Dery v. General Motors Corp. (In Re Fordson Engineering Corp.)

25 B.R. 506, 1982 Bankr. LEXIS 5339
CourtUnited States Bankruptcy Court, E.D. Michigan
DecidedDecember 8, 1982
Docket19-41001
StatusPublished
Cited by53 cases

This text of 25 B.R. 506 (Dery v. General Motors Corp. (In Re Fordson Engineering Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dery v. General Motors Corp. (In Re Fordson Engineering Corp.), 25 B.R. 506, 1982 Bankr. LEXIS 5339 (Mich. 1982).

Opinion

MEMORANDUM OPINION AND ORDER

GEORGE E. WOODS, Bankruptcy Judge.

Claiming a breach of contract, a complaint was filed in this Court by Fordson Engineering Corporation (Fordson) for recovery of damages from Brian & Gregory Contracting Company (B & G) in the amount of approximately $76,850.00.

*508 I.

On January 11, 1981, Fordson filed for relief under Chapter 11. On or about February 15, 1981, Fordson entered into two contracts with B & G wherein Fordson was to supply labor and materials for structural steel and support slabs on the General Motors Assembly Division (GMAD) Lake Orion project. GMAD is the owner of the project, Barton-Malow Company (Barton-Malow) is the construction manager, B & G is the prime contractor, and Fordson was the subcontractor of B & G. On August 31, 1981, Fordson terminated its contracts with B & G.

On September 18, 1981, Fordson filed a statement of account and mechanics’ lien. On December 18,1981, Fordson filed a complaint against GMAD, Barton-Malow, B & G and numerous sub-contractors seeking damages in the amount of $125,000.00 plus costs, interest and attorney fees. Fordson further requested that, in the event of a default, the Court find it to have a lien on the land and buildings at issue superior to that of the other defendants.

Claims as to defendants other than B & G have either been resolved or held in abeyance and are not the subject of the present action. 1 As to B & G, several findings were made by the Court during the course of litigation. First, on February 12, 1982, the Court issued a memorandum opinion and order finding that Fordson had substantially complied with the Michigan Mechanics’ Lien Act, MCLA 570.1 et seq. 2 Second, on May 18, 1982, the Court issued an order allowing B & G to amend its affirmative defenses and denying Fordson’s motion to dismiss and/or for summary judgment. Fordson’s motion denied B & G had any right of setoff.

The testimony presented at trial, as well as the findings of fact and conclusions of law filed by the parties, places Fordson’s claim for recovery into three categories: (1) amounts due under contract P240, (2) amounts due under contract P246, and (3) amounts billed as extras to those two contracts. Fordson computes the funds owed to it for labor and materials supplied to B & G essentially as follows:

Base Contract - $93,222.00 - P240 - Job #5-81
96% Complete $88,560.90
Change Order #1 1,881.00
Total $90,441.90
Paid to Date 79,401.00
Amount Due: $11,040.90
Base Contract - $264,520.00 - P246 - Job #6-81
95% Complete $251,294.00
Paid to Date 220,075.00
Amount Due: $31,219.00
Extras $ 72,988.51
Paid to Date 22,619.00
Amount Due $50,369.51
P240 $11,040.90
P246 31,219.00
Extras 50,369.51 $92,629.41
Equipment in Field $13,689.39
TOTAL DUE: $106,318.80 3

Fordson admitted termination of the contract prior to completion.

Defendant B & G argues that as to contract P240, and contract P246, Fordson has been fully paid; that the amount claimed as owing by Fordson represents retainer held to completion of the contracts plus a sum representing a portion of the contracts not completed as of September 1, 1981. As to the amounts billed as extras to the two contracts, B & G asserts that: (1) extras are introduced by emergency field orders and bulletins; (2) extras so introduced are only paid by issuance of a change order; (3) as *509 of September 1, 1981, no change orders had been issued, the first change order being issued on October 30, 1981; (4) change orders totaling $50,915.48 were approved subsequent to October 30,1981. However, B & G asserts, since the earliest change order is dated October 30 and Fordson terminated the contract as of August 31, no moneys were owed.

Additionally, B & G alleges it is undisputed that Fordson breached its contract by refusing to complete it; therefore, it is entitled to offset all consequential damages of the breach subsequent to August 31. The total amount of offset as proposed by B & G is $120,951.12. This figure includes payroll costs to complete; material costs to complete; the costs incurred in discharging Fordson’s mechanics’ lien; costs incurred in discharging the claim of W.S. Molnar Company, a supplier of Fordson; and attorney fees. With regard to the setoff amount, B & G contends that Fordson’s extras, allowed and paid to defendant subsequent to August 31, 1981, are in the amount of $50,-915.48 and that B & G has or will receive retainer for Fordson’s completed work, previously withheld by GMAD and Barton-Ma-low, in the amount of $31,377.30. B & G seeks to setoff from these amounts. B & G further proposes that the Court find that Fordson is indebted to it in the remaining amount of $38,658.34 and allow it to file its unsecured claim against the estate in that amount.

Prior to resolving this matter in terms of specific dollar amounts, certain legal issues must be addressed.

II.

A. Amendment of Affirmative Defenses:

Paragraph two of B & G’s first answer, filed on January 13, 1982, provided that at the time of termination of the contract, Fordson was owed $15,802.00 under contract P240, $30,047.21 under contract P246, and $75,427.28 for extras. On July 6, 1982, B & G, with the permission of the Court, amended its answer to provide that the amounts previously listed as owed under contracts P240 and P246 were in fact the value of work remaining to be done to complete the contracts.

Fordson asserts that statements contained in B & G’s first answer filed on January 13, 1982 constitute judicial admissions. The Court disagrees.

Judicial admissions are formal admissions in the pleadings which have the effect of withdrawing a fact from issue and dispensing wholly with the need for proof of the fact. Polk v. Missouri-Kansas-Texas Railway Company, 341 Mo. 1213, 111 S.W.2d 138 (1937); Sebree v. Rosen, 393 S.W.2d 590 (1965); see generally, McCormick’s on Evidence, ¶ 262 (2d ed. 1972). If pleadings are effective pleadings in the ease, they have the standing of judicial admissions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
25 B.R. 506, 1982 Bankr. LEXIS 5339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dery-v-general-motors-corp-in-re-fordson-engineering-corp-mieb-1982.