Brooks & Co. General Contractors, Inc. v. School Board of Chesterfield County

CourtCourt of Appeals of Virginia
DecidedFebruary 11, 2025
Docket1989232
StatusUnpublished

This text of Brooks & Co. General Contractors, Inc. v. School Board of Chesterfield County (Brooks & Co. General Contractors, Inc. v. School Board of Chesterfield County) is published on Counsel Stack Legal Research, covering Court of Appeals of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks & Co. General Contractors, Inc. v. School Board of Chesterfield County, (Va. Ct. App. 2025).

Opinion

COURT OF APPEALS OF VIRGINIA UNPUBLISHED

Present: Judges O’Brien, Malveaux and Raphael Argued at Richmond, Virginia

BROOKS & CO. GENERAL CONTRACTORS, INC. MEMORANDUM OPINION* BY v. Record No. 1989-23-2 JUDGE MARY GRACE O’BRIEN FEBRUARY 11, 2025 SCHOOL BOARD OF CHESTERFIELD COUNTY

FROM THE CIRCUIT COURT OF CHESTERFIELD COUNTY Edward A. Robbins, Jr., Judge

Bradley P. Marrs (Marrs & Henry, on briefs), for appellant.

Meredith E. Carpenter, Senior Assistant County Attorney (Jeffrey Lee Mincks, County Attorney, on brief), for appellee.

This appeal arises from the dismissal of a contract action that Brooks & Co. General

Contractors, Inc. (“Brooks”) brought against the School Board of Chesterfield County (“School

Board”). Brooks alleged that the School Board breached two contracts by not compensating Brooks

for costs to rent temporary freezer and cooler units during construction project delays. The court

sustained the School Board’s demurrer without leave to amend, finding that the contracts expressly

obliged Brooks to pay these costs. On appeal, Brooks argues the court erred in sustaining the

demurrer and denying leave to amend. For the following reasons, we affirm.

BACKGROUND

In 2021, the School Board needed to install a new food freezer at J.G. Hening Elementary

School and replace a food cooler/freezer at Bailey Bridge Middle School. To obtain contractors for

this work, the School Board issued invitations for bids (IFBs). The IFBs set due dates for

* This opinion is not designated for publication. See Code § 17.1-413(A). contractors to submit bids and for the School Board to open the submissions: May 5, 2021 was the

due date for the Hening bids, and May 6, 2021 was the due date for the Bailey Bridge bids. The

IFBs provided that “[a]ll bids submitted shall be binding for sixty (60) calendar days following bid

opening date.”

Brooks submitted bids and was awarded both contracts, which the parties executed on May

12, 2021. Each contract consisted of several “Contract Documents” enumerated in Article 9 of the

parties’ core agreement. The Contract Documents included instructions to bidders and amendments

thereto; a bid form; and the IFB with multiple “Addenda.” Article 9 also contained carve-out

language excluding documents from the contract. It stated that “[p]ortions of Addenda relating to

bidding or proposal requirements are not part of the Contract Documents unless the bidding or

proposal requirements are also enumerated in Article 9.” The end of Article 9 reserved a space for

listing “any additional documents that are intended to form part of the Contract Documents” and

reiterated that “portions of Addenda relating to bidding or proposal requirements, and other

information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the

Contract Documents unless enumerated in this Agreement.” The parties did not list additional

documents for either contract and left this portion of Article 9 blank.

Both contracts required Brooks to substantially complete the work 90 days after the School

Board issued a notice to proceed. This 90-day period was set forth in the parties’ core agreement,

and in two other Article 9 Contract Documents: the bidding-instruction amendments and the bid

form. These provisions did not specify a date for the School Board to issue a notice to proceed,

only that the work was to be substantially completed 90 days later.

Brooks, however, argues that both contracts “stipulated” that the School Board would

provide notices to proceed for each project in “mid-May” 2021. To support this argument, Brooks

relies on minutes from a “non-mandatory [p]re-[b]id conference” at which the School Board’s

-2- architect addressed the construction schedule. According to the meeting minutes, the architect said

that he “anticipated that the Notice to Proceed [would be] issued in mid-May.” The minutes

provided as follows:

Architect notes that Substantial Completion of the project shall occur no more than ninety (90) days following Notice to Proceed, with Substantial Completion by August 16, and Final Completion by September 16. It is anticipated that the Notice to Proceed will be issued in mid-May, which will begin the 90[-]day Contract period. Full, unencumbered access to the project site will be available to the Contractor on the first day following the end of the school year for students, currently scheduled to be June 18, 2021. All on-site construction work shall occur between June 19, 2021 and August 16, 2021. The Contractor shall have limited access to the site prior to June 18 for the purpose of on-site verification of existing conditions only.

(Emphasis added).1

The meeting minutes were identified in and attached to one of the Contract Documents—

specifically, Addendum 1 to each project’s IFB. Article 9 identified Addendum 1 as having six

pages, a page range that included the minutes. Article 9, did not, however, specifically refer to the

meeting minutes or list them in the space reserved for additional Contract Documents. Furthermore,

whereas Addendum 1 specifically explained when it modified contractual terms, the provision

referencing the meeting minutes merely stated: “The minutes of the non-mandatory [p]re-[b]id

conference [are] attached hereto.”

The contracts expressly required Brooks to activate the new freezer/cooler units2 at each

school by July 30, 2021, and to provide temporary freezer/cooler units at Brooks’s sole expense if

unable to meet that deadline. Specifically, Addendum 1 provided as follows:

1 The minutes were the same for each project, except that the Hening minutes added the phrase “following the May School Board meeting” after “[i]t is anticipated that the Notice to Proceed will be issued in mid-May.” 2 We use “freezer/cooler units” when referring collectively to the freezer/cooler unit for Bailey Bridge and the freezer unit for Hening. -3- a. [The School Board] will empty the existing [freezer/cooler] unit of all food and turn it off at the end of the last day of school (June 18, 2021). . . . The [School Board’s] staff will re-occupy the kitchen on Monday, August 02, 2021. On this date, the [School Board’s staff] will begin stocking the [k]itchen and the new [freezer/cooler] unit for use. Therefore, the new [freezer/cooler] shall be activated no later than Friday, July 30, 2021, so the unit will be conditioned the following Monday.

b. If the new [freezer/cooler] unit is not activated by July 30, 2021, [Brooks] shall at no additional cost to the [School Board], provide temporary [freezer/cooler] units of the type and quantity specified in the Project Manual . . . .

(Emphases added).

Brooks did not activate the new freezer/cooler units by July 30, 2021. Instead, Brooks

activated the new unit at Hening on October 22 and the new unit at Bailey Bridge on November 16.

Brooks submitted change orders to the School Board seeking reimbursement for

delay-related costs. Included in this submission was $4,541.22 for renting units for the Hening

project and $13,612.95 for the Bailey Bridge project. These requests reflected only a portion of the

total rental costs Brooks incurred. According to Brooks, it deducted from each total rental figure the

“amounts [that] it had expected to incur, per the prescribed project schedule” and “sought only the

rental expenses to the extent they were increased by virtue of the [School] Board’s delays.”

The School Board did not reimburse Brooks for its rental costs, reasoning that those costs

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palmer & Palmer v. Waterfront Marine
662 S.E.2d 77 (Supreme Court of Virginia, 2008)
Augusta Mut. Ins. Co. v. Mason
645 S.E.2d 290 (Supreme Court of Virginia, 2007)
Filak v. George
594 S.E.2d 610 (Supreme Court of Virginia, 2004)
Ward's Equipment, Inc. v. New Holland North America, Inc.
493 S.E.2d 516 (Supreme Court of Virginia, 1997)
Hechler Chevrolet, Inc. v. General Motors Corp.
337 S.E.2d 744 (Supreme Court of Virginia, 1985)
Allen v. Aetna Casualty & Surety Co.
281 S.E.2d 818 (Supreme Court of Virginia, 1981)
Mueller v. Commonwealth
426 S.E.2d 339 (Court of Appeals of Virginia, 1993)
AGCS Marine Ins. Co. v. Arlington Cnty.
800 S.E.2d 159 (Supreme Court of Virginia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Brooks & Co. General Contractors, Inc. v. School Board of Chesterfield County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-co-general-contractors-inc-v-school-board-of-chesterfield-vactapp-2025.