SEG Properties, LLC v. NTC Mazzuca Contracting, Inc.

Court of Appeals of Virginia·Decided May 20, 2025·No. 1770224·Unpublished

Opinion

COURT OF APPEALS OF VIRGINIA UNPUBLISHED

Present: Judges Chaney, Callins and Senior Judge Humphreys Argued at Leesburg, Virginia

SEG PROPERTIES, LLC, ET AL.

MEMORANDUM OPINION* BY

v. Record No. 1770-22-4 JUDGE DOMINIQUE A. CALLINS MAY 20, 2025

NTC MAZZUCA CONTRACTING, INC.

FROM THE CIRCUIT COURT OF LOUDOUN COUNTY Douglas L. Fleming, Jr., Judge

Robert H.J. Loftus (McCandlish & Lillard, on briefs), for appellants.

Benjamin L. Williams (John T. Bergin; Cozen O’Connor;

Kilpatrick Townsend & Stockton LLP, on brief), for appellee.

This matter concerns a construction and mechanic’s lien dispute involving the Silver Eagle Shooting Range Facility in Loudoun County. NTC Mazzuca Contracting, Inc.

(“Mazzuca”), the general contractor, sued SEG Properties, LLC and Silver Eagle Group, LLC (collectively, “SEG”), the owners of the shooting range facility, alleging unjust enrichment, breach of contract, tortious interference with an existing contract, and tortious interference with a business relationship. SEG filed a counterclaim against Mazzuca for contract damages and indemnification.

After referring the case to a commissioner in chancery, the circuit court confirmed the commissioner’s report in its entirety and entered judgment in favor of Mazzuca in the amount of $1,253,521, plus prejudgment interest at 6% per annum, beginning 30 days after SEG’s

*

This opinion is not designated for publication. See Code § 17.1-413(A).

termination of its contract with Mazzuca. Further, the court ordered SEG’s property sold at auction to satisfy the liens, unless SEG posted a cash bond.

On appeal, SEG assigns 44 errors to the circuit court judgment, disputing various factual findings and legal conclusions.1 For the following reasons, we affirm the circuit court’s judgment.

BACKGROUND

I. The Contract Between SEG and Mazzuca, and the Role of JLL On April 11, 2018, SEG entered into a contract (the “Contract”) with Mazzuca to construct a private shooting range (the “Project”) on SEG’s property, a “fast track” job. To assist with the Project, SEG hired a project manager—Jones, Lang, LaSalle, Inc. (“JLL”)—to, according to the bidding materials, serve in the capacity of “[SEG’s] representative for ‘all project and development matters.’” The agreement between SEG and JLL stated that JLL “shall assume all duties under this Agreement as an independent contractor; and in no event shall this be considered an agreement of employment, partnership or agency.”

The same day that SEG and Mazzuca entered into the Contract, JLL notified Mazzuca to proceed with the Project. In May 2018, SEG and Mazzuca signed a “Rider” that supplemented and modified the terms of the Contract. Neither the Contract nor the Rider contained a specific performance deadline or a substantial completion date; the Contract only included a proposed project schedule.

1 This number includes both main and subparts. And although the number of claims is not always indicative of the strength of a party’s appeal, the “blunderbuss approach,” Tatusko v. Commonwealth, 79 Va. App. 721, 729 (2024), SEG “utilized in this appeal is as unappreciated as it is ineffective,” Fadness v. Fadness, 52 Va. App. 833, 851 (2008).

II. Mazzuca’s Payment Applications The Contract provided that Mazzuca would file monthly payment applications (“PAs” or singular “PA”) with the “Architect,” who would evaluate Mazzuca’s work and verify the amounts properly due; the Architect would then either issue a certificate for payment to SEG within seven days or notify SEG and Mazzuca of the Architect’s reasons for withholding certification. According to § 4.1.3 of the Contract, if the Architect received the PA prior to the 25th day of the month, SEG was required to pay Mazzuca “no[] later than the 25 [sic] day of the following month.” If the Architect received the PA “after the date fixed above,” then SEG was required to pay Mazzuca no later than 30 days after the Architect received the PA. The Contract further required that if a dispute arose concerning payment, SEG would continue making payments for all undisputed portions of the Project no later than 30 days after the Architect received the PA.

Mazzuca submitted six PAs in total. JLL and Mazzuca both testified that, to “[s]peed things up,” they employed a “pencil” PA process which differed from the terms of the Contract. The “pencil” PA process involved Mazzuca submitting a “pencil” PA to JLL for review instead of sending the PA directly to the Architect for approval. JLL would then review the PA and advise Mazzuca if it had any comments or concerns about the PA. Upon completion of the “pencil” PA process, Mazzuca “was to send the final signed pay application back to the ‘ownership team,’ which included JLL, the Owner’s representative.” Thereafter, JLL would forward the signed PA to the Architect. JLL and Mazzuca adopted this “pencil” process for the first three PAs.

Regarding PA 1, Mazzuca submitted a “pencil” version to JLL on April 21, 2018.

Because there were clear errors in the PA, Mazzuca signed a revised PA 1 on April 24, 2018.

SEG did not pay Mazzuca for PA 1 until June 28, 2018, 65 days after Mazzuca signed the revised PA.

Mazzuca submitted PA 3 on June 29, 2018. Between June 29, 2018, and August 8, 2018, SEG and Mazzuca revised PA 3 as they considered whether certain change orders should be included or excluded. The base contract work value, however, from original submission to final submission, only decreased by one percentage point, from 70% to 69%. SEG paid the base contract work value of PA 3 on August 22, 2018.

III. SEG’s Notice to Cure and Formula for Cure On July 19, 2018, SEG issued to Mazzuca a notice to cure. SEG alleged that Mazzuca breached § 20.2.1 of the Contract by continually failing to supply skilled workers and grossly mismanaging the procurement process, which “caused delays in performance.” The notice also stated that, per the Contract as amended by the Rider Section 20.2.1.5, SEG had the right to terminate Mazzuca for cause if Mazzuca “fail[ed] to timely perform the Work, or any part of the Work, in accordance with the published contract schedule dates.” The notice to cure additionally stated that “[i]f your failures are not cured or your actions do not demonstrate a formula for cure satisfactory to SEG, within seven (7) days of today’s date, we intend to terminate your contract for cause under the above stated articles.” The notice to cure did not prescribe what constituted a satisfactory “formula for cure.”

Mazzuca responded to the notice the day after its receipt, indicating its intent to complete the Project and asking to meet to discuss the progress on the Project. Mazzuca did not receive a response from SEG, and so continued working past the seven-day timeline SEG outlined for possible termination.

IV. SEG’s Supplementation and Notice of Termination On August 23, 2018, a little over one month after its notice to cure, SEG informed Mazzuca it was “immediately” supplementing Mazzuca’s workforce under § 8.3 of the Contract. Contract § 8.3 required that SEG provide ten days’ written notice to Mazzuca prior to supplementing its workforce. Instead, SEG supplemented Mazzuca’s workforce the very next day, prior to Mazzuca’s August 25, 2018 written response to the notice. On September 6, 2018, SEG terminated Mazzuca for cause, “effective immediately.”

V. This Litigation In 2019, Mazzuca initiated litigation to enforce a mechanic’s lien, and its complaint alleged unjust enrichment, breach of contract, tortious interference with an existing contract, and tortious interference with a business relationship.2 SEG countersued for breach of contract. Thereafter, the circuit court referred the case to a commissioner in chancery to make various findings of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

SEG Properties, LLC v. NTC Mazzuca Contracting, Inc., (Va. Ct. App. 2025).

SEG Properties, LLC v. NTC Mazzuca Contracting, Inc. (SEG Properties, LLC v. NTC Mazzuca Contracting, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mathews v. PHH Mortg. Corp.
724 S.E.2d 196 (Supreme Court of Virginia, 2012)
Sunrise Continuing Care, LLC v. Wright
671 S.E.2d 132 (Supreme Court of Virginia, 2009)
Palmer & Palmer v. Waterfront Marine
662 S.E.2d 77 (Supreme Court of Virginia, 2008)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Upper Occoquan Sewage Auth. v. BLAKE CONST.
655 S.E.2d 10 (Supreme Court of Virginia, 2008)
Barber v. VistaRMS, Inc.
634 S.E.2d 706 (Supreme Court of Virginia, 2006)
City of Chesapeake v. STATES SELF-INSURERS
628 S.E.2d 539 (Supreme Court of Virginia, 2006)
Sanchez v. Medicorp Health System
618 S.E.2d 331 (Supreme Court of Virginia, 2005)
Stockbridge v. Gemini Air Cargo, Inc.
611 S.E.2d 600 (Supreme Court of Virginia, 2005)
Acordia of Virginia Insurance Agency, Inc. v. Genito Glenn, L.P.
560 S.E.2d 246 (Supreme Court of Virginia, 2002)
Johnson v. Cauley
546 S.E.2d 681 (Supreme Court of Virginia, 2001)
Countryside Orthopaedics, P.C. v. Peyton
541 S.E.2d 279 (Supreme Court of Virginia, 2001)
Government Employees Insurance v. Hall
533 S.E.2d 615 (Supreme Court of Virginia, 2000)
Reid v. Boyle
527 S.E.2d 137 (Supreme Court of Virginia, 2000)
Hartzell Fan, Inc. v. Waco, Inc.
505 S.E.2d 196 (Supreme Court of Virginia, 1998)
Advanced Marine Enterprises, Inc. v. PRC Inc.
501 S.E.2d 148 (Supreme Court of Virginia, 1998)
Ward's Equipment, Inc. v. New Holland North America, Inc.
493 S.E.2d 516 (Supreme Court of Virginia, 1997)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Orthopaedic and Spine Center v. Muller Martini Manufacturing Corp.
737 S.E.2d 544 (Court of Appeals of Virginia, 2013)
Fadness v. Fadness
667 S.E.2d 857 (Court of Appeals of Virginia, 2008)