Swain v. Battershell

1999 MT 101, 983 P.2d 873, 294 Mont. 282, 56 State Rptr. 424, 1999 Mont. LEXIS 113
CourtMontana Supreme Court
DecidedMay 18, 1999
Docket98-165
StatusPublished
Cited by12 cases

This text of 1999 MT 101 (Swain v. Battershell) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swain v. Battershell, 1999 MT 101, 983 P.2d 873, 294 Mont. 282, 56 State Rptr. 424, 1999 Mont. LEXIS 113 (Mo. 1999).

Opinion

JUSTICE HUNT

delivered the Opinion of the Court.

¶1 On December 27,1995, Appellant Ken Swain d/b/a Montana Concrete Finishing (Swain) filed a lawsuit against Respondents Thomas M. Battershell (Battershell) and Battershell Properties, Inc. (BPI) to execute a construction lien foreclosure and to recover damages for breach of contract, promissory estoppel, and breach of the covenant of good faith and fair dealing. On February 21,1996, Battershell and BPI filed their answers. In addition, BPI counterclaimed to recover damages for breach of contract, promissory estoppel, breach of the covenant of good faith and fair dealing, and fraud.

¶2 On November 12, 1996, Battershell filed a motion for partial summary judgment on Count I, concerning the construction lien foreclosure, on the ground that the construction lien was invalid and unenforceable as a matter of law. On February 7,1997, the First Judicial District Court, Lewis and Clark County, issued an order granting *284 Battershell’s partial summary judgment motion. The remaining counts proceeded to a non-jury trial in July and August of 1997. On December 26,1997, the court issued its findings of fact, conclusions of law, and order concluding that Swain was entitled to judgment in the amount of $2000, but that Battershell was entitled to $2650 in attorney’s fees incurred in defending the construction lien foreclosure part of the lawsuit. The court also concluded that BPI lacked standing to bring a counterclaim against Swain and, therefore, was not entitled to recover any damages pursuant to its counterclaim. The parties appealed to this Court.

¶3 On April 20,1998, Battershell filed with this Court a motion to dismiss Swain’s appeal pursuant to Rule 22, M.R.App.P. Battershell asserted that in January 1997, Swain had filed an amended construction lien naming Cascade Exchange, Inc. (Cascade) as the contracting owner instead of Battershell. Battershell argued that the filing of the amended construction lien rendered moot any appeal concerning the validity of the original construction lien. On April 5,1998, we issued an order denying Battershell’s motion to dismiss without prejudice.

¶4 Swain appeals from the court’s grant of partial summary judgment in favor of Battershell, and the later grant of attorney’s fees to Battershell, concerning the construction lien foreclosure count of the lawsuit. Battershell and BPI cross-appeal from the court’s findings of fact, conclusions of law, and order concerning the remaining counts of the lawsuit. Further, Battershell renews his motion to dismiss Swain’s appeal for mootness. We conclude that Swain’s appeal is not moot and we affirm on each issue.

¶5 Swain presents the following issues for review:

¶6 1. Did the court err in granting Battershell’s partial summary judgment motion on the ground that the construction lien was invalid as a matter of law?

¶7 2. Did the court err in granting Battershell his reasonable attorney’s fees in defending the construction lien foreclosure?

¶8 Battershell presents the following issue for review: Did the court err in finding that the sidewalk was poured in accordance with industry standards and that the lack of uniformity in the finish on the sidewalk was caused by rain?

¶9 BPI presents the following issue for review: Did the court err in concluding that BPI did not have standing to bring a counterclaim because it was not the party with whom Swain had contracted?

*285 FACTS

¶10 BPI is a Montana corporation which owns several property-holdings in and around Helena. Battershell is president of BPI and Jeff Battershell (Jeff), Battershell’s son, is vice-president of BPI. BPI is the record owner of a tract of real property in Helena on which a mini-mall was built. BPI obtained ownership of this property on February 27,1996, pursuant to a “1031 like kind exchange” under the Internal Revenue Code. Prior to this exchange, Cascade owned the mini-mall property. Construction of the mini-mall began in 1995, during Cascade’s ownership of the property. Battershell was the general contractor responsible for overseeing construction of the mini-mall.

¶11 On September 7,1995, Battershell contacted Swain to inquire about Swain’s availability to pour the concrete slab at the mini-mall. He told Swain that the foundation of the mini-mall had already been laid but that the work was progressing slowly. He told Swain he needed the slab to be poured in three days. Swain agreed to meet Battershell at the project site to inspect it. At the project site, Battershell represented to Swain that he owned the mini-mall property. After discussing the project, Swain contracted with Battershell to pour and finish the concrete slab at the mini-mall for $9100, to pour and finish the concrete slab at an adjacent store for $1200, and to pour and finish a concrete sidewalk at the mini-mall for $2000. The parties agreed that the mini-mall sidewalk would have a fine broom finish.

¶12 Swain performed the slab work for the first two jobs in September and received full payment. Swain performed the sidewalk work on October 3 and 5, 1995, but did not receive payment. Battershell was dissatisfied with the quality of workmanship, complaining that the sidewalk did not have a uniform fine broom finish. Battershell refused to pay Swain unless Swain rebuilt the sidewalk. Swain initially told Battershell that he thought he could fix the sidewalk. However, Swain did not return to the project site.

¶13 On November 7, 1995, Swain recorded a construction lien against the mini-mall property, naming Thomas M. Battershell as the contracting owner of the property. Thereafter, Swain filed suit to foreclose on the property and to recover contract damages. Battershell counterclaimed to recover contract damages and filed a motion for partial summary judgment on the issue of the construction lien foreclosure. On February 7,1997, the court granted Battershell’s motion, concluding that because Thomas M. Battershell was not the contracting owner of the mini-mall property, Swain’s construction lien failed *286 to meet the statutory notice requirements and was invalid as a matter of law. The parties’ remaining claims proceeded to a non-jury trial.

¶ 14 At trial, Swain testified that he poured the sidewalk in a workmanlike manner and in accordance with industry standards. He testified that the sidewalk was a commercially acceptable product, and noted that Battershell and the tenants and customers of the mini-mall were using the sidewalk. Swain testified that on the day he began work on the sidewalk, he had finished laying the forms for the sidewalk when he noticed inclement weather approaching. Swain and his crew told Jeff that they would not be able to achieve the fine broom finish requested by Battershell if the sidewalk was poured and finished in the rain. Jeff told Swain that it was imperative that the sidewalk be completed that day because the pavers were waiting to begin the next day and may not be available at another time due to other obligations. Swain testified that Battershell had also told him in a prior conversation that construction of the mini-mall sidewalk must proceed according to a tight schedule. Despite Swain’s advice to the contrary, Jeff instructed Swain and his crew to pour the sidewalk that day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skyline Consulting v. Mortensen
2022 MT 192 (Montana Supreme Court, 2022)
Conservatorship of J.J.W.
2016 MT 339N (Montana Supreme Court, 2016)
Dick Anderson Construction, Inc. v. Monroe Property Co.
2011 MT 138 (Montana Supreme Court, 2011)
Johnston v. Palmer
2007 MT 99 (Montana Supreme Court, 2007)
Bain v. Liberty Mutual Fire Insuran
2005 MT 299N (Montana Supreme Court, 2005)
Simms v. State Compensation Insurance Fund
2005 MT 175 (Montana Supreme Court, 2005)
Earthworks v. Waldher
2002 MT 272N (Montana Supreme Court, 2002)
Burton v. Adams
2002 MT 236N (Montana Supreme Court, 2002)
S.L.H. v. State Compensation Mutual Insurance Fund
2000 MT 362 (Montana Supreme Court, 2000)
Petri v. James Talcott Constructio
2000 MT 355N (Montana Supreme Court, 2000)
Burns v. a Cash Construction Lien Bond
2000 MT 233 (Montana Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
1999 MT 101, 983 P.2d 873, 294 Mont. 282, 56 State Rptr. 424, 1999 Mont. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swain-v-battershell-mont-1999.