Dck Worldwide Holdings Inc. v. CH SP Acquisition LLC

2015 MT 225, 355 P.3d 724, 380 Mont. 215, 2015 Mont. LEXIS 398
CourtMontana Supreme Court
DecidedAugust 4, 2015
DocketDA 14-0602
StatusPublished
Cited by4 cases

This text of 2015 MT 225 (Dck Worldwide Holdings Inc. v. CH SP Acquisition LLC) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dck Worldwide Holdings Inc. v. CH SP Acquisition LLC, 2015 MT 225, 355 P.3d 724, 380 Mont. 215, 2015 Mont. LEXIS 398 (Mo. 2015).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 CH SP Acquisition LLC (CHSP) appeals from an order entered by the Eighteenth Judicial District Court, Gallatin County, granting summary judgment in favor of dck Worldwide Holdings, Inc. (Worldwide). We reverse and remand for entry of summary judgment in favor of CHSP.

¶2 We address the following issues on appeal:

¶3 1. Did the District Court err by concluding that the unpaid portion of the contractor’s fee was lienable as a matter of law?

¶4 2. Did the District Court err by concluding that the subcontractor’s fee was lienable as a matter of law?

FACTUAL AND PROCEDURAL BACKGROUND

¶5 On August 24, 2007, Dick Construction Company (Dick), predecessor in interest to Worldwide, entered into a cost-plus contract with Spanish Peaks Lodge, LLC (Spanish Peaks) to serve as the general contractor for the construction of Spanish Peaks Lodge Resort (Resort) near Big Sky. Pursuant to the contract, Spanish Peaks was to reimburse Dick for the actual costs of construction plus a contractor’s fee of 5% of the total cost of the project and 5% on self-performed work. The parties capped the total price for the Resort at $130,483,926, which resulted in a contractor’s fee of $6,915,195. Under the terms of the contract, Spanish Peaks was to pay the contractor’s fee in installments as the work progressed, and Dick was entitled to the entire fee in the event the contract was terminated, based upon an estimate of the cost of the work that remained to be completed. To bankroll the project, Spanish Peaks procured financing through Citigroup Global Markets Realty Corp. (Citigroup), predecessor in interest to CHSP, and Citigroup took a $130 million mortgage against all of Spanish Peaks’ development properly, including the Resort.

¶6 In the fall of2008, during the economic recession, Spanish Peaks suspended work and ceased making the requisite payments to Dick in breach of the parties’ contract. By that point, Dick had invoiced approximately $21 million to Spanish Peaks in materials and labor and had been paid $1,438,968 of the total $6,915,195 contractor’s fee. Spanish Peaks thus owed Dick the unpaid portion of the contractor’s fee, or $5,476,277, under the terms of the contract. Spanish Peaks *217 thereafter filed for Chapter 7 bankruptcy, and the Resort was never finished.

¶7 Dick filed a construction hen claiming the amount of $10,500,000. Included in the lien was the unpaid portion of the contractor’s fee as well as the amount Dick owed to a subcontractor, Allied Steel, Inc. (Allied Steel), in the amount of $661,767. Allied Steel also filed its own construction hen for unpaid services and materials.

¶8 Allied Steel initiated this action against Spanish Peaks, Dick, and Citigroup seeking foreclosure of its construction hen, a money judgment, and a determination of priority. 1 Dick filed a cross-claim against Citigroup likewise seeking a determination of priority.

¶9 Allied Steel, Spanish Peaks, and Dick entered into a settlement agreement. The agreement provided a lull and final settlement of Allied Steel’s claims against Dick and Spanish Peaks. The agreement provided for Spanish Peaks to pay $500,000 to Dick and for Dick to then pay the $500,000 to AUied Steel. In consideration for the compensation, AUied Steel released and relinquished aU claims against Dick and Spanish Peaks. AUied Steel assigned aU of its claims against Dick and Spanish Peaks to Dick. AUied Steel was then dismissed from the action.

¶10 Thereafter, Worldwide purchased the assets of Dick, including Dick’s hen, at a public auction and CHSP purchased the mortgage. Consequently, Worldwide and CHSP became the real parties in interest to this action.

¶11 On April 24,2013, the District Court issued an order concluding that Worldwide’s construction hen had priority over CHSFs mortgage. However, the court noted “the dollar amount that is the basis of the lien is legitimately in dispute.” The court granted summary judgment with respect to priority, but denied summary judgment with respect to the amount of Worldwide’s hen.

¶12 On November 5, 2013, CHSP and Worldwide reached a partial settlement, memoriaHzed in a second settlement agreement. Under the terms of the second agreement, Worldwide was paid $2.7 milHon, and Worldwide released all claims against CHSP, except for its claims concerning its right to Hen the unpaid contractor’s fee and the amount of AlHed Steel’s subcontractor’s Hen. On those issues, Worldwide and CHSP filed cross-motions for summary judgment. The District Court granted Worldwide’s motion, concluding that the unpaid portion of the *218 contractor’s fee and the subcontractor’s fee were both secured by Worldwide in the amount of $5,476,277 and $661,767, respectively, and lienable as a matter of law. ¶13 CHSP appeals.

STANDARD OF REVIEW

¶14 We review a district court’s ruling on a motion for summary judgment de novo, applying the same criteria of M. R. Civ. P. 56 as the district court. Steichen v. Talcott Props., LLC, 2013 MT 2, ¶ 7, 368 Mont. 169, 292 P.3d 458. Summary judgment is appropriate when “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” M. R. Civ. P. 56(c)(3).

¶15 The district court’s interpretation of a statute is a matter of law, which we review de novo to determine whether the court’s interpretation is correct. State v. Weaver, 2008 MT 86, ¶ 10, 342 Mont. 196, 179 P.3d 534.

DISCUSSION

¶16 1. Did the District Court err by concluding that the unpaid portion of the contractor’s fee was lienable as a matter of law?

¶17 A construction lien, formerly known as a mechanic’s lien, is “ ‘a creature of statute, remedied in nature, with its foundation in equity and natural justice.’ ” Matos v. Rohrer, 203 Mont. 162, 174, 661 P.2d 443, 450 (1983) (quoting Beck v. Hanson, 180 Mont. 82, 87, 589 P.2d 141, 144 (1979)). Under the lien statutes, “it is not the contract for erecting or repairing the building which creates the lien, but it is the use of the materials furnished and the work and labor expended by the contractor ....” Smith v. Gunniss, 115 Mont. 362, 375, 144 P.2d 186, 189 (1944) (citing Van Stone v. Stillwell & Bierce Mfg. Co., 142 U.S. 128, 134, 12 S. Ct. 181, 183); see also Hammer v. Chapin, 256 F. Supp. 818, 819-820 (D. Mont. 1966).

¶18 The statutes governing construction liens are codified in Title 71, chapter 3, part 5 of the Montana Code Annotated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skyline Consulting v. Mortensen
2022 MT 192 (Montana Supreme Court, 2022)
Lucero v. Ford Motor Co.
2019 MT 150 (Montana Supreme Court, 2019)
Tch Bldrs. And Remod. v. Elements Of Const.
2019 MT 71 (Montana Supreme Court, 2019)
Vintage Construction, Inc. v. Feighner
2017 MT 109 (Montana Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2015 MT 225, 355 P.3d 724, 380 Mont. 215, 2015 Mont. LEXIS 398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dck-worldwide-holdings-inc-v-ch-sp-acquisition-llc-mont-2015.