SEG Properties, LLC v. NTC Mazzuca Contracting, Inc.

CourtCourt of Appeals of Virginia
DecidedMay 20, 2025
Docket1770224
StatusUnpublished

This text of SEG Properties, LLC v. NTC Mazzuca Contracting, Inc. (SEG Properties, LLC v. NTC Mazzuca Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SEG Properties, LLC v. NTC Mazzuca Contracting, Inc., (Va. Ct. App. 2025).

Opinion

COURT OF APPEALS OF VIRGINIA UNPUBLISHED

Present: Judges Chaney, Callins and Senior Judge Humphreys Argued at Leesburg, Virginia

SEG PROPERTIES, LLC, ET AL. MEMORANDUM OPINION* BY v. Record No. 1770-22-4 JUDGE DOMINIQUE A. CALLINS MAY 20, 2025 NTC MAZZUCA CONTRACTING, INC.

FROM THE CIRCUIT COURT OF LOUDOUN COUNTY Douglas L. Fleming, Jr., Judge

Robert H.J. Loftus (McCandlish & Lillard, on briefs), for appellants.

Benjamin L. Williams (John T. Bergin; Cozen O’Connor; Kilpatrick Townsend & Stockton LLP, on brief), for appellee.

This matter concerns a construction and mechanic’s lien dispute involving the Silver

Eagle Shooting Range Facility in Loudoun County. NTC Mazzuca Contracting, Inc.

(“Mazzuca”), the general contractor, sued SEG Properties, LLC and Silver Eagle Group, LLC

(collectively, “SEG”), the owners of the shooting range facility, alleging unjust enrichment,

breach of contract, tortious interference with an existing contract, and tortious interference with a

business relationship. SEG filed a counterclaim against Mazzuca for contract damages and

indemnification.

After referring the case to a commissioner in chancery, the circuit court confirmed the

commissioner’s report in its entirety and entered judgment in favor of Mazzuca in the amount of

$1,253,521, plus prejudgment interest at 6% per annum, beginning 30 days after SEG’s

* This opinion is not designated for publication. See Code § 17.1-413(A). termination of its contract with Mazzuca. Further, the court ordered SEG’s property sold at

auction to satisfy the liens, unless SEG posted a cash bond.

On appeal, SEG assigns 44 errors to the circuit court judgment, disputing various factual

findings and legal conclusions.1 For the following reasons, we affirm the circuit court’s

judgment.

BACKGROUND

I. The Contract Between SEG and Mazzuca, and the Role of JLL

On April 11, 2018, SEG entered into a contract (the “Contract”) with Mazzuca to

construct a private shooting range (the “Project”) on SEG’s property, a “fast track” job. To assist

with the Project, SEG hired a project manager—Jones, Lang, LaSalle, Inc. (“JLL”)—to,

according to the bidding materials, serve in the capacity of “[SEG’s] representative for ‘all

project and development matters.’” The agreement between SEG and JLL stated that JLL “shall

assume all duties under this Agreement as an independent contractor; and in no event shall this be

considered an agreement of employment, partnership or agency.”

The same day that SEG and Mazzuca entered into the Contract, JLL notified Mazzuca to

proceed with the Project. In May 2018, SEG and Mazzuca signed a “Rider” that supplemented

and modified the terms of the Contract. Neither the Contract nor the Rider contained a specific

performance deadline or a substantial completion date; the Contract only included a proposed

project schedule.

1 This number includes both main and subparts. And although the number of claims is not always indicative of the strength of a party’s appeal, the “blunderbuss approach,” Tatusko v. Commonwealth, 79 Va. App. 721, 729 (2024), SEG “utilized in this appeal is as unappreciated as it is ineffective,” Fadness v. Fadness, 52 Va. App. 833, 851 (2008). -2- II. Mazzuca’s Payment Applications

The Contract provided that Mazzuca would file monthly payment applications (“PAs” or

singular “PA”) with the “Architect,” who would evaluate Mazzuca’s work and verify the

amounts properly due; the Architect would then either issue a certificate for payment to SEG

within seven days or notify SEG and Mazzuca of the Architect’s reasons for withholding

certification. According to § 4.1.3 of the Contract, if the Architect received the PA prior to the

25th day of the month, SEG was required to pay Mazzuca “no[] later than the 25 [sic] day of the

following month.” If the Architect received the PA “after the date fixed above,” then SEG was

required to pay Mazzuca no later than 30 days after the Architect received the PA. The Contract

further required that if a dispute arose concerning payment, SEG would continue making

payments for all undisputed portions of the Project no later than 30 days after the Architect

received the PA.

Mazzuca submitted six PAs in total. JLL and Mazzuca both testified that, to “[s]peed

things up,” they employed a “pencil” PA process which differed from the terms of the Contract.

The “pencil” PA process involved Mazzuca submitting a “pencil” PA to JLL for review instead

of sending the PA directly to the Architect for approval. JLL would then review the PA and

advise Mazzuca if it had any comments or concerns about the PA. Upon completion of the

“pencil” PA process, Mazzuca “was to send the final signed pay application back to the

‘ownership team,’ which included JLL, the Owner’s representative.” Thereafter, JLL would

forward the signed PA to the Architect. JLL and Mazzuca adopted this “pencil” process for the

first three PAs.

Regarding PA 1, Mazzuca submitted a “pencil” version to JLL on April 21, 2018.

Because there were clear errors in the PA, Mazzuca signed a revised PA 1 on April 24, 2018.

-3- SEG did not pay Mazzuca for PA 1 until June 28, 2018, 65 days after Mazzuca signed the

revised PA.

Mazzuca submitted PA 3 on June 29, 2018. Between June 29, 2018, and August 8, 2018,

SEG and Mazzuca revised PA 3 as they considered whether certain change orders should be

included or excluded. The base contract work value, however, from original submission to final

submission, only decreased by one percentage point, from 70% to 69%. SEG paid the base

contract work value of PA 3 on August 22, 2018.

III. SEG’s Notice to Cure and Formula for Cure

On July 19, 2018, SEG issued to Mazzuca a notice to cure. SEG alleged that Mazzuca

breached § 20.2.1 of the Contract by continually failing to supply skilled workers and grossly

mismanaging the procurement process, which “caused delays in performance.” The notice also

stated that, per the Contract as amended by the Rider Section 20.2.1.5, SEG had the right to

terminate Mazzuca for cause if Mazzuca “fail[ed] to timely perform the Work, or any part of the

Work, in accordance with the published contract schedule dates.” The notice to cure additionally

stated that “[i]f your failures are not cured or your actions do not demonstrate a formula for cure

satisfactory to SEG, within seven (7) days of today’s date, we intend to terminate your contract

for cause under the above stated articles.” The notice to cure did not prescribe what constituted a

satisfactory “formula for cure.”

Mazzuca responded to the notice the day after its receipt, indicating its intent to complete

the Project and asking to meet to discuss the progress on the Project. Mazzuca did not receive a

response from SEG, and so continued working past the seven-day timeline SEG outlined for

possible termination.

-4- IV. SEG’s Supplementation and Notice of Termination

On August 23, 2018, a little over one month after its notice to cure, SEG informed

Mazzuca it was “immediately” supplementing Mazzuca’s workforce under § 8.3 of the Contract.

Contract § 8.3 required that SEG provide ten days’ written notice to Mazzuca prior to

supplementing its workforce. Instead, SEG supplemented Mazzuca’s workforce the very next

day, prior to Mazzuca’s August 25, 2018 written response to the notice. On September 6, 2018,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathews v. PHH Mortg. Corp.
724 S.E.2d 196 (Supreme Court of Virginia, 2012)
Sunrise Continuing Care, LLC v. Wright
671 S.E.2d 132 (Supreme Court of Virginia, 2009)
Palmer & Palmer v. Waterfront Marine
662 S.E.2d 77 (Supreme Court of Virginia, 2008)
Nichols Const. v. Virginia MacHine Tool
661 S.E.2d 467 (Supreme Court of Virginia, 2008)
Upper Occoquan Sewage Auth. v. BLAKE CONST.
655 S.E.2d 10 (Supreme Court of Virginia, 2008)
Barber v. VistaRMS, Inc.
634 S.E.2d 706 (Supreme Court of Virginia, 2006)
City of Chesapeake v. STATES SELF-INSURERS
628 S.E.2d 539 (Supreme Court of Virginia, 2006)
Sanchez v. Medicorp Health System
618 S.E.2d 331 (Supreme Court of Virginia, 2005)
Stockbridge v. Gemini Air Cargo, Inc.
611 S.E.2d 600 (Supreme Court of Virginia, 2005)
Acordia of Virginia Insurance Agency, Inc. v. Genito Glenn, L.P.
560 S.E.2d 246 (Supreme Court of Virginia, 2002)
Johnson v. Cauley
546 S.E.2d 681 (Supreme Court of Virginia, 2001)
Countryside Orthopaedics, P.C. v. Peyton
541 S.E.2d 279 (Supreme Court of Virginia, 2001)
Government Employees Insurance v. Hall
533 S.E.2d 615 (Supreme Court of Virginia, 2000)
Reid v. Boyle
527 S.E.2d 137 (Supreme Court of Virginia, 2000)
Hartzell Fan, Inc. v. Waco, Inc.
505 S.E.2d 196 (Supreme Court of Virginia, 1998)
Advanced Marine Enterprises, Inc. v. PRC Inc.
501 S.E.2d 148 (Supreme Court of Virginia, 1998)
Ward's Equipment, Inc. v. New Holland North America, Inc.
493 S.E.2d 516 (Supreme Court of Virginia, 1997)
Horton v. Horton
487 S.E.2d 200 (Supreme Court of Virginia, 1997)
Orthopaedic and Spine Center v. Muller Martini Manufacturing Corp.
737 S.E.2d 544 (Court of Appeals of Virginia, 2013)
Fadness v. Fadness
667 S.E.2d 857 (Court of Appeals of Virginia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
SEG Properties, LLC v. NTC Mazzuca Contracting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/seg-properties-llc-v-ntc-mazzuca-contracting-inc-vactapp-2025.