost over $100,000. At that time, Rohrers ordered Matos to quit working on the house. Matos’ final price on the home was $103,544.45. Rohrers paid Matos a total of $86,500. The parties agree that the total cost of labor and materials for the house was $84,881.13.

On December 23, 1980, Matos filed a mechanic’s lien against Rohrers’ property in the amount of $18,525.00. The lien provided in pertinent part: “That it is the intention of EDWARD MATOS, of Libby, Montana, claimant herein, to claim and hold a lien upon that certain tract or parcel of land hereinafter described, for the sum of $18,525.00 with interest thereon at the rate of 10% per annum from 10/24/ 80 until paid.

"...
“That the names of the owners of said premises described above at the date of this instrument according to the real estate records of Lincoln County, Montana, are Dann D. Rohrer and Paula Rohrer, of Libby, Montana.” (Emphasis *167 added)

The lien incorporated by reference two attachments, the first being a legal description of the parcel of land upon which the improvements were made, the second being a specific list of additional costs amounting to $18,525.00.

On February 19, 1981, Matos filed a complaint, seeking judgment against Rohrers in the amount of $18,525.00, to be derived from the proceeds of a sheriffs sale of the Rohrer property. Matos also sought judgment that his lien had priority over liens established by several material men, named as defendants in this action.

Rohrers answered that (1) the lien was invalid for failing to describe the “building structure or improvement” to which it attached; (2) under the contract and in accordance with Matos’ subsequent verbal assurances, the ceiling price of the house was $86,000; and (3) Matos was responsible for any unpaid obligations from the construction of the house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skyline Consulting v. Mortensen
2022 MT 192 (Montana Supreme Court, 2022)
Dck Worldwide Holdings Inc. v. CH SP Acquisition LLC
2015 MT 225 (Montana Supreme Court, 2015)
Lewistown Miller Construction Co. v. Martin
2011 MT 325 (Montana Supreme Court, 2011)
Sheldon v. Flathead County
707 P.2d 540 (Montana Supreme Court, 1985)
Price Building Service, Inc. v. Christensen
697 P.2d 1344 (Montana Supreme Court, 1985)
Kravik v. Lewis
691 P.2d 1373 (Montana Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
661 P.2d 443, 203 Mont. 162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matos-v-rohrer-mont-1983.