Camacho Family Partnership v. Patricia I. Romero, Inc.

District Court, D. Guam·Decided October 17, 2016·No. 1:13-cv-00026·Unknown

Opinion

IN THE DISTRICT COURT OF GUAM

CAMACHO FAMILY PARTNERSHIP d/b/a CIVIL CASE NO. 13-00026 “DIRT DOKTOR,” ORDER GRANTING IN PART AND Plaintiff, DENYING IN PART PLAINTIFF’S FIRST MOTION FOR PARTIAL v. SUMMARY JUDGMENT PATRICIAL I. ROMERO, INC., Defendant/Counterclaim Plaintiff, v.

CAMACHO FAMILY PARTNERSHIP d/b/a “DIRT DOKTOR” and FIRST NET

Counterclaim Co-defendants.

I. INTRODUCTION Before the court is Plaintiff Camacho Family Partnership’s first Motion for Partial Summary Judgment against Defendant Pacific West Builders (“PWB”) and its surety, Defendant Travelers Casualty and Surety Company (“Travelers”), for past due installment payments. (ECF No. 29.) The court took the matter on the briefs and announced its ruling from the bench without oral argument on October 7, 2016. The court now issues its written decision, for the reasons given herein, granting in part, on the claim for retention withheld by PWB in the amount of $42,855.02 covering work performed from December 2012 through February 2013, and denying in part, on the claim for installment payments in the amount of $627,452.31.

A. Procedural History On December 31, 2013, Dirt Doktor filed a complaint alleging breach of contract and requesting (1) an award of $777,550.36 for unpaid work performed by Dirt Doktor and accepted by PWB, (2) an additional award of $221,753.65 as a “reasonable value” of the additional work of “demolishing and redoing the concrete slabs as ordered by PWB,” and (3) for this court to declare that Dirt Doktor is not in default on the subcontract and is entitled to time extensions for its contract performance and monetary compensation as proved at trial. See Compl., ECF No. 1, at 4–5. On February 3, 2014, PWB filed an answer and counterclaim. See Ans. & Counterclaim, ECF No. 10. PWB denied all allegations and counterclaimed for breach of contract, asking for damages, interest, and attorneys’ fees. See id. at 10, 18. In the Answer, PWB also alleges a counterclaim against “counter-defendant” First Net Insurance Company. See Ans. at 10. Counterclaim Defendants Dirt Doktor and First Net filed their answer to the counterclaims. See Ans. to Counterclaims, ECF No. 13. On December 10, 2014, Dirt Doktor filed a Miller Act claim against the surety company that bonded with PWB to be jointly and severally liable for the performance of the contract with the Government, Travelers Casualty and Surety Company of America (“Travelers”). See Civil Case No. 14-00021, ECF No. 1. On February 11, 2015, the Magistrate Judge consolidated that case with the present case. See Civil Case No. 14-00021, ECF No. 6. On March 19, 2015, Dirt Doktor filed this Motion for Partial Summary Judgment, ECF No. 29, together with a Concise Statement of Material Facts and supporting exhibits and declarations (ECF No. 30). On April 9, 2015, Defendants Patricia Romero and Travelers filed an opposition memorandum, together with declarations and exhibits (ECF No. 32). On April 22, 2015, Dirt Doktor filed a reply brief (ECF No. 36). On February 25, 2016, Chief Judge Frances Tydingco-Gatewood recused herself from the case, and it was reassigned to the undersigned judge. (ECF No. 64.) B. Factual Background Plaintiff, a resident of Guam, is a partnership and general contractor doing business as Dirt Doktor. (Compl. ¶ 1; Counterclaim ¶ 2; Ans. to Counterclaims ¶ 1.) Defendant Patricia I. Romero, Inc., is a California corporation registered in Guam as a foreign corporation, and at all times material to this lawsuit was doing business as Pacific West Builders (“PWB”). (Compl. ¶ 2; Ans. ¶ 4.) On or about December 10, 2012, Dirt Doktor signed a contract with PWB to become a subcontractor to PWB’s prime contract with Naval Facilities Marianas (“NAVFAC” or “the Government”) to build the Red Horse Cantonment Operation Facility at Anderson Air Force Base, Guam. (Compl. ¶ 4; Ans. 6.) Dirt Doktor’s scope of work included pouring and installing concrete foundations, roofing, overhangs, sidewalks, and other concrete-related installments. (Declaration of Patricia I. Romero, ECF No. 32-2 ¶ 14; Subcontract Addendum No. 1, ECF No. 10, Ex. A; Dirt Doktor’s Ans. ¶ 1.) One of Dirt Doktor’s responsibilities under the subcontract was to pour four concrete slabs on grade for the project’s foundation. (Compl. ¶ 6; Ans. ¶ 8.) As of March 1, 2013, Dirt Doktor had not yet begun the pour of the building foundations. (Romero Decl. ¶ 15; PWB’s Ex. 3, ECF No. 32-6.) On or around March 20, 2013, PWB sent Dirt Doktor a 24-hour notice to cure. (Id. ¶ 16; PWB’s Ex. 4, ECF No. 32-7.) On April 12, 2013, PWB sent a follow-up email regarding Dirt Doktor’s unsatisfactory performance. (Id. ¶ 17; PWB’s Ex. 5, ECF No. 32-8.) After Dirt Doktor completed the pour, NAVFAC’s contracting officer found the concrete slab to be unsatisfactory, and on June 5, 2013, PWB received a letter of concern from the Government in which it rejected the concrete slab and threatened to assess liquidated damages. (Romero Decl. ¶ 18; PWB’s Ex. 6, ECF No. 32-9.) On or around June 6, 2013, PWB forwarded the letter of concern to Dirt Doktor, and the next day, Dirt Doktor submitted a plan of action to PWB to address the problems. (Id. ¶¶ 19–20; PWB’s Exs. 7-8, ECF Nos. 32-10, -11.) The Government sent second and third letters of concern to PWB on August 2 and 21, 2013, again detailing that Dirt Doktor’s work was delayed and unacceptable, and threatening to assess liquidated damages. (Romero Decl. ¶ 21–22; PWB’s Exs. 9-10, ECF Nos. 32-12, -13.) PWB wrote to Dirt Doktor on August 21, 2013, informing Dirt Doktor of the Government’s rejection of Dirt Doktor’s concrete slab and its threat to assess liquidated damages, and PWB advised Dirt Doktor and Firstnet Insurance that Dirt Doktor must replace the concrete slab and recover on the schedule. (Id. ¶ 23; PWB’s Ex. 11, ECF No. 32-14.) In this same letter, PWB informed Dirt Doktor that it had disapproved payment of Dirt Doktor’s invoices submitted for the periods ending March 30 ($101,196.32), April 30 ($109,588.68), May 31 ($69,147.98), and June 30 ($135,752.40), totaling $415,685.38, until the floor slab and overall work effort were in compliance with the project schedule. (PWB’s Ex. 11.) At some point during this time period, Dirt Doktor submitted a plan to PWB and the Government in which it proposed to repair the slab instead of removing it. (PWB’s Ex. 11 “You have already submitted a work plan for remediation of the floor slab ….”) On August 23, 2013, the Government sent a letter to PWB describing multiple problems with Dirt Doktor’s slab and stating that Dirt Doktor’s proposed plan to repair the slab was unacceptable. (Romero Decl. ¶ 24; PWB’s Ex. 12, ECF No. 32-15.) PWB then notified Dirt Doktor and Firstnet Insurance that the Government had given direction to remove and replace the slab. (Id. ¶ 25; PWB’s Ex. 13, ECF No. 32-16.) After learning that the Government rejected the proposed plan, Dirt Doktor notified PWB in writing that it disagreed with the Government’s assessment. (Counterclaim ¶ 12, Dirt Doktor and FirstNet’s Ans. ¶ 1.) On August 27, 2013, PWB informed Dirt Doktor and FirstNet Insurance in writing that the Government had rejected Dirt Doktor’s plan to repair the slab and had given explicit direction to replace the slab. (Romero Decl. ¶ 25; PWB’s Ex. 13, ECF No. 32-16.) In the same letter, PWB demanded that Dirt Doktor begin removing the slab within 48 hours, but also agreed to forward Dirt Doktor’s disagreement to the Government. (Id.) Finally, PWB notified Dirt Doktor that it cannot release any money to Dirt Doktor at the time. (PWB’s Ex. 13 at 3.) On August 29, 2013, Dirt Doktor submitted a plan to PWB for the slab demolition and replacement. (Romero Decl. ¶ 26; PWB’s Ex. 14, ECF No. 32-17; Counterclaim ¶ 13, Dirt Doktor’s Ans. 1.) On September 4 and 6, 2013, PWB provided Dirt Doktor with a schedule for the removal of the concrete slab. (Counterclaim ¶13; Dirt Doktor’s Ans. ¶ 1.) On September

Free access — add to your briefcase to read the full text and ask questions with AI

Camacho Family Partnership v. Patricia I. Romero, Inc., (gud 2016).

Camacho Family Partnership v. Patricia I. Romero, Inc. (Camacho Family Partnership v. Patricia I. Romero, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
In Re Oracle Corp. Securities Litigation
627 F.3d 376 (Ninth Circuit, 2010)
James Arena v. United States
226 F.2d 227 (Ninth Circuit, 1955)
Milenbach v. Commissioner of Internal Revenue
318 F.3d 924 (Ninth Circuit, 2003)
Soremekun v. Thrifty Payless, Inc.
509 F.3d 978 (Ninth Circuit, 2007)
Olympic Chartering SA v. MINISTRY OF IND. AND TRADE OF JORDAN
134 F. Supp. 2d 528 (S.D. New York, 2001)
Manganaro Corp. v. HITT Contracting, Inc.
193 F. Supp. 2d 88 (District of Columbia, 2002)
Schroeder v. McDonald
55 F.3d 454 (Ninth Circuit, 1995)
Van Dusseldorp v. Kim Lean Ho
4 F. Supp. 3d 1069 (S.D. Iowa, 2014)
Farquhar v. Collins
10 Ky. 31 (Court of Appeals of Kentucky, 1820)
Cortez v. City of New York
722 F.3d 483 (Second Circuit, 2013)
Barthelemy v. Air Lines Pilots Ass'n
897 F.2d 999 (Ninth Circuit, 1990)