1616 Reminc Ltd. Partnership v. Atchison & Keller Co. (In Re 1616 Reminc Ltd. Partnership)

14 B.R. 484, 1981 Bankr. LEXIS 2829
CourtUnited States Bankruptcy Court, E.D. Virginia
DecidedOctober 7, 1981
Docket17-13739
StatusPublished
Cited by2 cases

This text of 14 B.R. 484 (1616 Reminc Ltd. Partnership v. Atchison & Keller Co. (In Re 1616 Reminc Ltd. Partnership)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
1616 Reminc Ltd. Partnership v. Atchison & Keller Co. (In Re 1616 Reminc Ltd. Partnership), 14 B.R. 484, 1981 Bankr. LEXIS 2829 (Va. 1981).

Opinion

MEMORANDUM OPINION

MARTIN V. B. BOSTETTER, Jr., Bankruptcy Judge.

This matter came on for trial on the Demand for Affirmative Relief by 1616 Reminc Limited Partnership (“Reminc”) against Atchison & Keller Company (“At-chison & Keller”), Atchison & Keller, Inc., Roland Kinser, Tony Yaksh and Peerless Insurance Company (“Peerless”). At the conclusion of Reminc’s case, after three days of trial, the Court granted the defendants’ Motion for Directed Verdict. On appeal, the district court remanded the matter to this Court for the taking of additional evidence. The Court permitted the plaintiff, in its discretion, to reopen its case and heard evidence given by the defendants.

Reminc, a Virginia limited partnership, is a debtor-in-possession in a Chapter XII proceeding under the Bankruptcy Act presently before this Court. The partnership’s principal asset is an office building located at 1616 North Fort Myer Drive, Arlington, Virginia, which is commonly referred to as the “Xerox Building”. Atchison & Keller is a joint venture comprised of Atchison & Keller, Inc., Ronald E. Kinser and Tony Yaksh.

On July 11, 1973, Atchison & Keller entered into a subcontract with CITCON Corporation, the general contractor with whom Reminc had contracted for the construction of the Xerox Building to perform the mechanical work on the Xerox Building, including the fabrication and installation of a heating, ventilating and air conditioning system (“HVAC”). This work was to be in accordance with the contract plans drawn up by the architect (Robert Calhoun Smith) and the project engineer (Syska & Hennessy). In connection with this contractual obligation, Atchison & Keller entered into a performance and payment bond with Peerless in the amount of $1,345,000.00 to indemnify against loss or damage directly arising by reason of its failure to faithfully perform the subcontract.

Pursuant to its subcontract with CIT-CON, Atchison & Keller further subcontracted with various contractors and suppliers in order to meet its obligations, including Mitco Corporation which supplied Atchi-son & Keller with a variable air volume valve assembly and electric reheat units manufactured by ITE Corporation. Included in the installation of the HVAC system were 836 of the ITE electric reheat units. An occupancy permit was thereafter issued to Reminc on December 2, 1974 authorizing that a portion of the Xerox Building could be occupied by tenants. It appears, however, that the Xerox Corporation (“Xerox”) became a tenant of the building prior thereto in August of 1974, and occupied 180,000 square feet of space out of a total of 290,-000 square feet.

The building, to the apparent dissatisfaction of Xerox, suffered from numerous con *487 struction defects. These defects included leakage problems, elevator deficiencies and control problems with the HVAC system. Xerox, the principal tenant, complained of a lack of adequate air conditioning and a lack of heat as the seasons changed during the winter of 1974-1975.

The subcontract in question specified that Atchison & Keller supply and install a Variable Air Volume Valve Assembly or “VAV” unit. Included in the VAV unit is a “Mit-co” mixer valve, sound insulation lining, adjusting controls and an ITE electric reheat unit.

The VAV unit was designed by Mitco Corporation, one of four designated suppliers approved by the architect and project engineer. The Mitco mixer valve and ITE reheat unit were supplied by Mitco as part of the VAV unit. Design and shop drawings for these units were submitted to the architect and project engineer for their inspection, review and approval prior to the manufacture and installation of the VAV units.

A central air shaft, not constructed by Atchison & Keller, was to deliver air to the appropriate floor of the building where it would flow through a sheet-metal ductwork system. The air passed through the VAV unit to be either heated or cooled prior to entering individual rooms through floor or ceiling diffusers. The record shows that the air shaft was improperly constructed creating a lack of sufficient air flow. The record reveals also that if insufficient air passed through the VAV unit (j. e., the air pressure was low in the central shaft) the ■ diffusion process could be disturbed to the extent of causing the air in the system to “dump”. This dumping effect, caused by poor air distribution over the heating elements (reheat coils) of the reheat units, resulted in hot spots developing on the coils.

To prevent irreparable damage, the ITE reheat units were equipped with two principal safety devices that would cut off the reheat coils — automatic reset and manual reset. The automatic reset consisted of a tube strung across the face of the reheat coils in the center of the air flow. The manual reset consisted of a small surface-mounted disc located in a corner of the unit.

The record indicated that the ITE reheat unit, once shut off under the automatic reset, would return to service on its own after the unit had cooled down sufficiently. This, apparently, did not occur if the manual reset was triggered first, however. In this instance, maintenance personnel would have to physically reset the unit in order to bring it back into service.

Early efforts undertaken to resolve this problem were unsuccessful thereby necessitating the institution of remedial work. Included in this remedial work was the replacement of the 836 ITE reheat units.

Reminc asserts its claims in its own right and as assignee of CITCON on the subcontract, the joint venture agreement and the performance bond.

The Court first addresses the issue raised by Reminc under the Dual Obligee Performance and Payment Bond regarding the liability of Peerless, as surety, if any, under this bond.

Peerless relies upon two express conditions precedent to which all parties under the bond affixed their signatures and accepted. Paragraph Three states:

“3. That the obligees [Reminc] or any of them, shall notify the Surety by registered letter, addressed and mailed to it at its Home Office, of any breach of said contract within ninety (90) days after such breach shall have come to the knowledge of the Obligees or any of them, or the Architect [Robert Calhoun Smith] or Engineer [Syska & Hennessy].”

Peerless acknowledges that Reminc is in compliance with the requirement that it allege performance of conditions precedent, Fed.R.Civ.Proc. 9(c), but that it has failed to prove performance. The assertion is made by Peerless that Reminc failed to notify it either within the period prescribed in paragraph three or in the prescribed manner although Reminc had knowledge of an alleged breach.

A review of the record reveals that Rem-inc was made aware of major problems *488 with the HVAC system in late 1974 and early 1975. For instance, Theodore B. Gould, the General Partner for Reminc, identified a letter from CITCON to Ranger Construction Company 1 which placed Ranger on notice that Atchison & Keller had not completed the mechanical system in accordance with the plans and specifications and which also required the institution of remedial repairs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
14 B.R. 484, 1981 Bankr. LEXIS 2829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/1616-reminc-ltd-partnership-v-atchison-keller-co-in-re-1616-reminc-vaeb-1981.