Dyker Bldg. Co., Inc. v. United States, to Use of Parreco United States, to Use of Parreco v. Dyker Bldg. Co., Inc.

182 F.2d 85, 86 U.S. App. D.C. 297, 1950 U.S. App. LEXIS 2752
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 27, 1950
Docket10191_1
StatusPublished
Cited by31 cases

This text of 182 F.2d 85 (Dyker Bldg. Co., Inc. v. United States, to Use of Parreco United States, to Use of Parreco v. Dyker Bldg. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyker Bldg. Co., Inc. v. United States, to Use of Parreco United States, to Use of Parreco v. Dyker Bldg. Co., Inc., 182 F.2d 85, 86 U.S. App. D.C. 297, 1950 U.S. App. LEXIS 2752 (D.C. Cir. 1950).

Opinion

FAPIY, Circuit Judge.

Complaint was filed in the United States District Court for the District of Columbia in the name of the United States to the Use of Theodore Parreco and others against the Dyker Building Company and the United States Fidelity and Guaranty Company. Recovery was sought of $30,308.04 alleged to be due under a subcontract on a housing project for which the Building Company was the principal contractor with the United States. The United States Fidelity and Guaranty Company was surety on the bond of the contractor to protect persons supplying ' labor and materials. The subcontract of the Parrecos was for labor and materials for excavations, fillings, gradings, stripping of top soil, furnishing of borrow fill, and kindred work. Their action was met by a counterclaim of the Building Company for $9,673.84, alleging overpayment of that amount.

On May 31, 1944 the District Court, on motion of the use plaintiffs consented to by the Building Company referred the action to a special master to take evidence and to report the same with his findings of fact and conclusions of law. Four years later,, on June 1, 1948, he so reported to the court. On January 14, 1949,' his findings of fact and conclusions of law were sustained over-various objections of the parties. Judgment was accordingly given for the use plaintiffs in the sum of $13,765,96, with interest at the rate of six percentum per annum from October 8, 1943, as to the Building Company, and from April 22, 1944, as to the surety company. The judgment included costs, except that the costs of reference were ordered to be divided. Both sides appealed.

We discuss first the status of the findings of the special master. Rule 53(e) (2) of the Federal Rules of Civil Procedure, 28 U.S.C.A., provides: “* * * In Non-Jury Actions. In an action to be tried without a jury the court shall accept the master’s findings of fact unless clearly erroneous. * • * * ”

This is like the rule of the cases as laid down in Camden v. Stuart, 1891, 144 U.S. 104, 118, 12 S.Ct. 585, 590, 36 L.Ed. 363. The circumstances there were somewhat-similar to those in the case at bar. The-Court said: “In cases of this kind, referred to a master to state an account, depending, as they do, upon an examination of books, upon the oral testimony of witnesses, and' jperhaps, as in this case, upon the opinions-of an expert, ‘-his conclusions have every reasonable presumption in their favor, and are not to be set aside or modified unless, there clearly appears to have been error or mistake on his part’ ”, citing Tilghman v.. *87 Proctor, 1887, 125 U.S. 136, 8 S.Ct. 899, 31 L.Ed. 664, and other cases.

See, also, Crawford v. Neal, 1891, 144 U.S. 585, 596, 12 S.Ct. 759, 36 L.Ed. 552.

Rule 53(e) (2) is in terms designed to govern the conduct of the trial court. This is pointed out in Adams County v. Northern Pac. Ry. Co., 9 Cir., 1940, 115 F.2d 768, 779, in the following context, “This rule, of course, regulates the conduct of the trial judge and not that of the appellate court.” But Rule 52 provides in part, “ * * * The findings of a master, to the extent that the court adopts them, shall he considered as the findings of the court.” The same Rule also prqvides “Findings of fact shall not be set aside unless clearly erroneous, * * * We therefore may not properly set aside a judgment which rests upon findings of fact made by a special master and adopted by the trial court unless at least such findings are dearly erroneous.

1. The Amount Found Due the Use Plaintiffs for Stripping of Top Soil.

The special master awarded $16,416 to the use plaintiffs for the removal or stripping of 27,350 cubic yards of top soil at the contract rate. There is no serious dispute as to the quantity actually stripped. The Building Company contends, however, first that the contract limited the quantity for which payment should be made to approximately the amount required for landscaping, because, it says, the contract limited to landscape work the uses to which the removed top soil was to be put. It contends further that only about 50% of the total graded area contained top soil and that this also constituted a limitation which brought the amount stripped well under the quantity found by the master. A figure of approximately 15,051 cubic yards is reached by the Building Company. It relies for support of its first contention upon Smoot v. United States, 1914, 237 U.S. 38, 35 S.Ct. 540, 59 L.Ed. 829; Maryland Dredging & Contracting Co. v. Coplay Cement Mfg. Co., D.C. 1920, 265 F. 842, 844; and Atwater & Co. v. Terminal Coal Corp., D.C.1940, 32 F. Supp. 178, 181. These cases are to the effect that where a contract states an approximate quantity to be supplied but it appears that actual need is the true measurement intended, recovery is to be based on the amount needed. This principle is not applicable to the present case. The specifications provide that top soil over areas to be occupied by any buildings, streets, and other named areas should be removed to an average depth of six inches and stacked on the site. The special master stated: “The specifications required that the existing top soil, in certain specified areas was to be stripped to a certain thickness. No quantity limitation is mentioned in the contract between the parties or in the contract plans and specifications. It required only that it must exist in the specified positions.”

He answered the Building Company’s contention for a limitation of the compensable quantity to the amount needed for reuse by pointing out that the provisions relied upon to support this position “apply only to use after stripping and do not limit the volume to be stripped,” for which latter volume payment should be made. This was a proper interpretation of the contract; under it the cases relied upon by the appellants are not applicable.

As to the facts regarding quantity the amount computed by the engineer, 27,360 cubic yards removed and stacked, 1 is not clearly erroneous. No convincing evidence refutes this computation.

*88 We have noted the contention of the Building Company that verbal instructions were given to limit the stripping of top soil to 16,000 cubic yards. This was a sharply disputed factual issue. The special master during a rather full review of the conflicting evidence said, “If the defendant desired to make this modification to the contract * * * they were negligent in not making some definite arrangements which would have made the plaintiff responsible for stripping only 16,000 cubic yards of top soil.”

Further, “defendant clearly intended that no change orders of any kind would be recognized by them”, unless in . writing. The resolution of the special master of this disputed issue is well supported by evidence and we do not disturb it.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Godette v. Estate of Cox
592 A.2d 1028 (District of Columbia Court of Appeals, 1991)
Blake Construction Co. v. C. J. Coakley Co.
431 A.2d 569 (District of Columbia Court of Appeals, 1981)
Edmund J. Flynn Co. v. LaVay
431 A.2d 543 (District of Columbia Court of Appeals, 1981)
Devex Corp. v. General Motors Corp.
494 F. Supp. 1369 (D. Delaware, 1980)
EF Hutton & Co., Inc. v. Burkholder
413 F. Supp. 852 (District of Columbia, 1976)
Rosendorf v. Toomey
349 A.2d 694 (District of Columbia Court of Appeals, 1975)
Noel v. O'BRIEN
270 A.2d 350 (District of Columbia Court of Appeals, 1970)
Sankin v. 5410 Connecticut Avenue Corporation
281 F. Supp. 524 (District of Columbia, 1968)
Frances Uhlhorn v. U. S. Gypsum Company
366 F.2d 211 (Eighth Circuit, 1966)
Nichols v. Elkins
408 P.2d 34 (Court of Appeals of Arizona, 1965)
McSmith v. McSmith
387 P.2d 454 (Alaska Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
182 F.2d 85, 86 U.S. App. D.C. 297, 1950 U.S. App. LEXIS 2752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyker-bldg-co-inc-v-united-states-to-use-of-parreco-united-states-to-cadc-1950.