MRG Construction Corp. v. CBS Service, LLC

CourtDistrict Court, N.D. Indiana
DecidedMay 8, 2024
Docket3:23-cv-00241
StatusUnknown

This text of MRG Construction Corp. v. CBS Service, LLC (MRG Construction Corp. v. CBS Service, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MRG Construction Corp. v. CBS Service, LLC, (N.D. Ind. 2024).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF INDIANA SOUTH BEND DIVISION

MRG CONSTRUCTION CORP.,

Plaintiff,

v. CASE NO. 3:23-CV-241-MGG

CBS Service, LLC

Defendant.

OPINION AND ORDER Pending before the Court is Plaintiff’s motion for partial summary judgment. [DE 21].1 For the reasons discussed below, the motion is denied. I. Background A. Material Facts2 On April 27, 2022, Plaintiff MRG Construction Corp., as general contractor, and Defendant CBS Service, LLC, as subcontractor, entered into an agreement (“the

1 The parties consented to have a magistrate judge hear and decide the case, and, on June 5, 2023, the matter was referred to the undersigned for all further proceedings and the entry of judgment. [DE 11]. 2 For purposes of Plaintiff’s motion, the Court considers the undisputed facts as shown by the “Statement Of Undisputed Material Facts In Support Of Plaintiff’s Motion For Summary Judgment” (hereinafter “Plaintiff’s Fact Statement”) [DE 21-2], and the “Response To Plaintiff’s Statement Of Material Facts” (hereafter “Response to Plaintiff’s Fact Statement”) [DE 25]. In addition, the Court considers the facts set forth in Defendant’s Additional Material Facts portion of its Response to Plaintiff’s Fact Statement [DE 25 at 5-10]. See N.D. Ind. L.R. 56-1(b). Because the evidence, including all reasonable inferences, must be considered in a light most favorable to the nonmoving party, Bay v. Cassens Transport Co., 212 F.3d 969, 972 (7th Cir. 2000), the Court will consider Defendant’s additional material facts even if they are disputed. The Court notes, however, that Plaintiff did not file any reply to Defendant’s Additional Material Facts. See N.D. Ind. L.R. 56-1(c)(2). As a result, Defendant’s Additional Material Facts could also be treated as undisputed for present purposes. See Fed. R. Civ. P. 56(e) (“If a party ... fails to properly address another party’s assertion of fact as required by Rule 56(c), the court may ... consider the fact undisputed for purposes of the motion ....”). Subcontract”) by which CBS agreed to furnish and install all necessary electrical equipment for MRG’s Range USA project in Mishawaka, Indiana (“the Project”). See

[DE 24-1 at 1 (Smith Decl. ¶ 4); DE 4 at 6-23 (Subcontract)]. When CBS bid on the Project, MRG represented that construction would begin in late April 2022; the electrical work would be completed by October 2022; and construction on the whole Project would be completed by the Fall of 2022. [Id. at 2 (Smith Decl. ¶ 7)]. The only timing provision in the Subcontract itself, however, is paragraph 3.1, which states that CBS’s work “shall be commenced not later than 4/26/22, and, subject to authorized

adjustments, shall be substantially completed as per schedule approved by Contractor, Architect, and Owner.” [DE 4 at 7 (Subcontract, ¶ 3.1)]. Despite the reference to a schedule in paragraph 3.1, no schedule for the Project was included in the Subcontract. [DE 24-1 at 2 (Smith Decl. ¶ 10)]. Instead, after the parties signed the Subcontract, MRG provided CBS with an Adjusted Schedule for the

Project, which outlined the start dates and finish dates for all work to be performed on the Project. [Id. (Smith Decl. ¶ 11); see id. at 25-28 (Def. Ex. 2, Adjusted Schedule)]. Pursuant to the Adjusted Schedule, structural work on the Project (the “Structural Work”3) was to begin on May 16, 2022, and be completed by June 16, 2022. [Id. at 3 (Smith Decl. ¶ 15)]. Work to complete the building structure for the Project (the

“Building Work”4) was to begin once the Structural Work was completed and was to be

3 Structural Work included digging foundations, pouring footings, installing the building foundation, and roughing in underground electrical and plumbing. [DE 24-1 at 3 (Smith Decl. ¶ 15)]. 4 Building Work included installing external and internal masonry walls and structural steel in the building. [DE 24-1 at 3 (Smith Decl. ¶ 17)]. finished on August 30, 2022. [Id. (Smith Decl. ¶¶ 17, 18)]. CBS could not perform the rough in electrical work5 or the final trim electrical work6 until after the Building Work

was completed. [Id. (Smith Decl. ¶ 19)]. Accordingly, the Adjusted Schedule set the start date for CBS’s rough in electrical work on August 31, 2022, with that work to be completed about October 4, 2022. It provided for the final trim electrical work to begin on October 5, 2022, and completed on October 17, 2022. [Id. at 3-4 (Smith Decl. ¶¶ 20, 23)]. The Adjusted Schedule provided that the Project was to be fully completed, closed out, and turned over to the owner on November 4, 2022. [Id. at 3 (Smith Decl. ¶ 14)].

CBS completed the structural related electrical work “per the [Adjusted] [S]chedule,” which would have been sometime between May 16, 2022, and June 16, 2022. [Id. at 3 (Smith Decl. ¶¶ 15-16)]. But CBS was not able to begin the remainder of its electrical work on the Project because the Building Work was delayed beyond the stated August 30, 2022, completion date. [Id. at 3-4 (Smith Decl. ¶¶ 20-27)]. In fact, the Building

Work was still not completed in November 2022, when MRG prepared and delivered a New Schedule to CBS. [Id. at 4 (Smith Decl. ¶ 28); see id. at 29-36 (Def. Ex. 3, New Schedule)]. Under the New Schedule, the Building Work was to be completed on December 1, 2022, while CBS was to commence and complete its rough in electrical work in December 2022 and its final trim electrical work in early January 2023. [Id.

(Smith Decl. ¶¶ 30-31)].

5 Rough in electrical work includes laying electrical lines, mounting junction boxes, pulling wiring through wall studs, grounding, and setting up the electrical panel. [DE 24-1 at 3 (Smith Decl. ¶ 19)]. 6 Final trim electrical work includes installing light fixtures, light switches, and receptacles. [DE 24-1 at 3 (Smith Decl. ¶ 19)]. In December 2022, CBS informed MRG that it did not have the ability or the manpower to complete the remainder of the electrical work pursuant to the New

Schedule, because its electricians were occupied on other jobs in December 2022, and CBS said it could not pull them off those other scheduled jobs, which were on schedule, to accommodate the delays in the Project. [Id. at 5 (Smith Decl. ¶ 33)]. Neither party provides the Court with sufficient details concerning what happened next. MRG asserts that CBS “simply decided that it had better places to utilize its electricians and walked off the job leaving MRG to fend for itself.” [DE 21-1 at 4]. That assertion is somewhat

misleading, however, in light of MRG’s own undisputed fact statement, which states in multiple paragraphs that CBS’s electricians were all committed on other jobs and CBS did not have the additional manpower for the revised dates in the New Schedule. See [DE 21-2 (Plaintiff’s Fact Statement, ¶¶ 4, 10, 11, 12)]. In other words, it appears that what MRG means to say is that CBS declined to break any of its other contractual

commitments to accommodate MRG’s delayed scheduling. MRG also contends that “CBS never requested an extension nor was it provided an extension of time to complete the work due to an alleged delay in [the] project.” [DE 21-2 (Plaintiff’s Fact Statement, ¶ 9)]. But the citation MRG provides for this purportedly “undisputed” fact (which CBS denies, see [DE 25 at 4 (Response to

Plaintiff’s Fact Statement, ¶ 9)], only shows that an extension was not granted; the cited evidence says nothing about whether CBS ever requested an extension.7 Neither party has submitted sufficient evidence for the Court to determine whether CBS ever

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Blomberg v. Service Corp. International
639 F.3d 761 (Seventh Circuit, 2011)
Moore v. Vital Products, Inc.
641 F.3d 253 (Seventh Circuit, 2011)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)
Dennis R. Bay v. Cassens Transport Company
212 F.3d 969 (Seventh Circuit, 2000)
John Lawson, Sr. v. Csx Transportation, Incorporated
245 F.3d 916 (Seventh Circuit, 2001)
John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.
432 N.W.2d 584 (Wisconsin Supreme Court, 1988)
JJ Brown Co., Inc. v. JL Simmons Co., Inc.
118 N.E.2d 781 (Appellate Court of Illinois, 1954)
Fraternal Order of Police Lodge No. 52 v. Civil City of Elkhart
551 N.E.2d 469 (Indiana Court of Appeals, 1990)
Epperly v. Johnson
734 N.E.2d 1066 (Indiana Court of Appeals, 2000)
Krieg v. Hieber
802 N.E.2d 938 (Indiana Court of Appeals, 2004)
Patent Scaffolding Co. v. William Simpson Construction Co.
256 Cal. App. 2d 506 (California Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
MRG Construction Corp. v. CBS Service, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mrg-construction-corp-v-cbs-service-llc-innd-2024.