Bauer v. Cook

596 P.2d 200, 182 Mont. 221, 1979 Mont. LEXIS 825
CourtMontana Supreme Court
DecidedJune 13, 1979
Docket13889
StatusPublished
Cited by12 cases

This text of 596 P.2d 200 (Bauer v. Cook) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bauer v. Cook, 596 P.2d 200, 182 Mont. 221, 1979 Mont. LEXIS 825 (Mo. 1979).

Opinion

MR. JUSTICE SHEEHY

delivered the opinion of the Court.

This is an appeal from a judgment of the District Court, Missoula county, foreclosing a mechanic’s lien on a dwelling house and directing defendants to pay the lienholder’s costs and attorney fees.

In January 1975, James and Dieta Maria Cook contacted Blaisus J. Bauer, Jr., a building contractor, for the purpose of discussing the construction of a dwelling- house on property located in Missoula County, Montana. Bauer, who had been in the construction business since 1971 and had built approximately thirty houses in that time, agreed to build the home. On February 19, 1975, the parties entered into a contract whereby Bauer agreed that the proposed house would be “turn-key” complete within ninety days after commencement of work. The Cooks agreed to pay Bauer in the following manner:

“A. 20% of cost upon completion of floor.
“B. 20% of cost upon completion of framing, roofing and exterior windows & doors.
“C. 20% of cost upon completion of rough wiring, plumbing & heating.
“D. 20% of cost upon completion of sheet rock and texturing.
“E. 20% of cost upon completion ...”

The contract plans and specifications were presented to the Western Federal Savings and Loan Association of Missoula, Montana, for aprpoval of a loan to finance the construction. The loan was approved and an account opened whereby the funds were to be disbursed in accordance with the contract and Western Federal’s disbursement instructions, which required that all disbursement requests be approved and signed by the Cooks and a loan officer.

Bauer began construction immediately. Upon completion of the floor, a building inspector for Western Federal inspected the work and approved a disbursement of $8,301.33 to Bauer. The Cooks also approved the disbursement. Upon completion of the framing, *224 roofing, and exterior windows and doors, a similar procedure took place. Then, on April 1, 1975, after the building inspector had inspected the rough wiring, plumbing, and heating, and approved the disbursement, Dieta Cook refused to sign the disbursement request. Mrs. Cook refused to give her signature because she felt Bauer had not performed his part of the contract. A handwritten “Statement of Understanding” was given to Bauer by the Cooks, demanding that thirty-one items be completed before the disbursement request would be signed. Bauer explained to the Cooks that he could not continue construction without the funds, but Mrs. Cook refused to change her position.

On April 4, 1975, Bauer ceased work and did not return to the construction site. Thereafter, four days later, he filed and perfected a mechanic’s lien in the office of the Clerk and Recorder, Missoula County, under the provisions of section 45-501, et seq., R.C.M.1947, now section 71-3-501, et seq. MCA. Bauer claimed the Cooks owed him $8,300 for labor and materials. This amount was reduced to $3,000 after the Cooks paid $5,300 to various materialmen.

A suit to foreclose on the lien was filed April 22, 1975. Trial was commenced without a jury, in District Court, Missoula County on April 19, 1976. Three days later, due to calendar restrictions, the District Court ordered that the trial would be continued indefinitely. On December 9, 1976, the parties'agreed to submit the case to the court without further testimony. The District Court entered findings of fact, conclusions of law and judgment of foreclosure on March 24, 1977. Bauer was awarded $3,000 as foreclosure of the mechanic’s lien and $1,000 as reasonable attorney fees.

On appeal, the Cooks have raised two issues:

1. Did Bauer abandon the project for which he had contracted, thereby rendering his filing of the mechanic’s lien improper?
2. Did the District Court err in failing to reduce Bauer’s recovery under the lien due to his defective performance of the contract?

The general rule in Montana is that a mechanic’s lien arises *225 only upon completion (or substantial completion) of the contracted work. Western Plumbing of Bozeman v. Garrison (1976), 171 Mont. 85, 556 P.2d 520. However, the general rule does not apply if the laborer or materialman has been prevented from completing the work by the breach of the owner or a third party. Intermountain Electric, Inc. v. Berndt (1974), 164 Mont. 67, 518 P.2d 1168.

In the case on appeal the alleged breach occurred when the Cooks refused to sign the disbursement request which had been presented to them by Bauer. The Cooks contend (1) under the circumstances, their refusal to sign did not constitute a breach of contract, and (2) if they did breach the contract, Bauer was nonetheless unjustified in abandoning the contract.

In Gramm v. Insurance Unlimited (1963), 141 Mont. 456, 378, P.2d 662, we said:

“The rule is stated in Corbin on Contracts, § 946, as follows:
“ ‘The non-payment of an installment of money when due will always create a right of action for that money, but it will not always be a total breach.’
“Thus, it depends upon the particular facts of each case whether or not nonpayment of an installment is a total breach enabling the contractor to cease work, or whether it is merely a partial breach entitling the contractor to sue for the partial breach, but not permitting him to abandon the contract.”

The District Court concluded that Bauer completed the rough wiring, plumbing and heating on or about April 1, 1975, and that the building inspector examined the work and approved the disbursement of $8,300 to Bauer, but Dieta Cook refused to sign the disbursement request.

In reviewing findings of fact in a civil action tried by the District Court without a jury, this Court is confined to determining whether there is substantial credible evidence to support those findings. Hornung v. Estate of Lagerquist (1970), 155 Mont. 412, 473 P.2d 541. Although conflicts may exist in the evidence presented, it is the duty and function of the trial judge to resolve such conflicts. His findings will not be disturbed on appeal where they are based *226 on substantial though conflicting evidence. Fausett v. Blanchard (1969), 154 Mont. 301, 463, P.2d 319. Finally, in determining whether the trial court’s findings are supported by substantial evidence this Court must view the evidence in the light most favorable to the prevailing party. Hellickson v. Barrett Mobile Home Transport, Inc. (1973), 161 Mont. 455, 507 P.2d 523.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gwynn v. Cummins
2006 MT 239 (Montana Supreme Court, 2006)
Caplis v. Caplis
2004 MT 145 (Montana Supreme Court, 2004)
In Re the Marriage of Moss
1999 MT 62 (Montana Supreme Court, 1999)
St. John v. Missoula Electric Cooperative, Inc.
938 P.2d 586 (Montana Supreme Court, 1997)
Durand v. Dowdall
757 P.2d 1302 (Montana Supreme Court, 1988)
Graham v. Mack
Montana Supreme Court, 1984
Thomas v. Barnum
684 P.2d 1106 (Montana Supreme Court, 1984)
Matos v. Rohrer
661 P.2d 443 (Montana Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
596 P.2d 200, 182 Mont. 221, 1979 Mont. LEXIS 825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bauer-v-cook-mont-1979.