Skyline Consulting v. Mortensen

2022 MT 192, 518 P.3d 462
Montana Supreme Court·Decided October 4, 2022·No. DA 22-0103·Published·Cited by 1 cases

Opinion

10/04/2022

DA 22-0103 Case Number: DA 22-0103

IN THE SUPREME COURT OF THE STATE OF MONTANA

2022 MT 192

SKYLINE CONSULTING GROUP,

Plaintiff and Appellant,

v.

MORTENSEN WOODWORK, INC.,

Defendant and Appellee.

APPEAL FROM: District Court of the Eighteenth Judicial District, In and For the County of Gallatin, Cause No. DV-21-1215B Honorable Rienne H. McElyea, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Cherche Prezeau, Colin Phelps, Christensen & Prezeau, PLLP, Helena, Montana

For Appellee:

Ryan Lorenz, E.J. Guza & Associates, Bozeman, Montana

James R. Artzer, Henner & Scarbrough, LLP, Atlanta, Georgia

Submitted on Briefs: August 17, 2022

Decided: October 4, 2022

Filed: ir--6--if __________________________________________ Clerk Justice Beth Baker delivered the Opinion of the Court.

¶1 Skyline Consulting Group appeals an order entered by the Eighteenth Judicial

District Court, Gallatin County, denying its Motion to Vacate and Set Aside Bond

Substitution and Reinstate Construction Lien. We restate and address the following two

issues:

1. Did the District Court err in concluding that Mortensen Woodwork, a subcontractor, could file a substitute bond when Montana law authorizes only a “contracting owner” to do so?

2. Did the District Court err in concluding that Skyline Consulting Group waived its right to challenge the substitute bond by making alternative arguments in the parties’ arbitration proceeding?

We answer both issues affirmatively and reverse.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 This case concerns a dispute between two subcontractors who worked on the

Spanish Peaks Lodge construction project near Big Sky, Montana. In 2019, Suffolk

Construction, the general contractor for the project, subcontracted with Mortensen

Woodwork. Suffolk agreed to pay Mortensen $5.8 million for custom architectural

woodwork to go inside the Lodge. Mortensen, in turn, subcontracted with Skyline

Consulting to install its custom woodwork.

¶3 By the fall of 2021, Skyline alleged that Mortensen owed it nearly $600,000 for

unpaid labor and materials. Mortensen disagreed, contending that Skyline had abandoned

the installation work. To ensure its payment, Skyline filed a construction lien against the

2 Spanish Peaks Lodge property with the intent to pursue foreclosure. In the lien, Skyline

named the owner of the Lodge—SP Hotel Owner.

¶4 To keep the Lodge’s title clear of liens, both Suffolk’s contract with SP Hotel Owner

and Mortensen’s contract with Suffolk required Suffolk and Mortensen to remove any liens

filed by subcontractors against the project. Suffolk accordingly directed Mortensen to

“bond around” Skyline’s lien. Mortensen secured a bond from a surety company for 150%

of the amount Skyline claimed and petitioned the District Court to substitute the bond for

the lien. The District Court did so, freeing up the Lodge’s title.

¶5 Two days after the District Court’s substitution, Skyline filed an answer to

Mortensen in their separate arbitration proceeding. In its arbitration filing, Skyline asserted

that Mortensen “‘improperly filed a petition to substitute a bond for the construction lien”

and “inaccurately represented to the court that it was a ‘contracting owner.’” Skyline

requested to join SP Hotel Owner to the arbitration proceeding, especially “in the event

[Mortensen’s] bond substitution is declared invalid.” Skyline also requested to join Intact

Insurance, the surety that had issued Mortensen’s bond, “which purports to be serve [sic]

as substitution for [Skyline’s] construction lien.”

¶6 A week later, Skyline asked the District Court to reinstate its lien, arguing that

Mortensen, a subcontractor, was not authorized to substitute a bond because Montana’s

construction lien laws allow only a “contracting owner” to do so. The District Court denied

Skyline’s request in a one-paragraph decision, concluding that Mortensen had “acted at the

direction and as the agent of the Owner” and thus could substitute a bond for Skyline’s

lien.

3 STANDARDS OF REVIEW

¶7 The interpretation of a statute is a matter of law, which we review de novo. dck

Worldwide Holdings v. CH SP Acquisition LLC, 2015 MT 225, ¶ 15, 380 Mont. 215,

355 P.3d 724. We review for correctness a district court’s legal conclusion about whether

a party has waived a right. VanDyke Constr. Co. v. Stillwater Mining Co., 2003 MT 279,

¶ 11, 317 Mont. 519, 78 P.3d 844.

DISCUSSION

¶8 1. Did the District Court err in concluding that Mortensen Woodwork, a subcontractor, could file a substitute bond when Montana law authorizes only a “contracting owner” to do so?

¶9 Skyline argues that Mortensen was not permitted to file a bond in substitution for

Skyline’s construction lien because Mortensen was not a contracting owner. Mortensen

responds that its substitute bond is valid because it filed the bond on behalf of and at the

direction of the contracting owner.

¶10 Montana law provides that someone who furnishes labor or materials for a

construction project may secure payment by claiming a lien against the property and

pursuing foreclosure. Section 71-3-523, MCA. Once such a lien has been claimed, “the

contracting owner of any interest in the property, whether legal or beneficial,” may file a

bond in substitution for the lien, clearing up the property’s title while the payment dispute

proceeds. Section 71-3-551(1), MCA (emphasis added). The term “contracting owner” is

defined as “a person who owns an interest in real estate and who, personally or through an

agent, enters into an express or implied contract for the improvement of the real estate.”

4 Section 71-3-522(4)(a), MCA. Montana’s construction lien laws list no other party who

may substitute a bond besides a “contracting owner.”

¶11 When considering the meaning of a statute, courts simply must “ascertain and

declare” what is contained in the words of the statute. Section 1-2-101, MCA. We look to

the statute’s plain language, Comm’r of Political Practices for Mont. v. Mont. Republican

Party, 2021 MT 99, ¶ 7, 404 Mont. 80, 485 P.3d 741, and cannot “insert what has been

omitted.” Section 1-2-101, MCA. Additionally, the procedural requirements of

construction lien statutes “will be strictly construed.” Swain v. Battershell, 1999 MT 101,

¶ 26, 294 Mont. 282, 983 P.2d 873.

¶12 The plain language of Montana’s construction lien laws does not authorize general

contractors (like Suffolk) or subcontractors (like Mortensen) to substitute bonds for liens.

Sections 71-3-522, -551(1), MCA. It allows only contracting owners—those who own an

interest in property and enter into a contract for its improvement—to do so.

Montana law is notably different on this point. For example, the model Uniform

Construction Lien Act explicitly authorizes parties other than contracting owners to

substitute bonds for liens. Unif. Constr. Lien Act § 212 (1987) (“A construction lien does

not attach to real estate . . . if the owner or the prime contractor has procured . . . a

bond . . . .”). So do several of our sister states. See, e.g., Alaska Stat. § 34.35.072 (2021)

(“If the owner of the property . . . or a prime contractor or subcontractor disputes the

correctness or validity of the claim of lien . . . the owner or contractor may record . . . a

bond . . . .”); Cal. Civ.

Free access — add to your briefcase to read the full text and ask questions with AI

Skyline Consulting v. Mortensen, 2022 MT 192, 518 P.3d 462 (Mo. 2022).

2022 MT 192 (Skyline Consulting v. Mortensen) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. J. Westfall
2024 MT 99 (Montana Supreme Court, 2024)