Manganaro Corp. v. HITT Contracting, Inc.

193 F. Supp. 2d 88, 2002 U.S. Dist. LEXIS 3206, 2002 WL 314105
CourtDistrict Court, District of Columbia
DecidedJanuary 22, 2002
DocketCivil Action 00-401 (JMF)
StatusPublished
Cited by3 cases

This text of 193 F. Supp. 2d 88 (Manganaro Corp. v. HITT Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manganaro Corp. v. HITT Contracting, Inc., 193 F. Supp. 2d 88, 2002 U.S. Dist. LEXIS 3206, 2002 WL 314105 (D.D.C. 2002).

Opinion

*90 FINDINGS OF FACT, CONCLUSIONS OF LAW, AND MEMORANDUM OPINION

FACCIOLA, United States Magistrate Judge.

Introduction

This case arises out of a contract dispute between plaintiff Manganaro Corporation (“Manganaro”) and defendant HITT Contracting, Inc. (“HITT”). Manganaro, a Maryland corporation, sued HITT, a Virginia corporation, for breach of contract arising out of a construction project for Lu-cent Technologies (“Lucent”). The Lucent project, located at Metropolitan Square, 1450 G Street in Washington, D.C., was to be performed on a fast-track basis. HITT, Lucent’s prime contractor, hired Mangana-ro to perform the drywall and ceiling work on the 4th and 5th floors of Metropolitan Square. Due to the state-of-the-art “brutalized” architectural style, Manganaro was also contracted to install two speciality ceilings: 1) a radians ceiling and 2) a deeoustics ceiling.

On December 23, 1999, after completing all of its work except for the installation of two ceilings and certain “punch list” 1 items, Manganaro notified HITT that it would cease performance on the contract until it was paid for the work previously performed. HITT denied that it failed to make timely payments and claimed that Manganaro abandoned the project. HITT, therefore, terminated Manganaro’s subcontract and hired another subcontractor to finish the work.

In this lawsuit, Manganaro seeks what it claims is due from HITT. HITT seeks, as offsets or counterclaims, the costs incurred as a result of hiring other subcontractors to complete Manganaro’s work and to repair alleged deficiencies in Manganaro’s work.

FINDINGS OF FACT The Contract and its Addenda

1. On July 22, 1999, a contract was entered into by Manganaro and HITT in the base amount of .$393,000.00. The original contract (prior to the addition of the addenda) stated that the “Contractor’s receipt of payment by the owner shall be a condition precedent to the obligation of Contractor to make any payment to the Subcontractor.” Defs. Ex. 0005, ¶ 2A. Thomas Vagrin (‘"Vagrin”), President of Manganaro, insisted, however, that the following be added to the contract: “Notwithstanding the above, it is understood The Contractor has the ultimate obligation to pay the Subcontractor within a reasonable time regardless of payment status from the Owner.” Defs. Ex. 0010, ¶ 2A. HITT agreed to this modification of the original contract.

2. The addendum thus modified the original contract to require payment by HITT to Manganaro within a reasonable time after Manganaro’s requisition for payment was received, eliminating any obligation of Manganaro’s to await HITT’s payment by Lucent before Manganaro was paid by HITT.

3. Vagrin testified that this addendum is typical of Manganaro contracts and is intended to protect Manganaro, typically a subcontractor, from Mangana-ro’s not being paid within a reasonable time of the submission of its invoices to the general contractor.

4. Vagrin further testified that the addendum does not make a distinction between payments for “contract work” and payments for “change order” work. 2

*91 5. Yogen Patel (“Patel”), HITT’s Vice President, conceded on direct examination that it was his understanding that Manganaro was to be paid in a timely fashion even if HITT had not yet received payment from Lucent.

The Dispute and the Termination

6. The work Manganaro invoiced consisted of two elements. The first, the “contract work,” was work Manganaro was compelled to perform by the contract as written. Manganaro would bill for whatever percentage of it was completed in that month. The second, the “change order” work, was work that Manganaro had to do in excess of its contractual obligation. See note 2. Manganaro was permitted to seek additional compensation for the change order work.

7. At the midpoint of each month, it was Manganaro’s practice to send invoices seeking compensation for both work done and work Manganaro projected would be completed by the end of that month. The requisition specified: 1) the original contract sum, (2) the net change due to “change orders,” 3) the contract sum to date, 4) the total dollar amount of work completed to date, 5) the total dollar amount to date in earned retainage fees, 6) the total dollar amount to date in payments to Manganaro, and 7) the total dollar amount to date in outstanding payments currently due Manganaro. See e.cj. Defs. Ex. 19028. Manganaro’s monthly requisition also included information detailing the percentages of work completed and remaining to date and the dollar value of both percentages. See e.g. Defs. Ex. 19029.

8. Manganaro’s change order work was subject to a separate and distinct approval process from the contract work. Initially, Manganaro would estimate in writing the cost of the modifications in terms of material and labor and submit a work order, along with supporting documentation, to HITT. If HITT approved the change order work, one of its representatives would sign the work order, and then Manganaro would proceed to do the work.

9. Next, HITT sent the change order work it had approved to the owner, Lucent. Lucent’s approval of the work order, after the work was done, was crucial to Manganaro’s getting paid. HITT’s project accountant, Kitty Siegfried, testified that she could not pay Manganaro’s change work orders until Lucent approved them. According to defendants’ witnesses, Lu-cent was habitually and notoriously late in approving anything HITT submitted. Thus, HITT authorized Man-ganaro to do change order work, Man-ganaro did the change order work, but Manganaro did not get paid for it until Lucent authorized HITT to pay Man-ganaro.

10. To further complicate the matter, when it sent a check to Manganaro, HITT did not send an accompanying explanation of what it was paying. Vincent therefore assumed that the payment was for the contract work and believed that none of the money sent him was for the change order work. Adding to the confusion, Vin *92 cent at times made arithmetical errors in the calculation of the invoice. HITT corrected them but the record does not indicate that HITT advised Vincent of his errors when it sent the check.

11. Manganaro’s first invoices, for July and August, 1999, were paid without problem or exception and Mangana-ro’s work was moving rapidly towards its conclusion. In September, 1999, Manganaro billed HITT for the change orders listed in Chart 1 in the Appendix with an invoice that was submitted to Manganaro by a letter dated September 21, 1999 and that was due by October 21,1999.

12. In October, 1999, HITT paid the two change orders which appear in bold in the chart, but failed to pay for the remaining nine items. This resulted in an outstanding balance of $18,574.18.

18. Even though these change work orders remained unpaid, HITT approved subsequent change orders and Manganaro billed for these by an invoice it submitted on October 14,1999 and due by November 14, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The CUNEO LAW GROUP, PC v. Joseph
669 F. Supp. 2d 99 (District of Columbia, 2009)
Cuneo Law Group, P.C
District of Columbia, 2009

Cite This Page — Counsel Stack

Bluebook (online)
193 F. Supp. 2d 88, 2002 U.S. Dist. LEXIS 3206, 2002 WL 314105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manganaro-corp-v-hitt-contracting-inc-dcd-2002.