Haines Pipeline Construction, Inc. v. Montana Power Co.

830 P.2d 1230, 251 Mont. 422, 48 State Rptr. 1102, 1991 Mont. LEXIS 316
CourtMontana Supreme Court
DecidedDecember 16, 1991
Docket90-281
StatusPublished
Cited by23 cases

This text of 830 P.2d 1230 (Haines Pipeline Construction, Inc. v. Montana Power Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haines Pipeline Construction, Inc. v. Montana Power Co., 830 P.2d 1230, 251 Mont. 422, 48 State Rptr. 1102, 1991 Mont. LEXIS 316 (Mo. 1991).

Opinions

JUSTICE McDONOUGH

delivered the Opinion of the Court.

This is an appeal from a bench trial and judgment in the Second Judicial District Court, Silver Bow County. Defendant, Montana Power Company (MPC), appeals the judgment awarding Haines Pipeline Construction, Inc. (Haines), $502,361.26 in compensatory damages and $1,000,000 in punitive damages for MPC’s breach of a construction contract to build a natural gas pipeline. Haines has cross-appealed the portion of the judgment failing to award Haines damages for its lost profits. Regarding the judgment for compensatory damages we affirm in part and reverse in part. As to the punitive damages we reverse and remand, granting the parties leave to amend their pleadings in light of our decision in Story v. City of Bozeman (1990), 242 Mont. 436, 791 P.2d 767. In regards to the cross-appeal, we affirm the District Court’s judgment denying Haines recovery for lost anticipated profits.

MPC raises the following issues on appeal:

[424]*424I. Did the District Court err by admitting into evidence MPC’s internal audit regarding its construction contract with Haines?

II. Did the District Court err in concluding that MPC, rather than Haines, was liable for breach of the construction contract?

III. Did the District Court err in awarding Haines compensatory damages including $16,000 in travel expenses and $50,000 in unspecified general damages?

IV. Did the District Court err in awarding punitive damages for breach of the implied covenant of good faith and fair dealing?

Haines raises the following issue on cross-appeal:

V. Did the District Court err in failing to award Haines damages for its lost profits?

On June 16,1983, Haines as contractor and MPC as owner, entered into a written contract for the construction of the southern half of a 16 inch natural gas pipeline from Warm Springs to Cut Bank, Montana. Walter Kelley, MPC’s chief operating officer and a director, was MPC’s agent responsible for administration of the contract.

In lieu of a construction bond, the parties required Haines to post an irrevocable letter of credit for $750,000 in favor of MPC, and to maintain such letter of credit until final acceptance and payment of the work under the contract. The terms for drawing on the letter of credit were as follows:

‘We hereby certify that Haines Pipeline Construction, Inc. has failed to comply fully with the terms of our contract, dated June 18, 1983 covering their laying of the 200 mile 16 inch pipeline between Warm Springs and Cutbank. We are therefore entitled to this drawing of$_.”

The original expiration date of the letter of credit was January 15, 1984.

Construction of the pipeline required welding sections of pipe in accordance with procedures developed by MPC and in compliance with federal regulations. MPC entered into a contract with Gamma Sonics (Gamma), to provide X-ray inspection of the welds made by Haines. Welds identified by Gamma as insufficient were immediately marked and repaired by Haines. No welds were buried unless they had been X-ray inspected and approved by Gamma and MPC inspectors.

The project had regulatory problems brought to the attention of the Montana Public Service Commission (PSC) by labor leaders and the Department of Transportation. Hearings were held on several [425]*425alleged federal safety violations, regarding primarily the padding of the bed underneath the pipeline. At the time of the hearings, MPC declined to hold Haines harmless for these violations although Kelley testified that MPC accepted responsibility and paid costs for padding the pipeline. To avoid further hearings MPC developed a “plan to demonstrate fitness for service” of the portion of the pipeline that had been constructed and agreed to postpone further construction.

On April 16, 1984, the letter of credit which was previously extended, was reduced to $250,000 and the expiration date extended again, by agreement of the parties, from July 15,1984, to November 15, 1984. On April 23, 1984, the construction contract having been suspended pursuant to the fitness plan, MPC entered a settlement agreement with Haines covering all work done to that date. As part of that agreement, Haines would release all claims against MPC.

MPC hired Southwest Research Institute (SRI) to re-check the X-ray inspection of Gamma. On May 8, 1984, Haines and MPC entered into a second contract whereby Haines was to assist MPC in doing miscellaneous repair work on the completed portion of pipeline including repair of buried pipeline identified by SRI as defective. Under the contract Haines was paid as an independent contractor on an hourly basis.

On October 15, 1984, MPC Chief Executive Officer, Paul Schmechel, distributed a memorandum in response to the board of directors’ concerns about the pipeline. The memorandum indicated that MPC would “move Haines off the job” by mid-November. Furthermore, the memorandum indicated that the letter of credit was set to expire on November 15 and that the circumstances surrounding repair work were being reviewed to determine if claims should be made against Haines. Lastly, the memo noted that hydrostatic testing of the south half of the pipeline had been completed without failure.

On October 22,1984, Haines as a “good faith gesture” extended the letter of credit until May 15, 1985, at the request of MPC. On November 16, 1984, MPC terminated the June 1983 contract with Haines, pursuant to paragraph 31.0, allowing MPC to terminate at its convenience, and setting forth the amounts which Haines could recover upon such termination. Paragraph 31.0(c)(iii) of the contract specifically stated “the Contractor shall make no claim for lost anticipated profits.” The reason given by MPC for the termination was “severe cash problems.”

MPC conducted an internal audit of the pipeline construction. The audit focused on the shortcomings of MPC’s supervision of Haines [426]*426and Gamma. One of the recommendations of the audit was to proceed against Gamma for the cost of digging up the pipeline and making the necessary repairs. It was later determined that Gamma had insufficient assets to pursue.

In January of 1985, MPC retained a law firm to advise the company if it had a claim against Haines for the cost of fixing defective welds. MPC did not provide the firm with the audit report nor did they make Chief Operating Officer Kelley available to the firm. MPC received an opinion letter from the law firm on May 10, 1985, advising MPC that it could assert both contractual and negligence claims against Haines to recover the costs MPC would incur in repairing defective welds.

Subsequently, MPC attorney, Robert Gannon, recommended to MPC’s vice chairman, Jack Burke, that MPC draw upon the $250,000 letter of credit which was due to expire Wednesday, May 15. Gannon concluded that the costs of repairing the welds would substantially exceed the value of letter of credit. On Tuesday, May 14, Gannon and Burke met with MPC’s CEO, Paul Schmechel, to obtain authority to draw upon the letter of credit.

On May 15, 1985, MPC drew upon the letter of credit after informing Haines that it had failed to perform proper welding under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lewistown Miller Construction Co. v. Martin
2011 MT 325 (Montana Supreme Court, 2011)
Angleton v. Cox
238 P.3d 610 (Alaska Supreme Court, 2010)
Satellite Cable Serv.
1998 SD 67 (South Dakota Supreme Court, 1998)
Porter v. Galarneau
911 P.2d 1143 (Montana Supreme Court, 1996)
Ganz v. United States Cycling Federation
903 P.2d 212 (Montana Supreme Court, 1995)
Schaal v. Flathead Valley Community College
901 P.2d 541 (Montana Supreme Court, 1995)
AgAmerica, FCB v. Robson
901 P.2d 100 (Montana Supreme Court, 1995)
Support Obligation of Day v. State
900 P.2d 296 (Montana Supreme Court, 1995)
In Re the Marriage of Ansell
895 P.2d 619 (Montana Supreme Court, 1995)
Brockie v. Omo Construction, Inc.
887 P.2d 167 (Montana Supreme Court, 1994)
Fox Grain and Cattle Co. v. Maxwell
885 P.2d 432 (Montana Supreme Court, 1994)
Haines Pipeline Construction, Inc. v. Montana Power Co.
876 P.2d 632 (Montana Supreme Court, 1994)
Ihler v. Chisholm
855 P.2d 1009 (Montana Supreme Court, 1993)
In Re MSR Exploration, Ltd.
147 B.R. 560 (D. Montana, 1992)
McNeil v. Currie
830 P.2d 1241 (Montana Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
830 P.2d 1230, 251 Mont. 422, 48 State Rptr. 1102, 1991 Mont. LEXIS 316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haines-pipeline-construction-inc-v-montana-power-co-mont-1991.