Hagfeldt v. Mahaffey

575 P.2d 915, 176 Mont. 16, 1978 Mont. LEXIS 756
CourtMontana Supreme Court
DecidedMarch 1, 1978
Docket13910
StatusPublished
Cited by6 cases

This text of 575 P.2d 915 (Hagfeldt v. Mahaffey) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hagfeldt v. Mahaffey, 575 P.2d 915, 176 Mont. 16, 1978 Mont. LEXIS 756 (Mo. 1978).

Opinion

BERNARD W. THOMAS, District Judge,

sitting in place of Chief Justice Hatfield, delivered the opinion of the Court.

Plaintiff obtained judgment in District Court, Cascade County, for the recovery of money claimed to be due for the delivery of gravel and certain machine work, and for the foreclosure of a mechanic’s and materialman’s lien. Defendant appeals.

In the District Court this action and a prior one filed by Boyd C. Mahaffey and Nancy Mahaffey, defendants in this case against Curtis Hagfeldt, plaintiff, for removal of the lien and to recover damages for its filing, were consolidated for trial. At the trial only Hagfeldt’s claim was heard and the action brought by Mahaffeys is not involved in this appeal.

Defendants Gilbert D. Wells and Herbert M. Sherberne were joined as parties to this action because at the time of the events in question they were vendors of the land here involved under a contract for sale to Mahaffeys as purchasers. The contract was paid off during the pendency of this action so Wells and Sherberne are not affected by the judgment and should be dismissed as parties.

The District Court made general findings of fact that commencing on May 30, 1974, and ending on June 14, 1974, plaintiff, at the special instance and request of Mahaffeys, delivered certain labor and materials to them, as follows:

76 loads of gravel @ $30.00 per load.............$2,280.00

7 hours of loader work @ $25.00 per hr.......... 175.00

Total due...................$2,455.00

That defendants paid the sum of.................(1,000.00)

Leaving a balance due of......................$1,455.00

The District Court further found that the labor and materials were used on certain real property owned by defendants; concluded the lien was valid and subject to foreclosure, and entered judgment in accordance with its findings and conclusions.

*18 The only issue presented on appeal is the sufficienty of the evidence to support the findings, conclusions and judgment.

On the appeal of equity cases, this Court shall review all questions of fact arising upon the evidence presented in the record and determine the same. Section 93-216, R.C.M. 1947. If the evidence is not conflicting or if it preponderates decidedly against the findings of the trial court, this Court may make its own conclusions, but where there is substantial evidence to support the trial court, even though the evidence is conflicting, this Court will not disturb the findings. The credibility of witnesses and weight to be given their testimony is a matter for the trial court’s determination. The evidence must be viewed in the light most favorable to the prevailing party in the District Court. Johnson v. Johnson, (1977), 172 Mont. 94, 560 P.2d 1331; Keller v. Martin, Jr., 153 Mont. 9, 452 P.2d 422; State ex rel Nagle v. Naughton, 103 Mont. 306, 63 P.2d 123.

The transactions between the parties were conducted orally and occurred in the late spring and summer, 1974. The trial took place on February 10, 1977. By then time had taken its usual toll on the memory of the participants, resulting in uncertainty and confusion as to dates and details, and leaving the evidence unsatisfactory in some respects.

A review of the record shows that the parties are in substantial agreement on the following facts: Prior to May 30, 1974, plaintiff and Boyd C. Mahaffey held one or more discussions relative to plaintiff supplying defendant with a quantity of gravel to be delivered to a tract of land on which defendant planned to erect a shop building. These discussions culminated in an order by defendant for 10 loads of gravel at a price of $30 a load. Plaintiff owned a truck and he enlisted the aid of Gene Shumaker who also owned a truck and who had a lease on a gravel pit. Ten loads of gravel were delivered by plaintiff and Shumaker on May 30, and on that date defendant paid plaintiff for those 10 loads by a $300 check. Shortly thereafter, defendant ordered a second 10 loads which were delivered by plaintiff and paid for by defendant’s check in the *19 amount of $300 dated June 7, 1974. At or about the time the second order was delivered the parties had a discussion about delivery of further gravel and use of a loader, following which plaintiff did deliver more gravel to defendant’s land and did some work there with a loader. On July 7, 1974, plaintiff received a payment of $200 by a check given to him by Nancy Mahaffey, and at that time plaintiff gave Mrs. Mahaffey a statement showing delivery of 72 loads of gravel at $30, for a total of $2,160; 3A hours building an approach at $28, or $98; grand total of $2,258, less credit for $800, balance due, $1,458. On August 16, 1974, defendant paid another $200 by check. Since then he has refused to pay more.

Defendant in his brief argues that the dispute is not about the amount of gravel delivered, but rather over how the gravel was to be measured and what defendant agreed to pay; that, while plaintiff maintains he delivered 76 ten-yard loads or 760 yards of gravel at $3.00 per yard, defendant claims that there were 26 to 30 loads at $30 per load. From this, it appears that defendant concedes that around 760 yards of gravel were deliverd, but argues that delivery was made in 26 to 30 loads instead of the 76 loads as claimed by plaintiff. This would mean that the loads would have to average 25 yards or more each. There is substantial evidence against such a contention. Plaintiff’s evidence shows that the two trucks used by him had capacities of 13.4 yards and 14 yards respectively; that each load delivered contained a good 10 yards, which was also the customary load size in the trade, and that the price was $3.00 per yard or $30 for a ten-yard load, which was the way defendant was billed by plaintiff.

As stated above, there is no disagreement about the first two orders which resulted in the delivery of the first 20 loads. Nor is it disputed that there was a third agreement for the delivery of more gravel. The difficulty arises on the terms of the third agreement. Defendant insists that he ordered only another 10 loads of gravel, plus some work with the loader. (No issue is urged relative to the loader work.) Plaintiff maintains that he was authorized to deliver sufficient gravel to finish the project defendant had in mind; that *20 is, enough gravel to complete the driveway and to provide a base for the footings, foundation and slab floor of the shop building defendant planned to erect. Since the evidence on this issue is conflicting, we must determine whether the record contains substantial evidence to support the court’s findings for plaintiff on this point.

The testimony submitted in behalf of plaintiff shows the following: At the first meeting of the parties defendant told plaintiff that he wanted to build a shop and needed gravel for a driveway. Defendant wanted to hold delivery of gravel down to 10 loads or 100 yards a week because he could not afford to pay more than $300 a week.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milanovich v. Janicich
2001 MT 65N (Montana Supreme Court, 2001)
United States v. Bretz
902 F.2d 41 (Ninth Circuit, 1990)
Matos v. Rohrer
661 P.2d 443 (Montana Supreme Court, 1983)
Steinmetz v. Robertus
637 P.2d 31 (Montana Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
575 P.2d 915, 176 Mont. 16, 1978 Mont. LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hagfeldt-v-mahaffey-mont-1978.