Palmer & Palmer v. Waterfront Marine

662 S.E.2d 77, 276 Va. 285, 2008 Va. LEXIS 83
CourtSupreme Court of Virginia
DecidedJune 6, 2008
Docket071373
StatusPublished
Cited by48 cases

This text of 662 S.E.2d 77 (Palmer & Palmer v. Waterfront Marine) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer & Palmer v. Waterfront Marine, 662 S.E.2d 77, 276 Va. 285, 2008 Va. LEXIS 83 (Va. 2008).

Opinion

OPINION BY Justice S. BERNARD GOODWYN.

In this appeal, we consider whether the trial court erred in its interpretation of a contract between Palmer & Palmer Company, LLC ("Palmer") and Waterfront Marine Construction, Inc. ("Waterfront") and in its imposition of liability on Palmer for damage resulting from Waterfront's crane falling into an abandoned, disconnected septic tank on Palmer's property.

Waterfront filed a complaint alleging breach of contract against Palmer and seeking damages primarily related to repair of its crane. Palmer and Waterfront filed joint stipulations as to the facts of the case, agreed that no material issues of fact remained in dispute, and submitted the matter for the trial court's consideration on competing motions for summary judgment. The trial court denied Palmer's motion for summary judgment and, holding that Palmer breached the contract, granted Waterfront's motion for summary judgment. The trial court awarded Waterfront damages plus attorneys' fees. Palmer appeals to this Court.

The facts are undisputed. Waterfront, a marine construction and pile driving company, and Palmer, the owner of the property and the general contractor for construction of a house on 856 South Atlantic Avenue, Virginia Beach ("Lot 2"), entered into a contract. The contract specified that Waterfront would drive foundation piles into the ground on Lot 2.

On August 5, 2004, an employee of Waterfront was operating a crane owned by Water-front on Lot 2 when the crane fell into a buried septic tank and was damaged. The septic tank was empty and covered with approximately four to ten inches of sand. Prior to the accident, neither Waterfront nor Palmer was aware of the existence of the septic tank. The house previously located on Lot 2 had been demolished before Palmer bought the property; however, the house utilized the City of Virginia Beach public sewage system from at least 1990. No recorded plat, survey, or drawing disclosed a septic tank on the property. Also, the Department of Public Health for the City of Virginia Beach, which is the agency that keeps records of private septic systems in the City of Virginia Beach, had no record of any septic system or tank as having been located on the subject property.

Waterfront sought damages from Palmer on a purely contractual basis because of the damage to Waterfront's crane and other expenses related thereto. The relevant provisions of the contract are as follows:

2.1 EXCLUSIONS: ... Waterfront ... assumes no responsibility for the following:

....

2. Removal of underground or overhead obstructions.

2.2 WORK AND/OR SERVICES TO BE PERFORMED BY OWNER PRIOR TO PILE DRIVING:

6. Location, protection, and removal of all utilities in area.

7. Protection of existing structures.

4.1 ADDITIONAL WORK: Should additional work such as, but not limited to, underground obstructions such as trees, stumps, rocks, debris, etc. be encountered, an extra charge for equipment, labor, overhead and profit will be charge [sic] at $250.00/hour for removal or augering.

*80 The trial court concluded that Palmer was liable based on the court's combined reading of sections 2.1(2) and 4.1, reasoning that reading those provisions together indicates that Palmer was responsible for removal of underground obstructions. Additionally, the trial court found that the septic tank was either a utility or an existing structure that Palmer was responsible for under sections 2.2(6) or 2.2(7) of the contract. On March 30, 2007, the trial court awarded Waterfront damages in the amount of $22,696.05 plus attorneys' fees in the amount of $11,006.55.

Palmer argues that the trial court erred in interpreting the contract and imposing liability and damages. Focusing on the language of the contract, Palmer contends that the contract does not reflect an agreement that Palmer would remove or locate an abandoned septic tank. According to Palmer, the trial court created a duty that was not memorialized in the contract.

Waterfront argues that the trial court correctly interpreted the contract. Waterfront states that Palmer is liable under the contract for primarily three reasons. First, Waterfront asserts that sections 2.1(2) and 4.1 demonstrate it was Palmer's responsibility to prepare the work site, which included removing underground obstructions. Second, Palmer failed to "locate and protect existing structures, specifically the septic tank, as required by Paragraph 2.2(7)." Third, section 2.2(6) provides that Palmer was responsible for the location and removal of "all utilities." Arguing that the septic tank is a utility, Waterfront contends that Palmer breached the contract by failing to comply with section 2.2(6).

Interpretation of a contract is a question of law that is reviewed de novo. PMA Capital Ins. Co. v. U.S. Airways, Inc., 271 Va. 352 , 357-58, 626 S.E.2d 369 , 372 (2006). When a contract is clear and unambiguous, it is the court's duty to interpret the contract, as written. Winn v. Aleda Constr. Co., 227 Va. 304 , 307, 315 S.E.2d 193 , 194 (1984). On appeal, this Court is not bound by the trial court's determinations regarding the interpretation of an unambiguous contract. Gordonsville Energy, L.P. v. Virginia Elec. & Power Co., 257 Va. 344 , 353, 512 S.E.2d 811 , 816 (1999).

In a breach of contract claim, the parties' contract becomes the law governing the case unless it is repugnant to some rule of law or public policy. Winn, 227 Va. at 307 , 315 S.E.2d at 194 . This Court must construe the contract as it is written. Christopher Assocs. v. J.C. Sessoms, Jr., 245 Va. 18 , 22, 425 S.E.2d 795 , 797 (1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew Hamden Cook v. Commonwealth of Virginia
Court of Appeals of Virginia, 2025
Eftakhar Alam v. Commonwealth of Virginia
Court of Appeals of Virginia, 2024
Orr v. Keystone RV Company
E.D. Virginia, 2024
Sobia Ahmed v. Imperial Auto, LLC
Court of Appeals of Virginia, 2024

Cite This Page — Counsel Stack

Bluebook (online)
662 S.E.2d 77, 276 Va. 285, 2008 Va. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-palmer-v-waterfront-marine-va-2008.