Camacho Family Partnership v. Patricia I. Romero, Inc.

CourtDistrict Court, D. Guam
DecidedOctober 17, 2016
Docket1:13-cv-00026
StatusUnknown

This text of Camacho Family Partnership v. Patricia I. Romero, Inc. (Camacho Family Partnership v. Patricia I. Romero, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camacho Family Partnership v. Patricia I. Romero, Inc., (gud 2016).

Opinion

1 IN THE DISTRICT COURT OF GUAM 2 TERRITORY OF GUAM

3 CAMACHO FAMILY PARTNERSHIP d/b/a CIVIL CASE NO. 13-00026 4 “DIRT DOKTOR,” 5 ORDER GRANTING IN PART AND Plaintiff, DENYING IN PART PLAINTIFF’S 6 FIRST MOTION FOR PARTIAL v. SUMMARY JUDGMENT 7 PATRICIAL I. ROMERO, INC., 8 Defendant/Counterclaim Plaintiff, 9 v. 10

11 CAMACHO FAMILY PARTNERSHIP d/b/a “DIRT DOKTOR” and FIRST NET 12 INSURANCE CO.,

13 Counterclaim Co-defendants.

14 15 I. INTRODUCTION 16 Before the court is Plaintiff Camacho Family Partnership’s first Motion for Partial 17 Summary Judgment against Defendant Pacific West Builders (“PWB”) and its surety, Defendant 18 Travelers Casualty and Surety Company (“Travelers”), for past due installment payments. (ECF 19 20 No. 29.) The court took the matter on the briefs and announced its ruling from the bench without 21 oral argument on October 7, 2016. The court now issues its written decision, for the reasons 22 given herein, granting in part, on the claim for retention withheld by PWB in the amount of 23 $42,855.02 covering work performed from December 2012 through February 2013, and denying 24 in part, on the claim for installment payments in the amount of $627,452.31. 25

26 1 II. BACKGROUND 2 A. Procedural History 3 On December 31, 2013, Dirt Doktor filed a complaint alleging breach of contract and 4 requesting (1) an award of $777,550.36 for unpaid work performed by Dirt Doktor and accepted 5 by PWB, (2) an additional award of $221,753.65 as a “reasonable value” of the additional work 6 of “demolishing and redoing the concrete slabs as ordered by PWB,” and (3) for this court to 7 declare that Dirt Doktor is not in default on the subcontract and is entitled to time extensions for 8 its contract performance and monetary compensation as proved at trial. See Compl., ECF No. 1, 9 at 4–5. 10 11 On February 3, 2014, PWB filed an answer and counterclaim. See Ans. & Counterclaim, 12 ECF No. 10. PWB denied all allegations and counterclaimed for breach of contract, asking for 13 damages, interest, and attorneys’ fees. See id. at 10, 18. In the Answer, PWB also alleges a 14 counterclaim against “counter-defendant” First Net Insurance Company. See Ans. at 10. 15 Counterclaim Defendants Dirt Doktor and First Net filed their answer to the counterclaims. See 16 Ans. to Counterclaims, ECF No. 13. 17 On December 10, 2014, Dirt Doktor filed a Miller Act claim against the surety company 18 that bonded with PWB to be jointly and severally liable for the performance of the contract with 19 the Government, Travelers Casualty and Surety Company of America (“Travelers”). See Civil 20 Case No. 14-00021, ECF No. 1. On February 11, 2015, the Magistrate Judge consolidated that 21 case with the present case. See Civil Case No. 14-00021, ECF No. 6. 22 23 On March 19, 2015, Dirt Doktor filed this Motion for Partial Summary Judgment, ECF 24 No. 29, together with a Concise Statement of Material Facts and supporting exhibits and 25 declarations (ECF No. 30). On April 9, 2015, Defendants Patricia Romero and Travelers filed an 26 1 opposition memorandum, together with declarations and exhibits (ECF No. 32). On April 22, 2 2015, Dirt Doktor filed a reply brief (ECF No. 36). 3 On February 25, 2016, Chief Judge Frances Tydingco-Gatewood recused herself from the 4 case, and it was reassigned to the undersigned judge. (ECF No. 64.) 5 B. Factual Background 6 Plaintiff, a resident of Guam, is a partnership and general contractor doing business as 7 Dirt Doktor. (Compl. ¶ 1; Counterclaim ¶ 2; Ans. to Counterclaims ¶ 1.) Defendant Patricia I. 8 Romero, Inc., is a California corporation registered in Guam as a foreign corporation, and at all 9 times material to this lawsuit was doing business as Pacific West Builders (“PWB”). (Compl. ¶ 10 11 2; Ans. ¶ 4.) 12 On or about December 10, 2012, Dirt Doktor signed a contract with PWB to become a 13 subcontractor to PWB’s prime contract with Naval Facilities Marianas (“NAVFAC” or “the 14 Government”) to build the Red Horse Cantonment Operation Facility at Anderson Air Force 15 Base, Guam. (Compl. ¶ 4; Ans. 6.) Dirt Doktor’s scope of work included pouring and installing 16 concrete foundations, roofing, overhangs, sidewalks, and other concrete-related installments. 17 (Declaration of Patricia I. Romero, ECF No. 32-2 ¶ 14; Subcontract Addendum No. 1, ECF No. 18 10, Ex. A; Dirt Doktor’s Ans. ¶ 1.) One of Dirt Doktor’s responsibilities under the subcontract 19 was to pour four concrete slabs on grade for the project’s foundation. (Compl. ¶ 6; Ans. ¶ 8.) 20 As of March 1, 2013, Dirt Doktor had not yet begun the pour of the building foundations. 21 (Romero Decl. ¶ 15; PWB’s Ex. 3, ECF No. 32-6.) On or around March 20, 2013, PWB sent Dirt 22 23 Doktor a 24-hour notice to cure. (Id. ¶ 16; PWB’s Ex. 4, ECF No. 32-7.) On April 12, 2013, 24 PWB sent a follow-up email regarding Dirt Doktor’s unsatisfactory performance. (Id. ¶ 17; 25 PWB’s Ex. 5, ECF No. 32-8.) 26 1 After Dirt Doktor completed the pour, NAVFAC’s contracting officer found the concrete 2 slab to be unsatisfactory, and on June 5, 2013, PWB received a letter of concern from the 3 Government in which it rejected the concrete slab and threatened to assess liquidated damages. 4 (Romero Decl. ¶ 18; PWB’s Ex. 6, ECF No. 32-9.) On or around June 6, 2013, PWB forwarded 5 the letter of concern to Dirt Doktor, and the next day, Dirt Doktor submitted a plan of action to 6 PWB to address the problems. (Id. ¶¶ 19–20; PWB’s Exs. 7-8, ECF Nos. 32-10, -11.) 7 The Government sent second and third letters of concern to PWB on August 2 and 21, 8 2013, again detailing that Dirt Doktor’s work was delayed and unacceptable, and threatening to 9 assess liquidated damages. (Romero Decl. ¶ 21–22; PWB’s Exs. 9-10, ECF Nos. 32-12, -13.) 10 11 PWB wrote to Dirt Doktor on August 21, 2013, informing Dirt Doktor of the Government’s 12 rejection of Dirt Doktor’s concrete slab and its threat to assess liquidated damages, and PWB 13 advised Dirt Doktor and Firstnet Insurance that Dirt Doktor must replace the concrete slab and 14 recover on the schedule. (Id. ¶ 23; PWB’s Ex. 11, ECF No. 32-14.) In this same letter, PWB 15 informed Dirt Doktor that it had disapproved payment of Dirt Doktor’s invoices submitted for 16 the periods ending March 30 ($101,196.32), April 30 ($109,588.68), May 31 ($69,147.98), and 17 June 30 ($135,752.40), totaling $415,685.38, until the floor slab and overall work effort were in 18 compliance with the project schedule. (PWB’s Ex. 11.) At some point during this time period, 19 Dirt Doktor submitted a plan to PWB and the Government in which it proposed to repair the slab 20 instead of removing it. (PWB’s Ex. 11 “You have already submitted a work plan for remediation 21 of the floor slab ….”) On August 23, 2013, the Government sent a letter to PWB describing 22 23 multiple problems with Dirt Doktor’s slab and stating that Dirt Doktor’s proposed plan to repair 24 the slab was unacceptable. (Romero Decl. ¶ 24; PWB’s Ex. 12, ECF No. 32-15.) PWB then 25 notified Dirt Doktor and Firstnet Insurance that the Government had given direction to remove 26 1 and replace the slab. (Id. ¶ 25; PWB’s Ex. 13, ECF No. 32-16.) After learning that the 2 Government rejected the proposed plan, Dirt Doktor notified PWB in writing that it disagreed 3 with the Government’s assessment. (Counterclaim ¶ 12, Dirt Doktor and FirstNet’s Ans. ¶ 1.) 4 On August 27, 2013, PWB informed Dirt Doktor and FirstNet Insurance in writing that 5 the Government had rejected Dirt Doktor’s plan to repair the slab and had given explicit 6 direction to replace the slab. (Romero Decl. ¶ 25; PWB’s Ex. 13, ECF No. 32-16.) In the same 7 letter, PWB demanded that Dirt Doktor begin removing the slab within 48 hours, but also agreed 8 to forward Dirt Doktor’s disagreement to the Government. (Id.) Finally, PWB notified Dirt 9 Doktor that it cannot release any money to Dirt Doktor at the time. (PWB’s Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
In Re Oracle Corp. Securities Litigation
627 F.3d 376 (Ninth Circuit, 2010)
James Arena v. United States
226 F.2d 227 (Ninth Circuit, 1955)
Milenbach v. Commissioner of Internal Revenue
318 F.3d 924 (Ninth Circuit, 2003)
Soremekun v. Thrifty Payless, Inc.
509 F.3d 978 (Ninth Circuit, 2007)
Olympic Chartering SA v. MINISTRY OF IND. AND TRADE OF JORDAN
134 F. Supp. 2d 528 (S.D. New York, 2001)
Manganaro Corp. v. HITT Contracting, Inc.
193 F. Supp. 2d 88 (District of Columbia, 2002)
Schroeder v. McDonald
55 F.3d 454 (Ninth Circuit, 1995)
Van Dusseldorp v. Kim Lean Ho
4 F. Supp. 3d 1069 (S.D. Iowa, 2014)
Farquhar v. Collins
10 Ky. 31 (Court of Appeals of Kentucky, 1820)
Cortez v. City of New York
722 F.3d 483 (Second Circuit, 2013)
Barthelemy v. Air Lines Pilots Ass'n
897 F.2d 999 (Ninth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Camacho Family Partnership v. Patricia I. Romero, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/camacho-family-partnership-v-patricia-i-romero-inc-gud-2016.