Dick Anderson Construction, Inc. v. Monroe Property Co.

2011 MT 138, 255 P.3d 1257, 361 Mont. 30, 2011 Mont. LEXIS 190
CourtMontana Supreme Court
DecidedJune 14, 2011
DocketDA 10-0440
StatusPublished
Cited by22 cases

This text of 2011 MT 138 (Dick Anderson Construction, Inc. v. Monroe Property Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dick Anderson Construction, Inc. v. Monroe Property Co., 2011 MT 138, 255 P.3d 1257, 361 Mont. 30, 2011 Mont. LEXIS 190 (Mo. 2011).

Opinion

CHIEF JUSTICE McGRATH

delivered the Opinion of the Court.

¶1 Dick Anderson Construction (DAC) appeals from the order of the District Court of the Fourth Judicial District granting summary judgment to Monroe Property Company. We reverse.

*31 BACKGROUND

¶2 This case arose over a decade ago when David Lipson, principal of the approximately 10,000-acre Paws Up Angus Ranch and Paws Up Horse Ranch in Missoula County, Montana, engaged DAC to construct buildings, roads and other improvements on the Ranch. Lipson projected that the work would cost approximately $10 million, and when DAC did not get paid for the last approximately $800,000 of billings, it filed a construction lien to secure its claim. DAC commenced a breach of contract and lien foreclosure action in 2001 and has spent the intervening years trying to bring this dispute to a conclusion and to collect the debt.

¶3 David Lipson has been described as a shrewd and experienced businessman. See e.g. Securities and Exchange Comm’n v. Lipson, 278 F.3d 656 (7th Cir. 2002). When Lipson engaged DAC for the Paws Up construction project in April, 2000, he entered a written contract with DAC on behalf of Monroe Construction, a limited liability company formed under the laws of Delaware, with a home address in Chicago. Monroe Construction was a shell entity without any on-going assets, while the Ranch itself was owned by another Lipson entity called Monroe Property, an LLC organized under the laws of Nevada. Lipson controlled both entities and testified that his intent was that Monroe Construction would contract with DAC and pay for the cost of the improvements at the Ranch, using money drawn from various sources within the Lipson organization. Monroe Property owned the Paws Up ranch at all relevant times, and when each phase of the construction was substantially completed, Monroe Construction sold that phase to Monroe Property for cost plus a 5% “contractor’s fee.”

¶4 At the time Lipson entered the construction contract with DAC, there was no written agreement between Monroe Construction and Monroe Property evidencing the arrangement that Monroe Construction would sell the phases of the DAC job as they were completed. In August, 2002, after this litigation was well under way, Monroe Construction and Monroe Property entered a written agreement purporting to memorialize the arrangement. It was “dated as of’ March 9, 2000, and David Lipson signed the document as President of Monroe Property, LLC, and as President of Monroe Construction, LLC and as “manager” of DEL Investments Corporation. Lipson testified that DEL is the manager of Monroe Property; that Monroe Property is a single-member LLC; that the single member of Monroe Property is Monroe Capital Partners, LLC, and that he is the representative of the manager DEL. He also testified that he was not employed by Monroe Property and that neither it nor Monroe *32 Construction has any employees or any ownership interest in the other entity. He testified that Monroe Property operates under the assumed names of Paws Up Angus Ranch, Paws Up Cattle Company and Paws Up Horse Ranch. It is clear that Lipson controlled Monroe Property, Monroe Construction, DEL Investments, and the Paws Up operations.

¶5 Neither Lipson nor the Monroe entities presented any explanation for the necessity or utility of the complicated structure of these entities. Whatever the effect of these intertwined entities may have been, one clear result was to isolate David Lipson, individually, and Monroe Property, as the titleholder of the Paws Up property, from direct contracts with contractors such as DAC. Monroe Construction by design had no discernable assets. They admitted in the District Court proceedings that one of the reasons for the structure was to make it judgment proof and to protect the Paws Up land itself from liens. This has been successful for a decade. Nevertheless, the individual that DAC dealt with throughout its project was David Lipson. Lipson had detailed discussions with DAC’s representative leading up to execution of the construction contract. Lipson signed the contract with DAC on behalf of Monroe Construction, and the contract designated the “project” as “Paws Up Angus Ranch, Greenough, Montana,” the land owned by Monroe Property.

¶6 During the construction phase, DAC personnel dealt with Lipson regularly and often. One of the many proceedings that has been held in the effort to conclude the DAC claim was an arbitration that took place in November, 2005 and which included a nine-day evidentiary hearing. The arbitrators in their written decision found that there were never any complete or detailed plans for the work that DAC was to complete, and that the costs of the project were not detailed cost estimates that DAC could rely on but were just budget estimates provided by Lipson. After DAC began work, its representatives warned Lipson about the increase in the estimated costs caused by the absence of complete plans and the “many changes that were being directed by Lipson.” Lipson and his wife met with DAC representatives weekly to provide directions on what they wanted done, and DAC would direct its crews accordingly. DAC representatives testified that this led to inconsistent and untimely instructions from the Lipsons, and that meeting the Lipsons’ changing expectations resulted in completed work being torn out and reconstructed. The evidence showed that between August, 2000 and March, 2001, Lipson directed 41 changes or additions to the plumbing and 113 pages of changes to the work done on the equestrian center. The arbitration panel found that the “skyrocketing costs” experienced toward the end of the project “were *33 the result of the changes and expansions directed by Dave Lipson.”

¶7 Monroe Construction paid DAC through the April 30, 2001 invoice, a total of $10,339,223. Monroe did not pay DAC’s June and July, 2001 invoices, which totaled $894,607. In July, 2001 DAC filed a construction lien against the property and in September, 2001 DAC sued Monroe Construction for breach of contract and Monroe Property to foreclose the lien. The Monroe entities responded with several counterclaims for constructive fraud, misrepresentation, negligence and breach of contract.

¶8 In 2002, the District Court denied Monroe’s motion for summary judgment and upheld the validity of DAC’s construction lien. In May, 2004, the District Court upheld the validity of the lien against further Monroe contentions that it was technically deficient. The District Court also dismissed all of Monroe’s tort-based counterclaims, leaving only the breach of contract counterclaim by Monroe Construction. These rulings have not been appealed.

¶9 The Monroe entities then moved to compel arbitration under the construction contract, and in March, 2005 the District Court ordered that the parties participate in arbitration. The arbitration proceeded with DAC and Monroe Construction only and included the nine-day evidentiary hearing, the only one held in any proceeding connected with this matter. In December, 2005 the arbitrators awarded DAC $802,661 in damages; $309,729 in interest; $33,186 in costs and $331,892 in attorney fees against Monroe Construction. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Netzer v. State
2025 MT 249 (Montana Supreme Court, 2025)
Guardian Tax v. Tasey
2025 MT 158 (Montana Supreme Court, 2025)
Myers v. Kleinhans
2024 MT 208 (Montana Supreme Court, 2024)
Cordero v. MT State Uni.
2024 MT 167 (Montana Supreme Court, 2024)
Missoula County v. DOC
2024 MT 98 (Montana Supreme Court, 2024)
Gerber v. Davalos
2024 MT 91N (Montana Supreme Court, 2024)
Stand Up Montana v. Msla Co. Schools
2023 MT 240 (Montana Supreme Court, 2023)
Whitefish 57 v. City
2023 MT 176 (Montana Supreme Court, 2023)
Kageco v. DOT
2023 MT 71 (Montana Supreme Court, 2023)
Kipfinger v. G.F. Obstetrical
2023 MT 44 (Montana Supreme Court, 2023)
Drescher v. Malee
2022 MT 200 (Montana Supreme Court, 2022)
Kostelecky v. Peas in a Pod
2022 MT 195 (Montana Supreme Court, 2022)
Skyline Consulting v. Mortensen
2022 MT 192 (Montana Supreme Court, 2022)
Timpano v. Central MT HRDC
2022 MT 169 (Montana Supreme Court, 2022)
Davidson v. Barstad
2019 MT 48 (Montana Supreme Court, 2019)
Big Sky Civil & Envtl., Inc. v. Dunlavy
2018 MT 236 (Montana Supreme Court, 2018)
Ash v. Merlette
2017 MT 305 (Montana Supreme Court, 2017)
Davis v. Westphal
2017 MT 276 (Montana Supreme Court, 2017)
Pilgeram v. Greenpoint Mortgage Funding, Inc.
2013 MT 354 (Montana Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2011 MT 138, 255 P.3d 1257, 361 Mont. 30, 2011 Mont. LEXIS 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dick-anderson-construction-inc-v-monroe-property-co-mont-2011.