Gwynn v. Cummins

2006 MT 239, 144 P.3d 82, 333 Mont. 522, 2006 Mont. LEXIS 462
CourtMontana Supreme Court
DecidedSeptember 26, 2006
Docket05-557
StatusPublished
Cited by2 cases

This text of 2006 MT 239 (Gwynn v. Cummins) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gwynn v. Cummins, 2006 MT 239, 144 P.3d 82, 333 Mont. 522, 2006 Mont. LEXIS 462 (Mo. 2006).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 David Gwynn (Gwynn) appeals from a summary judgment order entered for Douglas and Kim Cummins (the Cumminses) by the Fourth Judicial District Court, Missoula County. We reverse and remand.

¶2 We consider the following issue on appeal:

¶3 Whether the District Court properly granted summary judgment for the Cumminses.

BACKGROUND

¶4 In May 2004, the Cumminses obtained a bid proposal from Philip “Po” Hemry (Hemry), of Hemry Construction, to prepare their land and construct a concrete foundation for placement of their new modular home. The total bid for the construction project was $9,200, including *524 the excavation work, which Hemry itemized in the bid at $2,000. In June 2004, Hemry hired Gwynn as a subcontractor to perform the excavation work on the Cumminses’ property. Hemry told Gwynn that the contract work would be limited to excavation for a foundation with three-foot walls and backfill once the foundation was laid. The only portion of the proposal referencing the subcontract provided: “[d]ig out and bacfill [sic] with machine grade ($2000.00).”

¶5 What thereafter occurred between the parties is disputed, and, on review of the entry of summary judgment, we look to the parties’ factual assertions, which are set forth as follows. Gwynn alleges that he and his assistant, Wayne Nelson (Nelson), agreed to dig a hole for the foundation of the Cumminses’ home, and after Hemry installed the foundation, to backfill the hole and machine grade the surface around the foundation. However, when they arrived at the site on July 3, 2004, Gwynn and Nelson discovered that there was a 14’ x 70’ x 4” concrete pad on the site that had to be removed, and, further, the Cumminses advised them that the foundation walls would need to be four feet high instead of three feet. Gwynn informed the Cumminses that the $2,000 bid did not include the removal of the concrete pad and extra one foot of excavation. The Cumminses agreed to pay an additional $400 for removal of the concrete pad and for burial of the demolished portions on the work site. Gwynn informed them of the additional cost for excavating and backfilling the four-foot foundation wall (an additional eighty-eight cubic yards of fill), and the Cumminses told him to proceed. Gwynn demolished the concrete pad and laid the broken concrete at a place the Cumminses specified, to be covered later by over dig materials.

¶6 The Cumminses requested that Gwynn and Nelson use excavated backfill to construct a roadway to the lower portion of their property. Gwynn notified the Cumminses that he would charge an additional amount for hauling the fill and spreading it out. At the Cumminses’ direction, Gwynn and Nelson laid out the roadway, using approximately twenty-four cubic yards of fill material, and taking an additional four and half hours of time.

¶7 On July 5, 2004, Gwynn finished excavating the pit for the four-foot foundation. Gwynn claims that the Cumminses then changed their mind about burying the demolished concrete pad on site, and asked Gwynn to haul the concrete pieces away rather than bury them. Gwynn apprised the Cumminses of the additional fees for loading, hauling, and dumping these materials off site, and the Cumminses assured Gwynn that they would pay him for the additional work. On *525 July 24, 2004, they asked Gwynn to remove a mound of earth located fifteen feet away from the foundation, which Gwynn did. The Cumminses then requested Gwynn to compact the clay dirt surrounding the excavated foundation pit, which took him several more hours to complete. The Cumminses then asked Gwynn to dig a 10’ x 2’ x 2’ ditch to connect the foundation with the site of the septic tank, and, following Gwynn’s completion of the trench, asked him to dig up and fix a leaking septic line that connected the septic tank to its drain field, which Gwynn also completed.

¶8 On July 25,2004, his fourth day on site, Gwynn began backfilling the four-foot foundation hole, and finished it the next day. On July 26, 2004, Gwynn, his wife Diana Gwynn (Diana), and Nelson hauled out three loads of the demolished concrete pad. After Diana and Nelson left the site, Gwynn claims the Cumminses approached him and informed him that he would only be paid $180 for the extra work they had ordered. Gwynn replied that that was not what they had agreed to, and alleges that Doug Cummins retorted, “[t]o hell with you, I ain’t paying you nothing,” then turned around, ran, and drove away. After Gwynn related the conversation to Diana and Nelson, the three stopped working, took some photographs of the site, and proceeded to pack up their equipment. Hemry finished the excavation work.

¶9 On July 29, 2004, Hemry billed the Cumminses for $9,200, corresponding to Hemry’s original bid. The Cumminses paid the bill, and Hemry issued them a “Receipt and Waiver of Construction Lien” on August 12,2004, indicating that he had received payment and that the contract was paid in full. The invoice Hemry produced evidenced a contract between Hemry and the Cumminses, along with Gwynn’s status as a subcontractor. After the Cumminses paid Hemry, he attempted to pay Gwynn $2,000 for his subcontract work. Gwynn refused this payment, and Hemry sent the Cumminses the returned $2,000. The Cumminses then tried to pay this amount to Gwynn themselves, but Diana refused payment, as acceptance would involve signing a lien release, and informed the Cumminses that the bid was not for $2,000. Hemry alleges that Gwynn did not actually finish the work he claims to have performed, and in fact all the work was part of the original excavation bid of $2,000.

¶10 On August 23, 2004, Gwynn filed a construction lien on the Cumminses’ residence to secure payment for his services. Gwynn filed the lien without sending prior notice to the Cumminses. On January 21,2005, Gwynn filed an action in the District Court to foreclose upon the lien. Gwynn served the Cumminses with the complaint on *526 February 4, 2005. Gwynn contended that the proposal and invoice did not make any provision for the extra services he provided, including road building, septic trench digging and repair, demolition, and hauling materials off-site. Gwynn provided an itemized bill for his services, and claimed that the Cumminses owed him a total of $4,305. The Cumminses claimed that the additional work they requested was but a part of the “plethora of other services that were supposed to be part of the original excavation contract.” On February 17, 2005, the Cumminses filed an offer of judgment for $2,000. On February 25, 2005, the Cumminses moved to dismiss the complaint on the grounds that (1) Gwynn was required to file notice of a right to claim a lien because he was performing services as a subcontractor to Hemry; and (2) Gwynn had not completed his work, and therefore, he was not entitled to claim a lien. On March 8, 2005, the Cumminses filed a second offer of judgment for $2,500. The parties waived oral arguments. On April 27, 2005, the District Court granted summary judgment in favor of the Cumminses, concluding that the construction lien was invalid because there were no genuine issues of material fact that Gwynn (1) had not substantially completed the work, and (2) that the subcontract covered all the services Gwynn provided, and thus an exception to the notice requirement did not apply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Elliot
2022 MT 91N (Montana Supreme Court, 2022)
Vintage Construction, Inc. v. Feighner
2017 MT 109 (Montana Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2006 MT 239, 144 P.3d 82, 333 Mont. 522, 2006 Mont. LEXIS 462, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gwynn-v-cummins-mont-2006.