J. W. Creech, Inc. v. Norfolk Air Conditioning Corp.

377 S.E.2d 605, 237 Va. 320, 5 Va. Law Rep. 1859, 1989 Va. LEXIS 50
CourtSupreme Court of Virginia
DecidedMarch 3, 1989
DocketRecord 860525; Record 860540
StatusPublished
Cited by16 cases

This text of 377 S.E.2d 605 (J. W. Creech, Inc. v. Norfolk Air Conditioning Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. W. Creech, Inc. v. Norfolk Air Conditioning Corp., 377 S.E.2d 605, 237 Va. 320, 5 Va. Law Rep. 1859, 1989 Va. LEXIS 50 (Va. 1989).

Opinion

RUSSELL, J.,

delivered the opinion of the Court.

This appeal arises from a construction contract dispute. It presents questions concerning responsibility for the additional cost of replacing damaged equipment, prejudgment interest, and remittitur.

In 1978, the Commonwealth, on behalf of Old Dominion University (ODU), engaged J. W. Creech, Inc. (Creech), as a general contractor to construct a new life science building at the ODU campus in Norfolk. The building is a complex, four-story structure containing environmental laboratories which simulate various climates encountered throughout the world. An essential part of the contract was the climate control system, which Creech awarded to a mechanical subcontractor, Norfolk Air Conditioning Corporation (Norfolk Air). Norfolk Air entered into various sub-subcontracts for parts of its work.

Numerous disputes arose between Creech and Norfolk Air during construction, and the building was not turned over to ODU until January 1981, six months behind schedule. Even then, the architect did not grant final approval, and final payment was not made to Creech, until July 6, 1982. On that date, Creech owed Norfolk Air $66,926.05 on Norfolk Air’s subcontract. Norfolk Air claimed an additional $23,142.16 for “extras.” Creech claimed various credits and “back charges.”

Norfolk Air brought this action in October 1982. The parties agreed that $66,926.05 was due to Norfolk Air on the basic subcontract, but disagreed with respect to claimed extras, credits, back charges, and interest. The case was tried to a jury. The jury returned several special verdicts which had been submitted by agreement of the parties. The court made certain adjustments to the verdicts and entered final judgment in March 1986. We granted appeals on the separate petitions filed by each party, and consolidated them for argument. The two appeals raise the three questions discussed below.

*323 I. THE EVAPCO COIL

Norfolk Air purchased from a materialman, and installed on the roof of the life science building, an evaporative condenser, called the “Evapco unit,” for a system of coolers serving refrigerated boxes in the environmental laboratories. The Evapco unit contained a copper coil through which water was continuously circulated by a pump. In the fall of 1980, Norfolk Air suggested to the architect, through Creech, that an antifreeze solution should be introduced into the coil to prevent freezing. The architect informed Norfolk Air that freezing would not be a danger if the system was operating, because of the continuous circulation provided by the pump.

On Thanksgiving weekend, 1980, a team of specialists from California, employed by another subcontractor, was conducting a series of tests in the laboratories. On Friday evening, having failed to complete their tests, they asked D. W. Phelps, Norfolk Air’s supervisor, if they might return on Saturday in order to complete their testing so as to be able to return to California. Phelps said, “[w]ell, I won’t be here. So whatever you do, you’ll have to shut [the pump] down when you leave.”

When work on the job resumed on Monday, it was discovered that the system had been shut down, the water in it had frozen, and the coil had developed approximately 100 leaks. Creech told Norfolk Air to “immediately make the necessary repair so that the unit can be put into operation.” Norfolk Air worked on the system over a period of months, attempting to repair the leaks. Eventually, Norfolk Air billed Creech $8,035.04 as an “extra,” more than the cost of a new coil, for the repair work.

The contract made the architect the sole arbiter of what was to be billed as “extra” work, and what was to be included in the contract. The architect was also made the sole judge of satisfactory completion. The architect ruled that ODU was entitled to a new Evapco unit, not a repaired one, and refused to accept the installation after Norfolk Air had done its repair work. Norfolk Air then obtained a replacement unit from the supplier and installed it, billing Creech $7,338.13 as an additional “extra” for the cost of the new unit. The architect flatly refused to approve either the charge for repairs or the charge for replacement as an “extra.”

At trial, over Creech’s objection, the court submitted both “extra” claims to the jury. The jury’s special verdicts found against *324 Norfolk Air on its claim for repairs, but awarded Norfolk Air $7,338.13 for the cost of the coil replacement. Creech assigns error to the court’s ruling submitting those claims to the jury.

We think the court erred. Norfolk Air, because of the erroneous instructions to “shut [the pump] down when you leave,” given by its superintendent to the laboratory testing team from California, was responsible for the damage. Further, under the terms of its contract, Norfolk Air was expressly made responsible for “work and equipment until finally inspected, tested, and accepted”; it was also required to “protect work against theft, injury or damage.” Finally, Norfolk Air’s contract provided: “If there is disagreement as to whether an item of work is an extra or a part of the contract, the Architects’ and Owners’ authorized agent’s decision on the matter will be final and binding for all parties.” As noted above, the architect ruled against Norfolk Air on this claim. Thus, as a matter of law, the problems with the Evapco coil were the responsibility of Norfolk Air, not Creech. The court erred in submitting the issue to the jury and we will reverse the judgment insofar as it includes this item.

II. PREJUDGMENT INTEREST

At trial, Norfolk Air contended that it had been entitled to payment “by December, 1980,” and that it was entitled to the amount of interest the claimed sum could have earned if timely paid and invested. Over Creech’s objection, Norfolk Air introduced a savings certificate from a lending institution to show that long-term deposits earned interest at 15% per annum in July 1982. Creech contended that no interest should be allowed at all, and álternatively contended that interest, if allowed, should not begin to run until November 30, 1983, when Norfolk Air ultimately completed the payment of its sub-subcontractors. The court instructed the jury that its verdict might include “interest from the date payment was due and at the rate you determine.” A verdict form was submitted to the jury which called prejudgment interest “delay damages.” The jury filled in blank spaces on the form to provide for interest at 15% from July 6, 1982, the date ODU paid Creech in full.

Creech moved to set the verdict aside on the ground, among others, that 15% exceeded the rate permitted by Code § 8.01-382, which provides, in pertinent part:

*325 Except as otherwise provided in § 8.3-122, in any action at law or suit in equity, the verdict of the jury, or if no jury the judgment or decree of the court, may provide for interest on any principal sum awarded, or any part thereof, and fix the period at which the interest shall commence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Devine, Donald v. Buki
Supreme Court of Virginia, 2015
Michael K. Hardey v. Elizabeth Metzger
Court of Appeals of Virginia, 2008
Upper Occoquan Sewage Auth. v. BLAKE CONST.
655 S.E.2d 10 (Supreme Court of Virginia, 2008)
Lambert v. Callahan (In Re Lambert Oil Co.)
347 B.R. 508 (W.D. Virginia, 2006)
LeBrun v. Yakeley
67 Va. Cir. 122 (Fairfax County Circuit Court, 2005)
Manganaro Corp. v. HITT Contracting, Inc.
193 F. Supp. 2d 88 (District of Columbia, 2002)
Shepard v. Capitol Foundry of Virginia, Inc.
554 S.E.2d 72 (Supreme Court of Virginia, 2001)
Poulston v. Rock
467 S.E.2d 479 (Supreme Court of Virginia, 1996)
Lane Construction Corp. v. Trading Merchandising Co.
36 Va. Cir. 399 (Stafford County Circuit Court, 1995)
Charles E. Wilson v. Commonwealth
Court of Appeals of Virginia, 1995
McClung v. Smith
870 F. Supp. 1384 (E.D. Virginia, 1994)
Bartz v. Board of Supervisors
379 S.E.2d 356 (Supreme Court of Virginia, 1989)
Bartz v. BD. OF SUP'RS OF FAIRFAX COUNTY
379 S.E.2d 356 (Supreme Court of Virginia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
377 S.E.2d 605, 237 Va. 320, 5 Va. Law Rep. 1859, 1989 Va. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-w-creech-inc-v-norfolk-air-conditioning-corp-va-1989.